BONUS!!! Download part of VCE4Dumps CCM dumps for free: https://drive.google.com/open?id=1R7iK8jsEBVncBV0EAU9p9BCnkYtP63m2
Our CCM real exam dumps are specially prepared for you. Try our CCM study tool and absorb new knowledge. After a period of learning, you will find that you are making progress. The knowledge you have studied on our CCM exam question will enrich your life and make you wise. Do not reject challenging yourself. Your life will finally benefit from your positive changes. Let us struggle together and become better. Then you will do not need to admire others’ life. Our CCM Real Exam dumps will fully change your life.
| Section | Weight | Objectives |
|---|---|---|
| Topic 1: Reimbursement Methods | 12% | - Managed care and accountable care concepts - Payment and reimbursement methodologies - Financial resources and negotiation - Coding and utilization review principles - Insurance principles and benefit structures |
| Topic 2: Ethics, Legal, and Practice Standards | 18% | - Professional ethics and conduct - Advocacy and patient rights - Legal and regulatory requirements - Confidentiality and privacy - Scope of practice and roles |
| Topic 3: Care Management | 30% | - Cost containment principles - Age-specific care application - Client-centered care plan development - Care coordination and collaboration - Evidence-based case management models and tools - Caseload assignment and selection criteria - Medication management |
| Topic 4: Quality and Outcomes Evaluation and Measurements | 10% | - Accreditation and regulatory standards - Outcome measurement and analysis - Data collection and reporting - Cost-benefit and effectiveness analysis - Performance improvement |
| Topic 5: Psychosocial Concepts and Support Systems | 20% | - Mental health and substance use considerations - Family dynamics and support systems - Cultural competence and diversity - Abuse and neglect recognition - Behavioral change theories and models |
| Topic 6: Healthcare Delivery Systems and Community Resources | 10% | - Interdisciplinary collaboration - Community-based services and resources - Healthcare policy and systems - Continuum of care settings |
No matter you are a company empoyee or a student, you will find that our CCM training quiz is priced reasonably to afford. Though the price is quite low but the quality is unparalleled high. We own numerous of loyal clients that constantly bought our CCM Exam Braindumps and recommended them to their friends, classmates or colleagues. Besides, we give discounts to our customers from time to time. Lots of our customers prised our CCM practice guide a value-added product.
NEW QUESTION # 134
Which one of the following statements is NOT correct in respect of FIDIC Yellow Book (both editions)?
Answer: B
Explanation:
Option C is NOT correct. FIDIC Yellow Book General Conditions aim to allocate risks fairly and equitably between the Employer and Contractor. The contract balances risks according to who is best able to manage them. It does not impose a disproportionate risk burden on the Contractor.
Options A, B, and D are correct statements describing typical contract formation, risk allocation, and Contractor's design and execution responsibilities.
References:
FIDIC Yellow Book 1999 and 2017 Editions - Introduction and Risk Allocation Clauses FIDIC Contract Manager Study Guide, Module on Introduction to FIDIC Contracts
NEW QUESTION # 135
(Under the FIDIC Red and Yellow Books (edition 1999), which two of the following answers are correct regarding the application for Interim Payment Certificates? Choose all correct answers.)
Answer: C,D
Explanation:
Under FIDIC Red Book and Yellow Book 1999, Sub-Clause 14.3 [Application for Interim Payment Certificates] governs the Contractor's obligations when submitting statements for interim payments.
Option B is correct because the Statement must include amounts relating to Provisional Sums where applicable. These sums form part of the Contract Price adjustments and must be reflected in interim applications when instructed or executed.
Option C is also correct. Sub-Clause 14.3 explicitly requires that each Statement be accompanied by supporting documents. This includes records of progress and, importantly, the progress report under Sub- Clause 4.21 [Progress Reports], ensuring that the Engineer can properly assess the value of work done.
Option A is incorrect because FIDIC does not mandate submission "in five copies" nor submission directly to the Employer; typically, submissions are made to the Engineer, and the number of copies is not fixed in the General Conditions.
Option D is incorrect as stated. While Plant and Materials may be considered under Sub-Clause 14.5 [Plant and Materials intended for the Works], their inclusion is subject to specific conditions and certification, not simply "added and deducted" generically within every Statement.
Thus, the correct application aligns with procedural compliance, proper substantiation, and inclusion of relevant financial components as per Clause 14.
NEW QUESTION # 136
Which two of the following statements are correct, regarding the Programme under FIDIC Red, Yellow and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities).
Answer: A,B
Explanation:
Option A is correct: The Contractor must proceed according to the approved Programme, and the Employer's personnel rely on the Programme for coordinating their activities.
Option B is correct: Submission and approval of the Programme do not relieve the Contractor of the obligation to give timely notices for delays or other events as required under the contract (e.g., notices under Sub-Clause 8.4).
Option C is incorrect because the Programme is not strictly a contract document binding parties in the legal sense; it is a working tool to manage and monitor progress.
Option D is incorrect; the Engineer/Employer must review the Programme and notify the Contractor if it does not comply, per contract clauses.
References:
FIDIC Red, Yellow, and Silver Books 2017, Sub-Clause 8.3 and 8.4 - Programme and Notices FIDIC Contract Manager Study Guide, Module on Time and Delay Management
NEW QUESTION # 137
Which two of the following statements are correct regarding the dayworks under FIDIC Red, Yellow, and Silver Books (both editions)?
Choose all of the correct answers (multiple possibilities).
Answer: A,C
Explanation:
Dayworks refer to works executed on a time basis (e.g., labor and plant) with payment made according to predetermined rates rather than a lump sum or unit rate contract price.
* Option A is incorrect. Even if a Daywork Schedule is not initially included, the dayworks Sub-Clause (e.
g., Sub-Clause 13.7 in Red and Yellow Books, 13.8 in Silver Book 1999) still applies to dayworks ordered during the contract execution. The schedule facilitates pricing, but the Sub-Clause governs the method and conditions for dayworks.
* Option B is correct. The dayworks Sub-Clause is applicable not only to traditional construction works but can also be applied to other types of works, such as variations or additional works that cannot be precisely measured or foreseen and are charged on a time basis.
* Option C is incorrect. The dayworks Sub-Clause is used in all FIDIC standard forms (Red, Yellow, and Silver Books), not only for remeasurement in the Red Book. In the Yellow Book (plant and design- build) and Silver Book (EPC/turnkey), dayworks are similarly applicable for certain variations or unforeseen works.
* Option D is correct. The Engineer (in Red and Yellow Books) or the Employer (in the Silver Book, where the Engineer's role is limited) may instruct that a variation be executed on a daywork basis. This instruction is typically used when the scope or quantity cannot be reasonably pre-determined.
References:
FIDIC Red Book 2017 Edition, Sub-Clause 13.7 - Dayworks
FIDIC Yellow Book 2017 Edition, Sub-Clause 13.7 - Dayworks
FIDIC Silver Book 1999 Edition, Sub-Clause 13.8 - Dayworks
FIDIC Contract Manager Study Guide, Module on Contract Administration Procedures
NEW QUESTION # 138
(Which of the following two statements are correct regarding subcontractors under FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities).)
Answer: C,D
Explanation:
Under FIDIC 2017 (Clause 4.4 [Subcontractors]), the Contractor is generally permitted to subcontract parts of the Works, but subject to specific controls and limitations.
Option B is correct. FIDIC expressly provides that the Contractor shall not subcontract the whole of the Works without prior consent of the Engineer. This ensures that the Contractor remains the primary responsible party and does not transfer the entire contractual obligation to others without oversight.
Option D is also correct. The Contract Data may specify certain portions of the Works that cannot be subcontracted, preserving critical elements under the direct responsibility of the Contractor.
Option A is incorrect because only the Engineer's consent is generally required for subcontracting (not both Engineer and Employer), except in specific cases defined in the Contract.
Option C is incorrect because the Contractor remains fully responsible for the acts, defaults, and neglect of all Subcontractors, as if they were the Contractor's own actions. This is a fundamental FIDIC principle ensuring a single point of responsibility.
These provisions maintain control, accountability, and quality assurance in project execution while allowing flexibility in subcontracting arrangements.
NEW QUESTION # 139
......
VCE4Dumps's CCM exam training materials evoke great repercussions in the examinees, and has established a very good reputation, which means that choosing VCE4Dumps CCM exam training materials is to choose success. After you buy our CCM VCE Dumps, if you fail to pass the certification exam or there are any problems of learning materials, we will give a full refund. What's more, after you buy our CCM exam, we will provide one year free renewal service.
Reliable CCM Exam Price: https://www.vce4dumps.com/CCM-valid-torrent.html
BONUS!!! Download part of VCE4Dumps CCM dumps for free: https://drive.google.com/open?id=1R7iK8jsEBVncBV0EAU9p9BCnkYtP63m2