PRINCE2 PRINCE2-7-Practitioner Exam Syllabus Topics:

SectionWeightObjectives
People & Project Context Integration20%- Sustainability, digital & tailoring
  • 1. Tailoring PRINCE2 to project context
    • 2. Digital and data management
      • 3. Sustainability and ESG alignment
        - People management and collaboration
        • 1. Communication and stakeholder engagement
          • 2. Roles and responsibilities
            PRINCE2 Principles12%- Apply the seven PRINCE2 Principles in context
            • 1. Tailor to suit the project environment
              • 2. Manage by stages
                • 3. Continued business justification
                  • 4. Define roles and responsibilities
                    • 5. Manage by exception
                      • 6. Focus on products
                        • 7. Learn from experience
                          PRINCE2 Processes28%- Apply the seven Processes
                          • 1. Closing a Project
                            • 2. Managing Stage Boundaries
                              • 3. Controlling a Stage
                                • 4. Initiating a Project
                                  • 5. Directing a Project
                                    • 6. Starting a Project
                                      • 7. Managing Product Delivery
                                        PRINCE2 Practices40%- Apply and tailor the seven Practices
                                        • 1. Quality
                                          • 2. Organisation
                                            • 3. Business Case
                                              • 4. Risk
                                                • 5. Progress
                                                  • 6. Change
                                                    • 7. Plans

                                                      >> PRINCE2 PRINCE2-7-Practitioner無料ダウンロード <<

                                                      最短ルートのPRINCE2-7-Practitioner 合格への扉を開こう

                                                      PRINCE2-7-Practitionerテスト資料は、ユーザーが勉強するたびに合理的な配置であり、可能な限りユーザーが最新のPRINCE2-7-Practitioner試験トレントを長期間使用しないようにします。 。ユーザーが知識を習得する必要があるたびにPRINCE2-7-Practitioner練習教材は、ユーザーがこの期間に学習タスクを完了することができる限り、PRINCE2-7-Practitionerテスト教材は自動的に学習システムを終了し、ユーザーに休憩を取るよう警告します。次の学習期間に備えてください。

                                                      PRINCE2 Project Management Practitioner (Version 7) 認定 PRINCE2-7-Practitioner 試験問題 (Q52-Q57):

                                                      質問 # 52
                                                      During stage 1, the City Council purchasing team must prepare the contract that will govern BuildyBrick's later design and construction work. The project manager agrees with the purchasing team the products, time and cost for this work package.
                                                      Which practice is being applied through the 'controlling a stage' process?

                                                      正解:C

                                                      解説:
                                                      The correct answer is C - Plans . PRINCE2 applies the plans practice throughout project delivery, including when individual work packages are defined and authorized. A work package establishes what products are to be delivered and the constraints and control arrangements governing their production.
                                                      In this scenario, the project manager agrees with the City Council purchasing team the products, time, and cost associated with preparing the contract. These are core planning elements. The work must be defined sufficiently so that the team understands what it is expected to produce, when it should be completed, what resources or expenditure are available, and the limits within which it is authorized to operate.
                                                      Option A, business case, concerns the project's continuing investment justification and does not principally govern the detailed definition of products, time, and cost for a delegated work package. Option B, organization, defines roles, responsibilities, relationships, and the project-management structure. Although the relationship between project manager and team manager is relevant, the information explicitly being agreed here concerns planning. Option D, quality, would focus on product specifications, quality methods, acceptance arrangements, and quality control rather than the overall product/time/cost definition.
                                                      The work package therefore demonstrates application of the plans practice within controlling a stage.
                                                      PRINCE2 7 reference topics: Plans practice; controlling a stage; work packages; products; estimates; time and cost; delegated planning and control.


                                                      質問 # 53
                                                      The Business Opportunities Director, acting as project executive, proposes that the Head of the Portfolio Office should perform business assurance and should also approve the viability of the business case and the achievability of the project plan.
                                                      Is this an appropriate application of the organization practice, and why?

                                                      正解:A

                                                      解説:
                                                      The correct answer is C . PRINCE2 distinguishes between accountability and assurance . Project assurance provides an independent assessment of whether the project is being conducted properly and whether the information presented to the project board is reliable. Assurance can therefore review the business case, examine the project plan, and provide confidence concerning viability and achievability.
                                                      However, assigning an assurance provider does not transfer the project executive's accountability. The project executive remains ultimately accountable for ensuring that the project continues to represent a worthwhile investment and that the business case remains valid. The project executive also chairs the project board and is responsible for balancing the business, user, and supplier interests.
                                                      Option A incorrectly assumes that delegation of assurance transfers accountability. PRINCE2 explicitly preserves accountability at the project board level. Option B similarly confuses independent review with ownership of the business case. Option D is also too restrictive: an appropriately independent portfolio-office function may perform project assurance if this arrangement is suitable and does not compromise the required independence.
                                                      The Head of Portfolio Office may therefore perform business-assurance work, but cannot assume the project executive's fundamental accountability for project justification.
                                                      PRINCE2 7 reference topics: Organization practice; project executive; project assurance; delegation versus accountability; business assurance; continued business justification.


                                                      質問 # 54
                                                      A high-level requirement that the design should be consistent with its surroundings was recorded during
                                                      'starting up a project'. During initiation, the project manager works with Council members, residents, retailers and BuildyBrick to clarify the required design characteristics and define measurable acceptance criteria.
                                                      Which management product should be updated with this information?

                                                      正解:C

                                                      解説:
                                                      The correct answer is A - Project product description . The project product description defines the project' s overall output and establishes the principal basis on which that output will ultimately be judged acceptable.
                                                      It includes the overall purpose, composition, quality expectations, acceptance criteria, and other characteristics necessary to determine whether the final project product is fit for its intended purpose.
                                                      The original statement that the design should be "consistent with its surroundings" is high level and inherently difficult to verify. During initiation, the project manager works with relevant stakeholders to translate that broad expectation into clearer design characteristics and measurable acceptance criteria . These details refine the definition of the overall project product and therefore belong in the project product description.
                                                      Option B is incorrect because a work package authorizes and controls specific work delegated to a team manager; it does not define the acceptance criteria for the entire project product. Option C, the product flow diagram, shows the sequence and dependencies involved in creating products rather than their acceptance requirements. Option D, the project plan, describes how and when the project's products will be delivered, but the overall acceptance definition belongs in the project product description.
                                                      This refinement also supports stakeholder alignment by turning an ambiguous requirement into objectively testable acceptance conditions.
                                                      PRINCE2 7 reference topics: Plans practice; project product description; quality expectations; acceptance criteria; starting up a project; initiating a project.


                                                      質問 # 55
                                                      Before a BuildyBrick subcontractor begins testing the utilities and systems, the proposed team plan and the commitment to deliver the testing work package must be agreed.
                                                      Which role agrees to carry out the work package in the 'managing product delivery' process?

                                                      正解:A

                                                      解説:
                                                      The correct answer is B - Team manager . Within the managing product delivery process, the team manager is responsible for accepting responsibility for an authorized work package and committing the delivery team to producing the specified products within the agreed constraints.
                                                      Before work begins, the team manager reviews the work package with the project manager to confirm that its requirements are understood and achievable. This includes examining the products to be delivered, product descriptions, quality requirements, tolerances, interfaces, constraints, reporting arrangements, risks, issues, and available resources. Where a team plan is required, it must also provide a credible basis for carrying out and controlling the specialist work. Acceptance therefore represents an explicit commitment by the team manager to deliver the work package.
                                                      Option A is incorrect because the project manager authorizes the work package but does not accept it on behalf of the delivery team. Option C is incorrect because the senior supplier represents the supplier interest on the project board and provides governance and specialist oversight rather than accepting individual work packages. Option D provides administrative or specialist project support but does not assume responsibility for specialist delivery.
                                                      PRINCE2 7 reference topics: Managing product delivery; accept a work package; team manager responsibilities; team plan; work-package authorization and acceptance.


                                                      質問 # 56
                                                      While preparing the project plan during initiation, the project manager proposes that stage 2 should end at the Council's financial year-end. This would allow the decision on funding for stage 3 to coincide with the Council's annual budget process.
                                                      Is this an appropriate application of the 'manage by stages' principle, and why?

                                                      正解:A


                                                      質問 # 57
                                                      ......