AD0-E911専門トレーリング & AD0-E911試験情報

AD0-E911試験ガイドの3つのバージョンはPDF版、PC版とAPPオンライン版を含め、当社のテストプラットフォーム上で利用可能です。その結果、携帯電話またはコンピューターでAD0-E911学習教材のオンラインテストエンジンを学習できます。また、自宅、会社、または地下鉄でAD0-E911実際の試験を勉強することもできます。ベテランであれば、AD0-E911試験の質問で勉強し、AD0-E911試験に合格するために、非常に効率的な方法で断片化時間を最大限に活用できます。

Adobe AD0-E911 Exam Overview:

Certification Vendor:Adobe
Exam Name:Adobe Workfront Project Manager Certified Professional
Exam Number:AD0-E911
Related Certifications:Adobe Workfront Fusion Developer Professional (AD0-E902)
Adobe Workfront Core Developer Professional (AD0-E912)
Adobe Workfront Core Developer Expert (AD0-E907)
Exam Duration:100 minutes
Certificate Validity Period:2 years
Available Languages:English
Passing Score:33 / 50
Exam Price:$125 USD
Exam Format:Scenario-based, Multiple Choice
Real Exam Qty:50
Sample Questions:Adobe AD0-E911 Sample Questions
Exam Way:Online proctored exam (via easyProctor dashboard).
Pre Condition:6-12 months of Adobe Workfront experience recommended.
Official Syllabus URL:https://certification.adobe.com/courses/1320

>> AD0-E911専門トレーリング <<

AD0-E911試験情報 & AD0-E911認定資格

我々GoShikenは一番信頼できるIT試験資料販売サイトになれるために、弊社はお客様に最完備かつ最新版のAD0-E911問題集を提供して努力します。我々の問題集によって、ほとんどの受験生は大方の人から見る大変なAdobe AD0-E911試験にうまく合格しました。この成功データはAD0-E911試験に準備する皆様にGoShikenのAD0-E911問題集を勧める根拠とします。もしあなたは残念的にAD0-E911試験に失敗したら、全額で返金することを承諾します。すべてのことはあなたの安心的に試験に準備できるのためのです。

Adobe AD0-E911 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • 受付と計画:Workfrontにおける作業依頼の受付、レビュー、計画のプロセスについて説明します。これには、タスク設定、権限、プロジェクト階層、リスク追跡、計画フェーズにおける関連レポート作成などが含まれます。
トピック 2
  • 実行:Workfrontにおけるプロジェクトの積極的な管理を網羅しており、マイルストーン、承認、リソース割り当て、財務追跡、チームコミュニケーション、校正、ガントチャート、プロジェクト実行中のカスタムレポート作成などが含まれます。
トピック 3
  • 完了処理:プロジェクトを完了する際に必要なアクションと評価について説明します。これには、オブジェクトのステータストリガーやプロジェクト全体の成功度の測定などが含まれます。

Adobe Workfront Project Manager Certified Professional 認定 AD0-E911 試験問題 (Q13-Q18):

質問 # 13
A task won't close when trying to select "Complete."
Which two reasons block someone from being able to close a task? (Choose two.)

正解:D、E

解説:
In Adobe Workfront, two common reasons a task cannot be marked Complete are incomplete enforced predecessors and incomplete subtasks on a parent task. Adobe documentation explains that when a predecessor is enforced, Workfront does not allow the successor task to be marked In Progress or Complete until the predecessor task is completed. Therefore, if the predecessor task is still In Progress, it can block the current task from being closed, provided the predecessor relationship is enforced. Adobe also explains that parent tasks cannot be updated to Complete when the project's Summary Completion Mode is set to Automatic and the subtasks are not completed. This means incomplete child tasks can prevent the parent task from closing. Being a predecessor to another task does not stop the current task from being completed. Assignment to a job role rather than a named user does not inherently prevent completion, and an Active project status is normal for work execution. Therefore, the correct answers are A and B.


質問 # 14
A project manager has been asked to create a report showing the planned completion date for all the project manager's projects. The report must show results in a calendar view and all entries should be purple. What steps should the project manager take to create this view?

正解:C


質問 # 15
The second task in a project should be completed within 48 hours and needs to begin 5 business days after the first task is completed.
Which task settings should be configured to meet these requirements?

正解:A

解説:
In Adobe Workfront, to configure tasks according to the requirement of the second task beginning 5 business days after the first task, you need to set the appropriate "Duration" and use "Finish-Start" dependencies. The task's duration is key to determining the time allowed for its completion. The "Finish-Start" dependency ensures that the second task begins only after the first is finished, and a lag can be set to introduce a delay, such as 5 business days. Setting a "Finish-Start" dependency with a lag allows for proper scheduling of tasks in sequence without overlapping.


質問 # 16
How is the primary assignee of a task determined?

正解:A

解説:
In Adobe Workfront, when multiple users are assigned to a task, the system designates the user who was assigned first as the primary assignee. This is the user responsible for driving the task to completion, and their name will appear in the primary assignee field. This approach ensures clear accountability within teams.


質問 # 17
Which aspect of a project determines the Progress Status?

正解:C

解説:
In Adobe Workfront, the Progress Status of a project is determined by the project's progression across its timeline. Adobe documentation states that Workfront determines project Progress Status by evaluating how the project is progressing against its timeline, including comparisons between planned, projected, and estimated completion dates. This is why project Progress Status can appear as values such as On Time, At Risk, Behind, or Late depending on how the current forecast relates to the planned completion date. Critical Path is important because it identifies the sequence of tasks that can affect the project timeline, but it is not the direct field or aspect that determines Progress Status. Milestone Tasks are used to mark important points or phases in a project and can help with milestone reporting, but they also do not determine the overall Progress Status by themselves. Therefore, the correct answer is A. Timeline.