P.S. Free & New CCM dumps are available on Google Drive shared by ValidVCE: https://drive.google.com/open?id=1T0UfcmbG2wWJSPXF5KQcgiy_BrI8Rxij
Whether you want to improve your skills, expertise or career growth, with ValidVCE's CCM training and CCM certification resources help you achieve your goals. Our exams files feature hands-on tasks and real-world scenarios; in just a matter of days, you'll be more productive and embracing new technology standards. Our online resources and events enable you to focus on learning just what you want on your timeframe. You get access to every exams files and there continuously update our study materials; these exam updates are supplied free of charge to our valued customers. Get the best CCM Exam Training; as you study from our exam-files.
| Section | Objectives |
|---|---|
| Topic 1: Psychosocial and Support Systems | - Psychosocial assessment - Community resources and support systems |
| Topic 2: Care Delivery and Reimbursement Methods | - Insurance and reimbursement structures - Healthcare delivery systems |
| Topic 3: Ethics, Legal, and Regulatory Aspects | - Legal and regulatory compliance - Professional ethics in case management |
| Topic 4: Quality and Outcomes Evaluation | - Quality improvement methods - Outcome measurement and evaluation |
| Topic 5: Rehabilitation and Disability Management | - Rehabilitation principles - Return-to-work planning |
We are in a constant state of learning new knowledge, but also a process of constantly forgotten, we always learned then forget, how to solve this problem, the answer is to have a good memory method, our CCM study materials will do well on this point. Our CCM Study Materials have their own unique learning method, abandon the traditional rote learning, adopt diversified memory patterns, such as the combination of text and graphics memory method, to distinguish between the memory of knowledge.
NEW QUESTION # 87
Which two of the following statements are correct regarding the dayworks under FIDIC Red, Yellow, and Silver Books (both editions)?
Choose all of the correct answers (multiple possibilities).
Answer: B,C
Explanation:
Dayworksrefer to works executed on a time basis (e.g., labor and plant) with payment made according to predetermined rates rather than a lump sum or unit rate contract price.
* Option Aisincorrect. Even if a Daywork Schedule is not initially included, the dayworks Sub-Clause (e.g., Sub-Clause 13.7 in Red and Yellow Books, 13.8 in Silver Book 1999) still applies to dayworks ordered during the contract execution. The schedule facilitates pricing, but the Sub-Clause governs the method and conditions for dayworks.
* Option Biscorrect. The dayworks Sub-Clause is applicable not only to traditional construction works but can also be applied to other types of works, such as variations or additional works that cannot be precisely measured or foreseen and are charged on a time basis.
* Option Cisincorrect. The dayworks Sub-Clause is used in all FIDIC standard forms (Red, Yellow, and Silver Books), not only for remeasurement in the Red Book. In the Yellow Book (plant and design- build) and Silver Book (EPC/turnkey), dayworks are similarly applicable for certain variations or unforeseen works.
* Option Discorrect. The Engineer (in Red and Yellow Books) or the Employer (in the Silver Book, where the Engineer's role is limited) may instruct that a variation be executed on a daywork basis. This instruction is typically used when the scope or quantity cannot be reasonably pre-determined.
References:
FIDIC Red Book 2017 Edition, Sub-Clause 13.7 - Dayworks
FIDIC Yellow Book 2017 Edition, Sub-Clause 13.7 - Dayworks
FIDIC Silver Book 1999 Edition, Sub-Clause 13.8 - Dayworks
FIDIC Contract Manager Study Guide, Module on Contract Administration Procedures
NEW QUESTION # 88
When is the Employer obliged to return the Performance Security (PS) under the FIDIC Red Book (edition
1999)?
Answer: B
Explanation:
Comprehensive and Detailed Explanation:
Under FIDIC Red Book 1999, the Performance Security (or Performance Guarantee) is held to ensure the Contractor's performance during the defects liability period. The security is typically released only after the Employer issues the Performance Certificate, which confirms the completion of defects liability obligations and that the Contractor has fulfilled the contract.
The contract commonly specifies a fixed period (often 21 days) within which the Employer must return the Performance Security after issuance of the Performance Certificate (Option D). The Taking-Over Certificate (Options A and C) marks substantial completion but does not end the Contractor's obligations for defects.
References:
FIDIC Red Book 1999, Sub-Clause 10.2 - Taking-Over Certificate
FIDIC Red Book 1999, Sub-Clause 10.4 - Performance Certificate
FIDIC Red Book 1999, Sub-Clause 10.5 - Release of Performance Security
FIDIC Contract Manager Study Guide, Module on Payment Procedures and Financial Management
NEW QUESTION # 89
In case a Variation is initiated by the Engineer for prompt implementation ...... [FIDIC Red, and Yellow Books, 2017 Editions] Choose all of the correct answers (multiple possibilities).
Answer: D,E
Explanation:
Option B is correct: When instructed to implement a Variation promptly, the Contractor must commence work and keep detailed records for subsequent valuation and impact assessment.
Option D is correct: The Contractor is required to submit, within 28 days, a description, programme, and price proposal relating to the Variation as part of contract procedures.
Option A is incorrect: The Contractor generally must proceed promptly regardless of dispute about foreseeability but may reserve rights via notices.
Option C is incorrect: Safety cannot be compromised; the Contractor should not undertake hazardous work without mitigation.
Option E is incorrect: The Contractor is generally bound to start work upon instruction even if the price is not yet agreed.
References:
FIDIC Red and Yellow Books 2017 Editions, Sub-Clause 3.5 - Variation Procedure FIDIC Contract Manager Study Guide, Module on Variations and Change Management
NEW QUESTION # 90
(Under the FIDIC Red and Yellow Books (edition 1999), which two of the following answers are correct regarding the application for Interim Payment Certificates? Choose all correct answers.)
Answer: C,D
Explanation:
Under FIDIC Red Book and Yellow Book 1999, Sub-Clause 14.3 [Application for Interim Payment Certificates] governs the Contractor's obligations when submitting statements for interim payments.
Option B is correct because the Statement must include amounts relating to Provisional Sums where applicable. These sums form part of the Contract Price adjustments and must be reflected in interim applications when instructed or executed.
Option C is also correct. Sub-Clause 14.3 explicitly requires that each Statement be accompanied by supporting documents. This includes records of progress and, importantly, the progress report under Sub- Clause 4.21 [Progress Reports], ensuring that the Engineer can properly assess the value of work done.
Option A is incorrect because FIDIC does not mandate submission "in five copies" nor submission directly to the Employer; typically, submissions are made to the Engineer, and the number of copies is not fixed in the General Conditions.
Option D is incorrect as stated. While Plant and Materials may be considered under Sub-Clause 14.5 [Plant and Materials intended for the Works], their inclusion is subject to specific conditions and certification, not simply "added and deducted" generically within every Statement.
Thus, the correct application aligns with procedural compliance, proper substantiation, and inclusion of relevant financial components as per Clause 14.
NEW QUESTION # 91
Towards the end of implementing a varied work (initiated originally by the Contractor as a "Value Engineering Proposal", relevant designs provided by the Contractor) it turned out, that there is some part of it not complying with the otherwise prevailing standards. Which statements are correct in this situation? [FIDIC Red Book, 2017 Edition] Choose all of the correct answers (multiple possibilities).
Answer: B,C
Explanation:
Option C is correct: The Contractor is obligated to rectify any non-compliance with prevailing standards promptly.
Option D is correct: The Contractor carries responsibility for design fitness and correctness, even if the Engineer has approved or not objected to the design.
Option A is incorrect; Engineer approval does not absolve the Contractor from responsibility for defective design or works.
Option B is not necessarily required; only non-compliant parts need correction, not entire varied works.
References:
FIDIC Red Book 2017 Edition, Sub-Clause 4.1 and Clause 13 - Contractor's Obligations and Variations FIDIC Contract Manager Study Guide, Module on Variations and Design Responsibilities
NEW QUESTION # 92
......
Immediately after you have made a purchase for our CCM practice test, you can download our exam study materials to make preparations for the exams. It is universally acknowledged that time is a key factor in terms of the success of exams. There is why our CCM Test Prep exam is well received by the general public. I believe if you are full aware of the benefits the immediate download of our PDF study exam brings to you, you will choose our CCM actual study guide.
Exam CCM Prep: https://www.validvce.com/CCM-exam-collection.html
BTW, DOWNLOAD part of ValidVCE CCM dumps from Cloud Storage: https://drive.google.com/open?id=1T0UfcmbG2wWJSPXF5KQcgiy_BrI8Rxij