| Certification Vendor: | Adobe |
|---|---|
| Exam Name: | Adobe Workfront Project Manager Certified Professional |
| Exam Number: | AD0-E911 |
| Exam Duration: | 100 minutes |
| Passing Score: | 66% (33 out of 50) |
| Exam Format: | Scenario-based, Drag and drop, Multiple choice |
| Available Languages: | English |
| Certificate Validity Period: | 2 years |
| Real Exam Qty: | 50 |
| Related Certifications: | Adobe Workfront Certified Specialist |
| Exam Price: | $125 (Global), $95 (India) |
| Recommended Training: | Adobe Workfront Project Manager Learning Path Adobe Workfront Documentation |
| Exam Registration: | Adobe Certification Portal |
| Sample Questions: | Adobe AD0-E911 Sample Questions |
| Exam Way: | Online proctored exam (remote, monitored via camera and microphone) |
| Pre Condition: | Recommended 6–12 months of hands-on experience using Adobe Workfront; no mandatory prerequisite exams |
| Official Syllabus URL: | https://certification.adobe.com/certification/project-manager-certified-professional/1320 |
我們PDFExamDumps Adobe的AD0-E911的考試考古題是經過實踐檢驗的,我們可以提供基於廣泛的研究和現實世界的經驗,我們PDFExamDumps擁有超過計畫0年的IT認證經驗,AD0-E911考試培訓,包括問題和答案。在互聯網上,你可以找到各種培訓工具,準備自己的AD0-E911考試認證,PDFExamDumps的AD0-E911考試試題及答案是最好的培訓資料,我們提供了最全面的驗證問題及答案,讓你得到一年的免費更新期。
| 主題 | 簡介 |
|---|---|
| 主題 1 |
|
| 主題 2 |
|
| 主題 3 |
|
問題 #56
A company has decided that all projects for the year need to be created from templates and staffed in the following quarter. The projects will need to remain in a backlog until the team has capacity to work on them. There has been confusion previously because the team used Planning status for all work not started.
What should the project manager do to help the team see the difference between work in the backlog versus work that is now being planned?
答案:C
解題說明:
In Workfront, creating a custom status specifically for "Backlog" allows the team to differentiate between work that is pending capacity and work that is actively being planned. This prevents confusion and allows for better project tracking, ensuring that tasks move smoothly from backlog to the planning phase when appropriate.
問題 #57
A project manager is assigned to a new Workfront request. The requestor has asked that three team members receive notifications when any updates are posted to the request.
How should the project manager keep these team members apprised of updates?
答案:A
解題說明:
In Adobe Workfront, team members can be subscribed to a request so that they receive updates whenever changes or comments are made. This ensures they stay informed of any progress or issues. Adding a request to favorites only bookmarks it for easy access, but does not trigger automatic notifications. Making multiple primary contacts is not an efficient way to handle notifications.
問題 #58
A project manager has been asked to create a report showing the planned completion date for all the project manager's projects. The report must show results in a calendar view and all entries should be purple. What steps should the project manager take to create this view?
答案:C
解題說明:
To create a report that meets the specifications, the project manager should create a new report from the Reports page, filter by Project Owner ID, and add a column for Planned Completion Date. Setting the default view to Calendar View and using the Color ID field to assign the color purple ensures that all the manager's projects are visible in the desired format and color.
問題 #59
The last 5 tasks in a project need to happen within 10 days of the end of the project.
Which Task Constraint should the project manager use to configure this timeline without setting specific dates?
答案:C
解題說明:
In Workfront, the "As Late As Possible" task constraint ensures that tasks are scheduled as close to the project's end date as possible. This is useful when specific start dates are not necessary, but tasks need to happen near the end of the project timeline. This constraint allows for flexibility while still ensuring that the tasks are completed within the required time frame.
問題 #60
Which project status will default the automatic Project Condition to "On Time"?
答案:C
解題說明:
In Adobe Workfront, the automatic project Condition is controlled by the project's Condition Type when it is set to Progress Status. Adobe documentation explains that Project Condition is a visual indicator of how a project is progressing and is automatically calculated from the project's Progress Status, which is based on task progress and project dates. The documentation also states that projects in certain statuses are always marked On Target, regardless of task dates or progress. These statuses include Idea, Requested, Approved, and Rejected. In Workfront terminology, the Progress Status On Time maps to the project Condition On Target. Among the answer choices, only Idea is listed by Adobe as a status that always defaults the automatic project Condition to On Target/On Time behavior. Planning and On Hold do not have this same default rule; On Hold projects can still show as At Risk or In Trouble. Therefore, the correct answer is A. Idea.
問題 #61
......