P.S. Free & New PMI-RMP dumps are available on Google Drive shared by Fast2test: https://drive.google.com/open?id=1n8EBOh1m0lJ-i4G3r2aAULtFPFAlNm7_
Generally speaking, every candidate wants to pass the exam just one time. PMI-RMP learning materials of us can do that for you. Since we have a professional team to collect and research the latest information for the exam, and therefore the quality can be guaranteed. We offer you free demo for PMI-RMP Exam Materials to have a try, so that you can know what the complete version is like. Besides, we also pass guarantee and money back guarantee, and if you fail to pass the exam after using PMI-RMP exam materials of us, we will give you refund.
The PMI-RMP certification exam contains a total of 170 multiple-choice questions, which are to be completed within the allocated timeframe of 210 minutes. The test has a tutorial and a survey that are optional for every candidate. Each of them can take at least 15 minutes of your time. However, this time is not included in the exam time of 210 minutes. 20 questions out of 170 are pretest items, so they do not affect your overall score. These questions are included in the content of this test to legitimize its validity. The computer-based exam is administered by the Pearson VUE testing company and is delivered in the English language only. The exam will cost you $520 if you are a PMI member and $670 if you are a non-member. If you fail the test at your first attempt, you will have the opportunity for two retakes within a 1-year eligibility period. The retake fee amounts to $335 for the members and $435 for the non-members.
The PMI-RMP certificate required renewal every three years. To maintain your certification status, you will need to earn 30 Professional Development Units (PDUs) in the risk management domain with a 3-year period.
>> PMI-RMP Reliable Exam Online <<
Fast2test has one of the most comprehensive and top-notch PMI PMI-RMP Exam Questions. We eliminated the filler and simplified the PMI Risk Management Professional preparation process so you can ace the PMI certification exam on your first try. Our PMI PMI-RMP Questions include real-world examples to help you learn the fundamentals of the subject not only for the PMI exam but also for your future job.
PMI-RMP certification exam is a rigorous exam that covers a wide range of topics related to risk management. PMI-RMP exam consists of 170 multiple-choice questions, which need to be answered in four hours. To pass the exam, candidates need to score at least 61% or higher. PMI Risk Management Professional certification is valid for three years, and candidates need to earn 30 professional development units (PDUs) in risk management every three years to maintain their certification.
The Project Management Institute (PMI) is a globally recognized organization that offers various certifications to professionals in the project management domain. One of the most sought-after certifications from PMI is the PMI-RMP (PMI Risk Management Professional) certification. PMI Risk Management Professional certification is specifically designed for professionals who want to specialize in risk management practices and techniques.
NEW QUESTION # 240
You are the project manager of the HJU project for your company. This project will last for 18 months and has a project budget of $567,000. Robert, one of your stakeholders, has introduced a scope change request that will likely have an impact on the project costs and schedule. Robert assures you that he will pay for the extra time and costs associated with the risk event. You tell Robert that the change request may affect more areas of the project than just time and cost and that you are worried about the additional risks the change request will bring. What project management component is responsible for evaluating a change request and its impact on all of the project management knowledge areas?
Answer: B
NEW QUESTION # 241
An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.
What should the risk manager do next?
Answer: C
Explanation:
According to the PMI Risk Management Professional (PMI-RMP)Examination Content Outline1, a secondary risk is a risk that arises as a direct result of implementing a risk response to a specific risk. In this case, the risk response is to contract an external vendor to provide additional capacity and expertise to the project team. The secondary risk is the confidentiality risk that the contracts department has identified. The risk manager should assess the secondary risk to determine its probability, impact, and priority, and to plan appropriate responses. This is part of the Perform Qualitative Risk Analysis and Plan Risk Responses processes in the PMBOKGuide2. Reference: 1: PMI Risk Management Professional (PMI-RMP)Examination Content Outline 2: A Guide to the Project Management Body of Knowledge (PMBOKGuide) - Sixth Edition
NEW QUESTION # 242
As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.
What is the total contingency budget that should be created?
Answer: A
Explanation:
In risk management, to calculate the contingency budget for risks, we use the Expected Monetary Value (EMV) formula: EMV=Probability of Risk×Impact of Risk\text{EMV} = \text{Probability of Risk} \times
\text{Impact of Risk}EMV=Probability of Risk×Impact of Risk
For Risk A:
Probability: 40% or 0.40
Impact: US$100,000\text{EMV of Risk A} = 0.40 \times 100,000 = US$40,000 For Risk B:
Probability: 60% or 0.60
Impact: US$20,000\text{EMV of Risk B} = 0.60 \times 20,000 = US$12,000
Total contingency budget = EMV of Risk A + EMV of Risk B
40,000 + 12,000 = US$52,000
Thus, the total contingency budget required for both risks is US$52,000. This approach follows PMI's risk management guidelines, specifically under the " Quantitative Risk Analysis " process. This process focuses on determining numerical probabilities and monetary impacts to compute the expected financial impact of identified risks.
NEW QUESTION # 243
Pete works as a project manager for BlueWell Inc. The Management has told him that he must implement an agreed-upon contingency response if the cost performance index in his project is less than 0.90. Consider that Pete's project has a budget at completion of $275,000. His project is 65 percent complete and he has spent $175,000 to date. However, Pete is scheduled to be 78 percent complete. What is the cost performance index for this project to determine if the contingency response should happen?
Answer: A
NEW QUESTION # 244
The project manager reviews project risks with the risk manager to update, monitor, and close risks in the risk register. The project manager determines one of the risks has a residual risk.
How should the risk manager document the impact of the residual risk?
Answer: D
Explanation:
In risk management, when a residual risk is identified, it is crucial to reassess its impact on the project's overall risk profile. Residual risks are those risks that remain even after all mitigation strategies have been applied. According to best practices and the procedures outlined in the documents provided, particularly in the
"Risk Management Procedure" and the "Risk Assessment" guidelines, the appropriate steps to manage residual risks involve:
1. Reassessing the Risk: The first step involves reviewing the impact of the residual risk in the context of existing budget reserves. This ensures that the project has adequate resources to address any potential consequences of the residual risk.
2. Documenting in the Risk Register: After reviewing the residual risk, it should be documented in the risk register with updated details on its impact and any required actions. This aligns with the standard procedure for managing risks throughout a project's lifecycle as described in the "Consolidated Risk Register" section of the Risk Management Procedure.
3. Budget Reserves: Specifically, the focus on budget reserves is crucial because it directly relates to the financial management of risks. According to PMI's Risk Management guidelines and the practices outlined in the provided documents, ensuring that sufficient contingency funds are available to address residual risks is a key aspect of comprehensive risk management. This approach helps in maintaining the financial health of the project while accounting for unforeseen events.
In summary, option D is the correct answer because it reflects the necessary actions that should be taken when dealing with residual risks: reassessing their impact on budget reserves and ensuring that the risk register is updated to reflect these considerations. This process is vital for maintaining control over the project's risk profile and ensuring that any remaining risks are managed effectively and within the project's financial constraints.