Wenn Sie ZertPruefung wählen, versprechen wir Ihnen eine 100%-Pass-Garantie zur Oracle 1Z0-1075-26 Zertifizierungsprüfung. Sonst erstatteten wir Ihnen Ihre an uns geleisteten Zahlung.
| Section | Objectives |
|---|---|
| Work Definition and Work Execution | - Work order execution and control - Work definitions and structures |
| Shop Floor Management | - Production tracking and reporting - Work execution monitoring |
| Manufacturing Planning Integration | - Material and resource planning - Integration with supply chain planning |
| Manufacturing Cloud Fundamentals | - Manufacturing execution overview - Core Manufacturing concepts in Oracle Cloud |
| Quality and Costing in Manufacturing | - Manufacturing costing principles - Quality inspection integration |
| Manufacturing Configuration and Setup | - Setup of manufacturing parameters - Plant and resource configuration |
>> 1Z0-1075-26 Zertifikatsdemo <<
Die Prüfungsfragen und Antworten zur Oracle 1Z0-1075-26 Zertifizierungsprüfung von ZertPruefung wird von unserem Expertenteam nach ihren umfangreichen Kenntnissen und Erfahrungen berarbeitet. Sie können die Bedürfnisse der Kandidaten abdecken. Sie finden vielleicht in anderen Büchern oder auf anderen Websites auch die Oracle 1Z0-1075-26 Schulungsunterlagen. Aber die Schulungsunterlagen von ZertPruefung sind die umfassendste unter ihnen und zugleich kann Ihnen die beste Garantie geben. Bitte wählen Sie die Oracle 1Z0-1075-26 Prüfungsfragen und Antworten von ZertPruefung.
45. Frage
Which three statements are true about the main areas of Managerial Accounting?
Antwort: A,B,D
Begründung:
In Oracle Manufacturing Cloud and related financial applications, managerial accounting plays a significant role in tracking and managing costs across supply chain and manufacturing activities. The following is a breakdown of the correct statements:
Statement A: Receipt Accounting is the application that performs accrual accounting for all types of receipts - Receipt Accounting is a crucial module in Oracle Cloud that supports the tracking of costs and performs accruals related to receipts. This includes processes such as procurement receipts, interorganization transfers, and supplier shipments. This allows organizations to recognize and account for the expenses associated with these receipts.
Statement B: Landed Cost Management gives organizations financial visibility into their extended supply chain costs - Landed Cost Management is designed to capture additional costs that arise during the transportation, handling, and processing of goods. This includes costs like shipping, insurance, and customs duties. By including these in the overall cost, it provides a more comprehensive view of the actual costs of goods in the supply chain.
Statement D: Cost method can be defined with granularity down to individual items - In Oracle Manufacturing Cloud, costing methods can be assigned not only at the organization level but also at a granular level down to individual items. This provides flexibility in defining different costing strategies for different products depending on their nature, manufacturing process, or market conditions.
Incorrect Statements:
Statement C: Supply Chain Orchestration automatically selects the correct process based on user-defined Subledger Accounting rules when a supply creation is initiated - While Supply Chain Orchestration automates various supply chain processes, it does not select processes based on Subledger Accounting rules. The orchestration system is more focused on managing and coordinating supply chain processes rather than determining accounting rules.
46. Frage
Which three requirements are fulfilled by nonstandard work orders?
Antwort: A,B,C
Begründung:
Nonstandard work orders in Oracle Manufacturing Cloud are used for specialized tasks that do not follow typical production processes. The following are the main requirements fulfilled by nonstandard work orders:
Repair: Nonstandard work orders can be used for maintenance and repair tasks to fix or refurbish defective or damaged items.
Rework: These work orders are also used for rework processes, where a product needs to be reprocessed to meet quality standards or specifications.
Prototype: Nonstandard work orders can handle prototype production, where items are produced in small quantities for testing and development before mass production.
Rescheduling (A) is typically handled by standard work orders in the production schedule rather than through nonstandard work orders.
47. Frage
You are defining a standard operation for visual inspection. You want the completion of this standard operation to be reported in all work orders that reference it.
Which setup task must you perform to achieve this?
Antwort: C
Begründung:
In Oracle Manufacturing Cloud, when defining a standard operation such as visual inspection, marking it as a Count Point ensures that its completion will be tracked and reported for all work orders referencing it. A Count Point operation is one where progress must be explicitly recorded, allowing visibility into work order completion.
Selecting the Count Point check box ensures that this operation becomes a mandatory checkpoint where users must report completion in all related work orders. This is essential for operations like visual inspection, where reporting completion is critical to production quality.
48. Frage
You create a work order, in which some of the operations have components with the Push supply type. While reporting material consumption on the Report Material Transaction page, you want the Push components to default whenever the operator selects Show Components.
Which setup task must you perform in the Manage Plant Parameters section to achieve this?
Antwort: B
Begründung:
To ensure that Push components are automatically defaulted when reporting material consumption on the Report Material Transaction page, you must configure the system to use the Work Definition as the default source for transactions.
Setting Default Transaction Mode to Work Definition ensures that the system automatically pulls the component list and quantities as defined in the work order or work definition when operators perform material transactions. This setting streamlines the material consumption process for Push supply type components.
49. Frage
During a Manufacturing Cloud implementation, a Production Supervisor wants to close the work orders for the previous month and make sure that they include the correct cost.
What must they do to achieve this?
Antwort: D
Begründung:
To ensure that work orders for the previous month are closed with the correct costs, the Production Supervisor must:
Include all costs and variances in the work orders before closing them. This ensures that the work orders reflect the true cost of production, including any deviations from the expected costs. However, if there are work orders that are still in progress or expected to receive updates (such as material or labor transactions), those work orders should not be closed until all costs are finalized.
Incorrect options:
A: Excluding cost variances would result in inaccurate costing.
B: All costs, including variances, must be included before closing.
D: Costs cannot be updated after the work order is closed, so all updates must occur before closing the work order.
50. Frage
......
Wenn Sie an der Oracle 1Z0-1075-26 Zertifizierungsprüfung teilnehmen wollen, sind die 1Z0-1075-26 dumps von ZertPruefung Ihr bestes Vorbereitungsgerät. Die Prüfungsfragen können Ihnen helfen,die 1Z0-1075-26 Prüfung mühlos zu bestehen. Und diese Prüfungsfragen sind sehr gut bewertet, mit denen Sie sich nicht um Ihre 1Z0-1075-26 Zertifizierung sorgen. Die dumps können alle Probleme lösen, auf die Sie sich vorbereiten müssen. Und vor dem Kauf der Oracle 1Z0-1075-26 Prüfungsunterlagen können Sie das kostlose Demo als Probe herunterladen, damit Sie wissen können, ob die Prüfungsunterlagen für Sie geeignet sind.