The learners’ learning conditions are varied and many of them may have no access to the internet to learn our PRINCE2Practitioner study materials. If the learners leave home or their companies they can’t link the internet to learn our PRINCE2Practitioner study materials. But you use our APP online version you can learn offline. If only you use the PRINCE2Practitioner study materials in the environment of being online for the first time you can use them offline later. So it will be very convenient for every learner because they won’t worry about when they go out or go to the remote area that they can’t link the internet to learn our PRINCE2Practitioner Study Materials, and they can use our APP online version to learn at any place or time. That’s the great merit of our APP online version and the learners who have difficulties in linking the internet outside their homes or companies can utilize this advantage, they can learn our PRINCE2Practitioner study materials at any place.
| Section | Objectives |
|---|---|
| PRINCE2 Processes | - Directing a Project - Closing a Project - Controlling a Stage - Starting up a Project - Managing Product Delivery - Managing a Stage Boundary - Initiating a Project |
| PRINCE2 Themes | - Organization - Progress - Risk - Business Case - Quality - Plans - Change |
| PRINCE2 Principles | - Manage by stages - Focus on products - Manage by exception - Learn from experience - Continued business justification - Defined roles and responsibilities - Tailor to suit the project |
>> VCE PRINCE2Practitioner Exam Simulator <<
The format name of Channel Partner Program PRINCE2Practitioner practice test questions is PRINCE2 PDF Questions file, desktop practice test software, and web-based practice test software. Choose the nay type of Channel Partner Program PRINCE2 Practitioner Exam PRINCE2Practitioner Practice Exam Questions that fit your PRINCE2 PRINCE2Practitioner exam preparation requirement and budget and start preparation without wasting further time.
NEW QUESTION # 161
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom- based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:
End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company' s document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
STARTING UP A PROJECT
Here are three actions carried out during the 'starting up a project' process.
As part of which activity (A-F) should each action occur?
Choose only one activity for each action. Each activity can be used once, more than once, or not at all.
Answer:
Explanation:
Explanation:
NEW QUESTION # 162
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:
Do nothing.
Re-engineer selected business functions.
Outsource selected business functions.
The feasibility study concluded that there was a case for outsourcing the MFH Information Technology
Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:
One service provider should be contracted to provide the services currently provided by the
Information Technology Division and the Facilities Division.
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems and
operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:
Use PRINCE2.
Set up the project with 4 management stages:
Stage 1. Standard PRINCE2 initiation activities.
Stage 2. Create detailed designs (future organization, processes, systems and operating
models) and the service level agreement between MFH and the future service
provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run
trial period.
Initial estimates indicated that the project would cost (GBP)2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the
recommendations as a basis for the project. There is an expected saving of (GBP)20m over 10 years.
The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.
Which 2 statements should be recorded under the Timescale heading?
Answer: A,C
NEW QUESTION # 163
The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?
Answer: B
NEW QUESTION # 164
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.) There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:
Design for each month - correctly showing at public holidays and new company logo
Selected photographs- 12 professionally-produced photographs, showing different members of staff
Selected paper and selected envelope - for printing and mailing the calendar
Chosen label design - a competition to design a label will be held as part of this project
List of customers - names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
Create the customer fast using information from the Accounts and Marketing departments
Confirm compliance with the Data Protection Legislation
Create a design for each month - this will be done by the internal creative team
Select and appoint a professional photographer
Gather photograph design ideas from previous project and agree photographic session schedule
Prepare a production cost forecast
Select paper and envelope.
Stage 3 will include the activities to:
Produce and select tie professionally-taken photographs
Hold the label design competition and choose the label design
Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +
£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.
During stage 2, an early review of the photo design ideas from the Marketing department has highlighted the need for engineering machinery to be operating in the background during the photo sessions. This requires a change to the baselined Product Description for the photos. What action should the Project Manager take?
Answer: B
NEW QUESTION # 165
CONTROLLING A STAGE
During stage 4, an issue was raised by an ABC trainer that the 'classroom-based training materials' contained errors, even though they were signed off during stage 3. They had been based on materials from a previous course and still contained references to that course. The impact of this issue is now being assessed.
Here are three actions that were carried out as part of the 'controlling a stage' process.
During which activity (A-F) should each action happen?
Choose only one activity for each action. Each activity can be used once, more than once, or not at all.
Answer:
Explanation:
Explanation:
NEW QUESTION # 166
......
Prep4sureExam PRINCE2 Practitioner Exam (PRINCE2Practitioner) practice test material covers all the key topics and areas of knowledge necessary to master the PRINCE2 Certification Exam. Experienced industry professionals design the PRINCE2Practitioner exam questions and are regularly updated to reflect the latest changes in the PRINCE2 Practitioner Exam (PRINCE2Practitioner) exam. In addition, Prep4sureExam offers three different formats of practice material which are discussed below.
Reliable PRINCE2Practitioner Test Preparation: https://www.prep4sureexam.com/PRINCE2Practitioner-dumps-torrent.html
What's more, part of that Prep4sureExam PRINCE2Practitioner dumps now are free: https://drive.google.com/open?id=1U5sipBb9zXxlpUTCLDCxjPmWlNJ-3l3q