During nearly ten years, our company has kept on improving ourselves on the PRINCE2Practitioner study questions, and now we have become the leader in this field. And now our PRINCE2Practitioner training materials have become the most popular PRINCE2Practitioner Practice Engine in the international market. There are so many advantages of our PRINCE2Practitioner guide quiz, and as long as you have a try on them, you will definitely love our exam dumps.
| Section | Objectives |
|---|---|
| Themes of PRINCE2 | - Business Case theme application - Progress theme monitoring and corrective action - Change theme handling and control - Quality theme techniques - Risk theme identification and management - Organization theme roles and responsibilities - Plans theme planning and estimation |
| Tailoring PRINCE2 to Project Contexts | - Adapt methodology to different project environments - Scenario-based application of PRINCE2 principles |
| Processes of PRINCE2 | - Starting up a project process steps - Directing a project process decisions - Controlling a stage process activities - Managing product delivery process - Managing stage boundaries process - Initiating a project process tasks - Closing a project process completion |
| Principles of PRINCE2 | - Apply the seven PRINCE2 principles to scenarios |
>> New PRINCE2Practitioner Exam Pass4sure <<
To save you from loss of money and time, ValidDumps is offering a product that is specially designed to help you pass the PRINCE2 Practitioner Exam (PRINCE2Practitioner) exam on the first try. The PRINCE2 PRINCE2Practitioner Exam Dumps is easy to use and very easy to understand, ensuring that it is student-oriented. You can choose from 3 different formats available according to your needs. The 3 formats are desktop PRINCE2Practitioner Practice Test software, web-based PRINCE2 Practitioner Exam (PRINCE2Practitioner) practice exam, and PRINCE2Practitioner dumps PDF format.
NEW QUESTION # 32
Product Summary
A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.
Product Breakdown Structure (contains errors)
Extract from Stage Plan for stage 3.
(All entries are true statements but may not be shown under the correct heading or in the correct document).
Using the Product Summary and Product Breakdown Structure provided as additional Information for this question In the Scenario Booklet, answer the following question.
Column 1 is a list of some of the entries in the product breakdown structure. Determine whether each entry in Column 1 has been correctly shown in the product breakdown structure. Select from Column 2 the appropriate statement that correctly describes that entry. Each selection from Column 2 can be used once, more than once or not at all.
Answer:
Explanation:
Explanation:
NEW QUESTION # 33
The project is now in stage 2. The 'training venue specifications' will not be delivered to schedule and the stage is forecast to exceed its time tolerance. As a result, the project manager has agreed with the team manager that the 'training venue specifications' will be delivered in stage 3 instead of stage 2.
Is this an appropriate action, and why?
Answer: C
Explanation:
Explanation/Reference: https://www.prince2primer.com/project-board-and-project-manager-prince2-controls/ Progress Theme Testlet 1 Project Scenario Calendar Project (Note: The companies and people within the scenario are fictional.) There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards.
Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:
* Design for each month - correctly showing at public holidays and new company logo
* Selected photographs- 12 professionally-produced photographs, showing different members of staff
* Selected paper and selected envelope - for printing and mailing the calendar
* Chosen label design - a competition to design a label will be held as part of this project
* List of customers - names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
* Create the customer fast using information from the Accounts and Marketing departments
* Confirm compliance with the Data Protection Legislation
* Create a design for each month - this will be done by the internal creative team
* Select and appoint a professional photographer
* Gather photograph design ideas from previous project and agree photographic session schedule
* Prepare a production cost forecast
* Select paper and envelope.
Stage 3 will include the activities to:
* Produce and select tie professionally-taken photographs
* Hold the label design competition and choose the label design
* Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be E20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +E6,000 / -E6,000. A change budget of E500 has been allocated but there is no risk budget.
NEW QUESTION # 34
Scenario
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.
There is no mention of any Stage Plans, yet there are two further stages proposed. How will this be resolved?
Answer: A
NEW QUESTION # 35
Scenario
Additional Information
Product Description
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors) Introduction
1. This document defines the approach to be taken to achieve the required quality levels during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
The service level agreement contains a number of technical terms that are missing from its glossary of terms.
Answer: A
NEW QUESTION # 36
What additional risk will this place on the project?
Answer: A
NEW QUESTION # 37
......
ValidDumps has designed PRINCE2 Practitioner Exam which has actual exam Dumps questions, especially for the students who are willing to pass the PRINCE2 PRINCE2Practitioner exam for the betterment of their future. The study material is available in three different formats. PRINCE2 Practice Exam are also available so the students can test their preparation with unlimited tries and pass PRINCE2 Practitioner Exam (PRINCE2Practitioner) certification exam on the first try.