| Exam Name: | APICS Certified in Planning and Inventory Management (CPIM 8.0) Examination |
| Exam Number: | CPIM-8.0 |
| Related Certifications: | CSCP (Certified Supply Chain Professional) CLTD (Certified in Logistics, Transportation and Distribution) |
| Certificate Validity Period: | 5 years (renewal required via continuing education maintenance credits) |
| Real Exam Qty: | Approximately 150 multiple-choice questions per exam part |
| Passing Score: | Scaled score 300 (on a 200–350 scale) |
| Exam Price: | USD $495–$690 per exam (member vs non-member pricing varies by region) |
| Exam Duration: | 150–210 minutes per exam part (CPIM Part 1 and Part 2, varies by delivery update) |
| Exam Format: | Multiple-choice, Computer-based testing (CBT) |
| Available Languages: | English |
| Recommended Training: | ASCM CPIM Learning System ASCM Official Certification Training |
| Exam Registration: | Official CPIM Certification Page (ASCM) Pearson VUE ASCM Exam Registration |
| Sample Questions: | APICS CPIM-8.0 Sample Questions |
| Exam Way: | Computer-based exam via Pearson VUE test centers or online proctored exam |
| Pre Condition: | No formal prerequisites required; supply chain or operations knowledge recommended |
“如果放棄了,那比賽同時也就結束了。”這是來自安西教練的一句大家都熟知的名言。比賽是這樣,同樣考試也是這樣的。有很多人因為沒有充分的時間準備考試從而放棄了參加CPIM-8.0認證考試。但是,如果使用了好的資料,即使只有很短的時間來準備,你也完全可以以高分通過CPIM-8.0考試。不相信嗎?Fast2test的考古題就是這樣的資料。趕快試一下吧。
| 主題 | 簡介 |
|---|---|
| 主題 1 |
|
| 主題 2 |
|
| 主題 3 |
|
問題 #307
An organization suffered a loss to an asset at a frequency that was different than the initially estimated Annualized Rate of Occurrence (ARO). What is the appropriate course of action?
答案:C
問題 #308
The primary reason for tracing a component with scheduling problems to Its master production schedule (MPS) item is to:
答案:C
解題說明:
The primary reason for tracing a component with scheduling problems to its master production schedule (MPS) item is to determine if a customer order will be impacted. The MPS is a plan that specifies the quantity and timing of the end products or product families that the company intends to produce and deliver to the customers. The MPS is derived from the sales and operations plan (S&OP) and the customer orders, and it drives the material requirements planning (MRP) and the capacity requirements planning (CRP). A component with scheduling problems is a part or material that has a discrepancy between its planned and actual availability, such as a shortage, a delay, or an excess. Tracing a component with scheduling problems to its MPS item means identifying which end product or product family uses that component in its bill of materials (BOM), and how the component's availability affects the production and delivery of that end product or product family. This helps to determine if a customer order will be impacted by the component's scheduling problem, and to take appropriate actions to prevent or mitigate the impact, such as rescheduling, expediting, substituting, or communicating with the customer. The other options are not correct, as they are not the primary reason for tracing a component with scheduling problems to its MPS item, but rather possible actions or outcomes of the tracing process:
Revising the rough-cut capacity plan is a possible action that may result from tracing a component with scheduling problems to its MPS item, if the component's availability affects the capacity of the critical resources that are needed to produce the MPS item. Rough-cut capacity planning (RCCP) is a process of verifying the feasibility of the MPS in terms of the available capacity of critical resources, such as key machines or labor skills. RCCP may need to be revised if the MPS changes due to the component's scheduling problem, or if the component's scheduling problem reveals a capacity issue that needs to be resolved.
Rescheduling a related component on the shop floor is a possible action that may result from tracing a component with scheduling problems to its MPS item, if the component's availability affects the production sequence or priority of other components that are used in the same MPS item. Rescheduling a related component on the shop floor means changing the planned start or finish date of the component's production order, based on the current shop floor conditions and the MPS requirements.
Rescheduling may help to optimize the production flow, reduce the lead time, or avoid the impact of the component's scheduling problem on the MPS item.
Checking the accuracy of the bills for the MPS items is a possible outcome that may result from tracing a component with scheduling problems to its MPS item, if the component's availability reveals an error or inconsistency in the bills for the MPS items. Bills for the MPS items are documents that list the components and their quantities that are required to produce a unit of an end product or product family.
Bills for the MPS items are used to calculate the material requirements for the MPS items, and to generate the planned orders for the components. Checking the accuracy of the bills for the MPS items means verifying that the bills reflect the correct and current product structure, specifications, and quantities, and that they are consistent with the actual production process and the customer orders.
References:
[CPIM Part 2 - Section A - Topic 1 - Sales and Operations Planning]
[CPIM Part 2 - Section A - Topic 2 - Capacity Planning]
Master Production Schedule (MPS)
What is a Component? | Definition, Types, & Examples
Tracing a Component to Its MPS Item
Rough Cut Capacity Planning (RCCP)
[Rescheduling]
[Bill of Materials (BOM)]
問題 #309
The demand for an item has increasing forecast error, whereas all other factors remain constant. Which of the following remains constant while maintaining the same customer service level?
答案:D
解題說明:
Safety factor is a multiplier that is applied to the standard deviation of demand to determine the safety stock level. Safety factor remains constant while maintaining the same customer service level, as it reflects the desired probability of not stocking out. The higher the safety factor, the higher the customer service level, and vice versa. The other factors do not remain constant while maintaining the same customer service level.
Reorder point (ROP) is the inventory level that triggers a replenishment order. ROP increases with increasing forecast error, as more safety stock is needed to cover the demand uncertainty. Safety stock is the inventory that is carried to protect against forecast errors and demand fluctuations. Safety stock increases with increasing forecast error, as more buffer is needed to avoid stockouts. Inventory investment is the total value of the inventory that is held in the system. Inventory investment increases with increasing forecast error, as more inventory is required to maintain the same customer service level. References: Safety Factor | APICS Dictionary Term of the Day, APICS CPIM 8 Planning and Inventory Management | ASCM
問題 #310
Which of the following is a disadvantage of using federated identity?
答案:B
問題 #311
The cost accountant has discovered a consistent overage in actual run time for one operation. This information should be sent first to the:
答案:D
解題說明:
The production supervisor is the most appropriate person to send the information about the overage in actual run time for one operation. The production supervisor is responsible for overseeing the execution of the production plan and ensuring that the operations are performed efficiently and effectively. The production supervisor can review the actual run time data and compare it with the planned run time, identify the possible causes of the overage, and take corrective actions if needed. The production supervisor can also explain the overage to the cost accountant and other stakeholders, such as the product manager, the quality manager, and the engineering manager, and provide feedback for improving the planning and routing of the operation. Reference:
APICS CPIM Part 2 Exam Content Manual, p. 30
[APICS CPIM Learning System Version 8.0], Module 4, Section D, p. 4-35