You buy our Itcertking SAVE International CVS Certification which is 100% risk free. Before you decide to use Itcertking SAVE International CVS dumps, you can try our free demo and pdf. Click Itcertking, download it now! Affordable, and good service – free update for a year. Quality first. Welcomes your order. Thank you.
| Section | Objectives |
|---|---|
| Value Methodology Core Competencies | - Function Analysis - Value Methodology Job Plan Application - VM Facilitation and Leadership - Advanced VM Practice (Leadership-level application) - Value Methodology Foundations
|
You don't know how to acquire a promotion quickly while you're trying to get a new job or already have one but need a promotion. The sole option is SAVE International CVS certification, which makes it simple for you to advance in your career. Your skills will advance and your resume will be enhanced thanks to the SAVE International CVS Certification.
NEW QUESTION # 46
Which statement best describes the Implementation Phase?
Answer: A
Explanation:
The correct answer is B . Implementation is the post-presentation activity where accepted recommendations are converted into action. Although the six-phase workshop Job Plan ends with Presentation, SAVE's VM process recognizes post-workshop documentation and implementation activity as part of the broader value study process. The VM Standard's process flow shows pre-workshop, workshop, and post-workshop
/implementation activities.
Option A is incorrect because collecting user attitudes and study preparation occur before or during early study activities, not Implementation. Option C is wrong because Creativity generates alternatives, while Implementation executes approved proposals. Option D is wrong because unselected ideas are not automatically approved. At CVS level, Implementation requires ownership, assigned responsibilities, schedules, change management, technical follow-through, documentation, and confirmation of achieved value. A proposal has no realized value until it is adopted and executed. Weak VM programs often generate impressive workshop reports but fail during implementation because accountability, funding, decision authority, and tracking mechanisms are missing.
References/topics: Implementation Phase; Post-Workshop Activities; Value Realization.
NEW QUESTION # 47
Place the process flow chart for the Function Performance Specification in the correct order.
Answer:
Explanation:
Explanation:
Need # Function # Specific Requirement # Product
The correct order is Need # Function # Specific Requirement # Product . This is the exact logic of the Function Performance Specification process. The VM Guide figure for Function Performance Specification shows the sequence as "Need Function Specific Requirement Product" , where a user need is translated into a function, then into measurable requirements, and finally into a product solution.
The sequence is important because Value Methodology begins with the user's need or desire , not with a predetermined product. After the need is understood, the VM team defines the function that satisfies that need, normally in active verb/measurable noun format. SAVE's study-guide material explains that work functions are quantitative and stated using an active verb and measurable noun. The next step is the specific requirement , where the function is converted into measurable performance or quality criteria, such as assessment criteria, level, and flexibility. Only after the need, function, and requirement are clear should the team identify the product , which is the solution provided to satisfy the defined need. Starting with "Product" would be a classic VM error because it locks the team into a solution before understanding function.
References/topics: Function Analysis Phase; Function Performance Specification; Need; Function; Specific Requirement; Product; Performance Criteria.
NEW QUESTION # 48
Which of the following activities should a VM Facilitator recommend decision-makers conduct prior to the disposition of VM proposals?
Answer: A
Explanation:
The correct answer is D. Review VM proposals . Prior to the formal disposition of VM proposals, decision- makers must first understand what has been recommended, why each proposal was developed, what value improvement is expected, and what effects the proposal may have on cost, performance, quality, schedule, and risk. SAVE's VM Standard Reference describes the Implementation Phase as the point where the sponsoring organization reviews the results of the VM study and decides which VM proposals to implement .
( )
This sequence is important. Review comes before disposition. Disposition means determining whether each VM proposal is accepted, rejected, deferred, modified, or requires additional study. The SAVE Study Guide also identifies common implementation activities as reviewing the preliminary report and then conducting an implementation meeting to determine the disposition of each value alternative. ( ) Option A occurs after proposals are accepted, because the implementation plan is developed for approved actions. Option B may occur only when information is incomplete, but it is not the normal decision-maker activity before disposition. Option C is essentially the disposition activity itself, not the step before it.
References/topics: Implementation Phase; VM Proposal Review; Preliminary Report; Disposition of Value Alternatives; Implementation Planning.
NEW QUESTION # 49
Which of the following strategies should be employed to enhance the VM study presentation?
Choose 2 answers.
Answer: A,C
Explanation:
The correct strategies are A and C because the Presentation Phase is intended to communicate value alternatives clearly enough for management and stakeholders to make informed implementation decisions.
The SAVE Study Guide identifies the Presentation Phase purpose as presenting value alternatives to management, stakeholders, and decision makers, with the fundamental question focused on helping them make more informed decisions that fit strategic plans. ( ) Therefore, a concise summary of key points is essential because it reinforces the major recommendations, benefits, risks, and implementation direction without forcing decision makers to search through excessive detail.
Visuals such as charts and graphs are also appropriate because presentation products commonly include cost- versus-worth comparisons, present-worth analysis, risk analysis, and advantages-versus-disadvantages information. ( ) These items are best communicated visually when the objective is executive understanding and decision readiness. The formal VM Standard also states that the Presentation Phase involves an oral presentation followed by a written report, with the team obtaining approval or direction for additional information. ( courses.washington.edu ) A complex presentation format would reduce clarity, and detailed technical specifications belong mainly in the Development Phase technical data package, not as the primary means of enhancing the presentation.
References/topics: Presentation Phase; Value Alternatives; Management Decision Support; Oral Presentation; Formal Report.
NEW QUESTION # 50
Which of the following methods should the VM facilitator utilize during the Creativity Phase using discursive creativity techniques?
Choose 2 answers.
Answer: B,C
Explanation:
The correct answers are C. Break problems into sub-problems and D. Utilize mind-mapping techniques to visualize connections . In the Creativity Phase, the VM team generates alternative ways to perform the selected functions. SAVE's VM guidance describes this phase as a quantity-focused idea-generation activity where ideas are developed without judgment, habit, assumed restrictions, or premature feasibility screening. ( UW Courses ) Discursive creativity techniques are structured, logical, and systematic. They help the team move through the problem deliberately rather than relying only on spontaneous brainstorming. Breaking problems into sub- problems is appropriate because it allows the facilitator to separate a complex function, process, or constraint into smaller idea-generation targets. This improves coverage and prevents the team from treating the problem too broadly. Mind-mapping is also appropriate because it visually organizes relationships among functions, causes, ideas, constraints, and possible solution paths.
Option A is incorrect because focusing on the most feasible ideas belongs to the Evaluation Phase , not Creativity. Option B is a useful facilitation rule, but it is not specifically a discursive creativity technique.
References/topics: Creativity Phase; Discursive Creativity Techniques; Idea Generation; Function-Based Alternatives; Evaluation Phase Boundary.
NEW QUESTION # 51
......
We strongly recommend using our SAVE International CVS exam dumps to prepare for the SAVE International CVS certification. It is the best way to ensure success. With our SAVE International CVS practice questions, you can get the most out of your studying and maximize your chances of passing your SAVE International CVS Exam. Itcertking SAVE International CVS practice test software is the answer if you want to score higher in the SAVE International CVS exam and achieve your academic goals.
CVS Braindump Pdf: https://www.itcertking.com/CVS_exam.html
P.S. Free & New CVS dumps are available on Google Drive shared by Itcertking: https://drive.google.com/open?id=15c5pPSB5oXqA7ZQgq7gxs4VyNituClkV