CCM Positive Feedback - CCM Latest Practice Questions

P.S. Free & New CCM dumps are available on Google Drive shared by RealVCE: https://drive.google.com/open?id=1E-V0k0Vl3kE1arzl2gV4KH8ZlGjxXhIJ

Our CCM practice questions enjoy great popularity in this line. We provide our CCM exam braindumps on the superior quality and being confident that they will help you expand your horizon of knowledge of the exam. They are time-tested CCM Learning Materials, so they are classic. As well as our after-sales services. And we can always give you the most professional services on our CCM training guide.

Medical Professional CCM Exam Syllabus Topics:

SectionObjectives
Topic 1: Quality and Outcomes Evaluation- Quality improvement methods
- Outcome measurement and evaluation
Topic 2: Rehabilitation and Disability Management- Return-to-work planning
- Rehabilitation principles
Topic 3: Ethics, Legal, and Regulatory Aspects- Professional ethics in case management
- Legal and regulatory compliance
Topic 4: Care Delivery and Reimbursement Methods- Healthcare delivery systems
- Insurance and reimbursement structures
Topic 5: Psychosocial and Support Systems- Psychosocial assessment
- Community resources and support systems

>> CCM Positive Feedback <<

CCM Pass4sure vce - CCM Updated Training & CCM prep practice

CCM actual test not only are high-quality products, but also provided you with a high-quality service team. Our RealVCE platform is an authorized formal sales platform. Since the advent of CCM prep torrent, our products have been recognized by thousands of consumers. Everyone in CCM exam torrent ' team has gone through rigorous selection and training. We understand the importance of customer information for our customers. And we will strictly keep your purchase information confidential and there will be no information disclosure. At the same time, the content of CCM Exam Torrent is safe and you can download and use it with complete confidence.

Medical Professional Certified Case Manager Certification Exam (CCM) Sample Questions (Q76-Q81):

NEW QUESTION # 76
Which one of the following is NOT considered a change made in the 2017 edition of the FIDIC Red, Yellow, and Silver Books?

Answer: C

Explanation:
Comprehensive and Detailed Explanation:
Option D is not a new procedure introduced in the 2017 FIDIC editions.
The 2017 editions focus on dispute avoidance (A), quality management systems (B), and fair risk allocation (C), but do not explicitly require a Compliance Verification System as described.
References:
FIDIC Red, Yellow, Silver Books 2017 Editions - Overview of Changes
FIDIC Contract Manager Study Guide, Module on Contract Updates


NEW QUESTION # 77
(You are the Contract Manager for the Engineer in a highway project using FIDIC Red Book (edition 1999).
There is a Schedule of cost indexation included in the Contract. The project must be completed by 31 December of this year. If the Contractor fails to complete the Works by then, how will the adjustment of prices take place thereafter? (1 correct answer applies))

Answer: C

Explanation:
Under FIDIC Red Book 1999, Sub-Clause 13.8 [Adjustments for Changes in Cost] governs the mechanism for price adjustment based on cost indices. A critical provision applies when the Contractor fails to complete the Works within the Time for Completion.
In such circumstances, FIDIC protects the Employer against additional cost increases resulting from Contractor-caused delay. The clause explicitly states that the adjustment of prices after the contractual completion date shall be calculated using whichever index is more favourable to the Employer between:
* the indices applicable at the time the work is actually carried out (current index), and
* the indices applicable 49 days before the expiry of the Time for Completion.
This ensures that the Contractor does not benefit from inflation or cost escalation occurring after the contractual completion date if the delay is attributable to the Contractor. It reinforces the principle that the Contractor bears the financial consequences of delays under its responsibility.
Options A and B are incomplete because they ignore the comparison mechanism. Option D is incorrect because the rule is predefined and not subject to further agreement.
Thus, Option C correctly reflects the FIDIC contractual mechanism for price adjustment after delayed completion.


NEW QUESTION # 78
(Which two FIDIC Books (edition 2017) should especially be considered for use if the Employer needs the Contractor to take responsibility for the design and execution of the project. The construction will involve substantial work underground or work in other areas which tenderers cannot inspect.
Choose all of the correct answers (multiple possibilities).)

Answer: A,C

Explanation:
The key issue in this question is the allocation of design responsibility and the treatment of unforeseeable physical conditions (particularly relevant for underground works or inaccessible areas).
The Yellow Book 2017 is specifically designed for projects where the Contractor is responsible for both design and execution, while still maintaining a balanced risk allocation. Importantly, Sub-Clause 4.12
[Unforeseeable Physical Conditions] allows the Contractor to claim additional time and/or cost for conditions that could not reasonably have been foreseen. Therefore, for projects involving underground or uninspectable works, the Yellow Book is highly appropriate. Hence, Option A is correct.
The Silver Book 2017 (EPC/Turnkey) also places full responsibility for design and execution on the Contractor. However, it adopts a much stricter risk allocation: the Contractor generally bears the risk of unforeseen physical conditions. This makes it less suitable for projects with significant uncertainty-unless amendments are made. By modifying Sub-Clause 4.12 in the Particular Conditions to reallocate risk (e.g., allowing relief for unforeseeable conditions), the Silver Book can be adapted for such projects. Therefore, Option C is correct.
Option B (Red Book) is incorrect because design responsibility primarily lies with the Employer, not the Contractor.
Option D is incorrect because using the Silver Book without amendment would place excessive and potentially unmanageable risk on the Contractor in cases involving unknown subsurface conditions.
This reflects a core FIDIC principle: selecting the appropriate form depends heavily on risk allocation and the degree of uncertainty in site conditions.


NEW QUESTION # 79
There are four reasons that the Employer/Contractor shall advise in advance each other and the Engineer of any known or future events or circumstances.
Which two of the following statements are NOT applicable reasons?
(Choose all correct answers - multiple possibilities)

Answer: A,D

Explanation:
Under the FIDIC Red Book 2017 (similar principles apply in other editions), Sub-Clause 4.1 ("Contractor's General Obligations") and Sub-Clause 3.4 ("Delay Damages") require both Employer and Contractor to notify the Engineer in advance about any events or circumstances which may delay the works or adversely affect the Contractor's personnel or progress. This early notification ensures proper management and mitigation of risks that could impact the project timeline or quality.
* Option A (Delay the execution of the Works or a Section) is a core reason for notification since delays affect the critical path and programme, requiring possible extensions or adjustments.
* Option C (Adversely affect the work of the Contractor ' s Personnel) is also a valid reason because issues affecting workforce productivity or availability can impact project delivery.
On the other hand:
* Option B (Decrease the Contract Price) is not a reason to notify. Changes in contract price usually arise from variations or claims but are not a "known or future event" requiring prior notification unless linked to a variation or compensation event.
* Option D (Increase the performance of the Works when completed) is positive and does not negatively affect project progress or cost; therefore, it is not a reason for advance notification under these contract provisions.
Thus, the two not applicable reasons are B and D.
References:
FIDIC Conditions of Contract for Construction, 2017 Edition, Sub-Clause 4.1 - Contractor's General Obligations FIDIC Conditions of Contract for Construction, 2017 Edition, Sub-Clause 3.4 - Delay Damages FIDIC Contract Manager Study Guide, Module on Communication and Reporting


NEW QUESTION # 80
Regarding the FIDIC Silver Book (both editions), if a part of the Works is to be paid according to quantity supplied or work done, appropriate provisions must be included in the Particular Conditions. Is this statement true or false?

Answer: A

Explanation:
This statement is true. The Silver Book (EPC/Turnkey contracts) usually involves lump-sum payment, but if part payment is based on quantity or work done, this must be explicitly provided for in the Particular Conditions to avoid ambiguity.
Such provisions ensure clarity on payment terms in line with project specifics.
References:
FIDIC Silver Book 1999 & 2017 Editions, Sub-Clause 14 - Payment Provisions FIDIC Contract Manager Study Guide, Module on Payment Procedures


NEW QUESTION # 81
......

The RealVCE offers three formats for applicants to practice and prepare for the CCM exam as per their needs. The pdf format of RealVCE is portable and can be used on laptops, tablets, and smartphones. Print real Certified Case Manager Certification Exam (CCM) (CCM) exam questions in our PDF file. The pdf is user-friendly and accessible on any smart device, allowing applicants to study from anywhere at any time.

CCM Latest Practice Questions: https://www.realvce.com/CCM_free-dumps.html

P.S. Free & New CCM dumps are available on Google Drive shared by RealVCE: https://drive.google.com/open?id=1E-V0k0Vl3kE1arzl2gV4KH8ZlGjxXhIJ