BTW, DOWNLOAD part of Exams-boost CCM dumps from Cloud Storage: https://drive.google.com/open?id=1SDtNvRu0iLE2eJeTIG2Tm6aw8P5lcdoC
Remember that this is a crucial part of your career, and you must keep pace with the changing time to achieve something substantial in terms of a certification or a degree. So do avail yourself of this chance to get help from our exceptional Certified Case Manager Certification Exam (CCM) (CCM) dumps to grab the most competitive Certified Case Manager Certification Exam (CCM) (CCM) certificate.
| Section | Weight | Objectives |
|---|---|---|
| Ethical, Legal, and Practice Standards | 15% | - CCMC Code of Professional Conduct parameters - Regulatory compliance requirements and frameworks
|
| Psychosocial Concepts and Support Systems | 27% | - Behavioral health conditions and dependencies - Client dynamics and social determinants of health
|
| Care Delivery and Reimbursement Methods | 31% | - Reimbursement pathways and utilization management tools
|
| Quality and Outcomes Evaluation and Measurements | 18% | - Quality indicator metrics and performance tools
|
| Rehabilitation Concepts and Strategies | 9% | - Vocational and physical rehabilitation pathways
|
We promise that using CCM certification training materials of Exams-boost, you will pass CCM exam in your first try. If not or any problems in CCM certification training materials, we will refund fully. What's more, after you purchase our CCM Certification Training materials, Exams-boost will offer update service in one year.
NEW QUESTION # 116
Which one of the following statements is correct regarding the Provisional Sum under the FIDIC Red, Yellow, and Silver Books (edition 1999)?
Answer: B
Explanation:
Option B is correct. Under FIDIC contracts, the Contractor must provide proof of how the Provisional Sum has been expended when requested by the Engineer. This ensures transparency and proper use of funds allocated as Provisional Sums.
Option A is incorrect; Provisional Sums are often used based on instructions from the Engineer or Employer.
Option C is incorrect because Provisional Sums are precisely intended to be used, in whole or in part, according to Engineer's or Employer's instructions.
References:
FIDIC Red, Yellow, and Silver Books 1999 Edition, Sub-Clause 13.2 - Provisional Sums FIDIC Contract Manager Study Guide, Module on Payment Procedures
NEW QUESTION # 117
In the FIDIC Silver Book (both editions), the Notice of the Commencement Date will be informed by whom?
(1 correct response applies)
Answer: D
Explanation:
Comprehensive and Detailed Explanation:
In the FIDIC Silver Book (1999 and 2017 editions), which is tailored for EPC/Turnkey contracts, the Employer is responsible for notifying the Contractor of the Commencement Date (Sub-Clause 8.1). Unlike other FIDIC contracts where the Engineer might notify commencement, the Silver Book places more responsibility on the Employer due to the nature of the contract where the Contractor is largely responsible for design and execution with fewer Engineer roles.
The Employer's formal notification of the Commencement Date signals the official start of the Contractor's obligations and triggers timelines under the contract.
The Engineer or Resident Engineer typically does not issue such notice in the Silver Book framework.
References:
FIDIC Silver Book 1999 and 2017 Editions, Sub-Clause 8.1 - Commencement of Works FIDIC Contract Manager Study Guide, Module on Contract Formation and Execution
NEW QUESTION # 118
Both FIDIC Silver Book (SB) and Yellow Book (YB) (edition 1999) mention the Contractor scrutinising the Employer's Requirements. Which statement is correct?
Answer: D
Explanation:
mprehensive and Detailed Explanation:
Option D correctly captures the difference between Yellow and Silver Books (1999):
In the Yellow Book, the Contractor may raise concerns after contract close.
In the Silver Book, the Contractor must scrutinize and report on Employer's Requirements during the tender period, and after contract close this duty lapses.
Other options misunderstand timing or scope of scrutiny.
References:
FIDIC Yellow and Silver Books 1999 Editions, Sub-Clause 4.1 - Contractor's General Obligations FIDIC Contract Manager Study Guide, Module on Employer's Requirements and Scrutiny
NEW QUESTION # 119
When is the Employer obliged to return the Performance Security (PS) under the FIDIC Red Book (edition
1999)?
Answer: C
Explanation:
Under FIDIC Red Book 1999, the Performance Security (or Performance Guarantee) is held to ensure the Contractor's performance during the defects liability period. The security is typically released only after the Employer issues the Performance Certificate, which confirms the completion of defects liability obligations and that the Contractor has fulfilled the contract.
The contract commonly specifies a fixed period (often 21 days) within which the Employer must return the Performance Security after issuance of the Performance Certificate (Option D). The Taking-Over Certificate (Options A and C) marks substantial completion but does not end the Contractor's obligations for defects.
References:
FIDIC Red Book 1999, Sub-Clause 10.2 - Taking-Over Certificate
FIDIC Red Book 1999, Sub-Clause 10.4 - Performance Certificate
FIDIC Red Book 1999, Sub-Clause 10.5 - Release of Performance Security
FIDIC Contract Manager Study Guide, Module on Payment Procedures and Financial Management
NEW QUESTION # 120
(You are the Contract Manager for the Engineer in a highway project using FIDIC Red Book (edition 1999).
There is a Schedule of cost indexation included in the Contract. The project must be completed by 31 December of this year. If the Contractor fails to complete the Works by then, how will the adjustment of prices take place thereafter? (1 correct answer applies))
Answer: C
Explanation:
Under FIDIC Red Book 1999, Sub-Clause 13.8 [Adjustments for Changes in Cost] governs the mechanism for price adjustment based on cost indices. A critical provision applies when the Contractor fails to complete the Works within the Time for Completion.
In such circumstances, FIDIC protects the Employer against additional cost increases resulting from Contractor-caused delay. The clause explicitly states that the adjustment of prices after the contractual completion date shall be calculated using whichever index is more favourable to the Employer between:
* the indices applicable at the time the work is actually carried out (current index), and
* the indices applicable 49 days before the expiry of the Time for Completion.
This ensures that the Contractor does not benefit from inflation or cost escalation occurring after the contractual completion date if the delay is attributable to the Contractor. It reinforces the principle that the Contractor bears the financial consequences of delays under its responsibility.
Options A and B are incomplete because they ignore the comparison mechanism. Option D is incorrect because the rule is predefined and not subject to further agreement.
Thus, Option C correctly reflects the FIDIC contractual mechanism for price adjustment after delayed completion.
NEW QUESTION # 121
......
There are many benefits after you pass the CCM certification such as you can enter in the big company and double your wage. Our CCM study materials boost high passing rate and hit rate so that you needn’t worry that you can’t pass the test too much. We provide free tryout before the purchase to let you decide whether it is valuable or not by yourself. To further understand the merits and features of our CCM Practice Engine you could look at the introduction of our product in detail on our website.
CCM Valid Torrent: https://www.exams-boost.com/CCM-valid-materials.html
P.S. Free & New CCM dumps are available on Google Drive shared by Exams-boost: https://drive.google.com/open?id=1SDtNvRu0iLE2eJeTIG2Tm6aw8P5lcdoC