| Section | Objectives |
|---|---|
| Processes | - Closing a project - Starting up a project - Initiating a project - Directing a project - Managing product delivery - Controlling a stage - Managing a stage boundary |
| Practices | - Quality - Business case - Issues - Progress - Plans - Organizing - Risk |
| People | - People management and effective collaboration |
| Principles | - Apply the PRINCE2 principles in context |
>> PRINCE2-7-Practitioner질문과 답 <<
우리PassTIP 에서 제공하는 학습가이드에는 IT전문가들이 만들어낸 시험대비 자료들과PRINCE2 PRINCE2-7-Practitioner인증시험의 완벽한 문제와 답들입니다. 그리고 우리PassTIP에서는 IT업계에서의 높은 신뢰감으로 여러분들한테 100%보장을 드립니다. 우리에 믿음을 드리기 위하여PRINCE2 PRINCE2-7-Practitioner관련자료의 일부분 문제와 답 등 샘플을 무료로 다운받아 체험해볼수 있게 제공합니다.
질문 # 34
At project closure, the project manager prepares the end project report, noting that the project exceeded its budget by 10% and planned duration by 15% because of additional heritage protection work. The findings are summarized for the project board and shared with the LOB Portfolio Director so that other projects can learn from them.
Which practice is being applied?
정답:C
설명:
The correct answer is C - Progress . The progress practice establishes mechanisms for comparing actual achievements with planned targets, forecasting future performance, controlling deviations, and providing appropriate information to decision-makers. At project closure, this includes reviewing overall project performance against the baselines and targets that were originally authorized.
The end project report provides the project board with a consolidated assessment of how the project performed. In this scenario, the project manager records that actual cost exceeded the budget by 10% and actual duration exceeded the planned schedule by 15%. These are direct comparisons between actual and planned performance , placing the information squarely within the progress practice.
Sharing the findings with the LOB Portfolio Director also enables experience from the LouisShopping project to support organizational learning. This does not change the primary practice being demonstrated: the information being analysed and communicated is project performance against authorized targets.
Option A concerns whether continued or completed investment was justified in terms of costs, benefits, risks, and business objectives. Option B concerns creation and maintenance of plans. Option D concerns ensuring products meet defined quality requirements. Although each may contribute information to project closure, the specific evaluation of cost and time performance belongs principally to progress .
PRINCE2 7 reference topics: Progress practice; end project report; actual versus planned performance; project closure; lessons and organizational learning.
질문 # 35
Before the end of stage 2, the project board authorizes a change that adds more trees and seating to the external landscaping. The change can be delivered in stage 3 without any forecast breach of project tolerance.
While preparing the next stage plan, the project manager incorporates the additional products and work, updates the relevant product descriptions and product register entries, and reviews whether the project initiation documentation needs to be updated.
Is this an appropriate application of 'prepare the next stage plan', and why?
정답:D
설명:
The correct answer is A . When preparing the next stage plan, the project manager must incorporate all relevant authorized changes that affect the products or work to be undertaken in the forthcoming management stage. The stage plan must represent the current authorized baseline rather than an obsolete version of what was originally intended.
The additional trees and seating have already been authorized by the project board, and the change can be incorporated without a forecast breach of overall project tolerance. The project manager should therefore reflect the additional products and activities in the stage 3 plan, revise affected product descriptions and product-register information, and determine whether corresponding elements of the project initiation documentation need updating.
Option B is incorrect because an exception plan is not required for every authorized change. Exception planning is used where agreed tolerance is forecast to be exceeded and the higher management level requests a replacement plan. The scenario explicitly states that project tolerance is not forecast to be breached. Option C incorrectly introduces mandatory re-authorization by the business layer. Option D is incorrect because preparing the next stage plan is a project manager responsibility; project assurance may independently review the resulting information but does not prepare it instead.
PRINCE2 7 reference topics: Managing a stage boundary; prepare the next stage plan; authorized changes; product descriptions; product register; PID maintenance; exception plans.
질문 # 36
At the stage 2 boundary, the project manager recommends adding the replacement subcontractor's account manager to the project board to represent supplier interests during stage 3.
Which practice is being applied in 'managing a stage boundary'?
정답:B
설명:
The correct answer is B - Organization . The organization practice defines the project's structure of accountability and responsibility and ensures that the business, user, and supplier interests are appropriately represented throughout the project.
The proposed appointment concerns representation of the supplier interest on the project board . The senior supplier is accountable for ensuring that the specialist products can be designed and delivered and that suitable supplier resources, expertise, and technical capability are available. Where the supplier environment changes substantially between stages, the suitability of the project management team should be reconsidered rather than assuming that the original organizational structure must remain unchanged for the entire project.
The replacement subcontractor is expected to undertake the utilities and systems work during stage 3. It is therefore appropriate at the stage boundary to assess whether its account manager should provide senior supplier representation for the forthcoming stage.
Option A, plans, concerns what will be delivered and how, when, and by whom at the planning level, but the specific decision being described concerns project-governance representation. Option C concerns establishing and controlling product quality. Option D concerns monitoring actual and forecast performance against authorized plans and tolerances.
The scenario therefore applies the organization practice within managing a stage boundary to ensure that the governance structure remains appropriate for the next stage.
PRINCE2 7 reference topics: Organization practice; senior supplier; project board; supplier interest; managing a stage boundary; project organization.
질문 # 37
Near the end of stage 2, the supplier planned for the utilities and systems work becomes financially unstable and a replacement subcontractor is selected for stage 3. The project manager recommends that the replacement subcontractor's account manager should represent the supplier interest as senior supplier.
During which 'managing a stage boundary' activity should this recommendation be developed?
정답:B
설명:
The correct answer is B - Prepare the next stage plan . The managing a stage boundary process ensures that the project board receives sufficient information to review the current stage and make an informed decision about authorizing the next one. Preparing the next stage plan includes determining how the forthcoming stage will be organized, resourced, managed, and controlled.
The replacement subcontractor will perform important utilities and systems work during stage 3.
Consequently, the project manager must consider whether the existing project management team remains appropriate for the forthcoming stage. Recommending the subcontractor's account manager as the new senior supplier is directly connected with establishing appropriate supplier representation and governance for the work that will be undertaken in that next stage.
Option A concerns revising the higher-level project plan using current information and forecasts; it does not primarily establish stage-specific project management team arrangements. Option C concerns assessing how the current stage performed, including achievements and lessons. Option D occurs after the necessary stage- boundary information has been prepared and is used to request authorization from the project board.
The recommendation should therefore be developed while preparing the next stage plan , so that the required organization and supplier representation are clear before authorization of stage 3 is requested.
PRINCE2 7 reference topics: Managing a stage boundary; prepare the next stage plan; organization; senior supplier; supplier representation; project management team.
질문 # 38
During stage 3, several BuildyBrick subcontractors are working on different work packages. The project manager is concerned that lessons identified by one team will not reach the others and could lead to rework, delay or additional cost. The project manager therefore holds a fortnightly cross-team 'lunch and learn' session.
Is this an appropriate application of the 'learn from experience' principle, and why?
정답:A
설명:
The correct answer is A . The learn from experience principle requires learning to occur throughout the project lifecycle, not merely during initiation or closure. Lessons should be sought, recorded where appropriate, communicated to those who can use them, and incorporated into current or future decisions and ways of working.
The fortnightly cross-team session directly addresses the project manager's concern that lessons emerging in one work package may otherwise remain isolated. Sharing them across teams allows corrective knowledge to be applied while it can still prevent rework, delay, cost escalation, or repeated mistakes. Official PeopleCert material emphasizes that lessons should be considered before starting, captured during delivery, and actively applied; simply recording a lesson without changing future behavior does not constitute effective learning.
Option B describes another legitimate source of lessons-previous projects-but does not explain the specific benefit demonstrated in the scenario, which concerns lessons arising across teams during the current stage .
Option C contradicts PRINCE2's expectation that lessons improve project performance rather than being regarded as non-productive overhead. Option D incorrectly postpones learning until the end of the stage, when the opportunity to prevent immediate repetition may already have passed.
PRINCE2 7 reference topics: Learn from experience; lessons log; knowledge sharing; applying lessons throughout the project lifecycle.