Testpdf的PRINCE2-7-Practitioner資料不僅能讓你通過考試,還可以讓你學到關於PRINCE2-7-Practitioner考試的很多知識。Testpdf的考古題把你應該要掌握的技能全都包含在試題中,這樣你就可以很好地提高自己的能力,並且在工作中更好地應用它們。Testpdf的PRINCE2-7-Practitioner考古題絕對是你準備考試並提高自己技能的最好的選擇。你要相信Testpdf可以給你一個美好的未來。
| Section | Weight | Objectives |
|---|---|---|
| PRINCE2 Principles | 12% | - Apply the seven PRINCE2 Principles in context
|
| People & Project Context Integration | 20% | - People management and collaboration
|
| PRINCE2 Practices | 40% | - Apply and tailor the seven Practices
|
| PRINCE2 Processes | 28% | - Apply the seven Processes
|
>> 新版PRINCE2-7-Practitioner題庫上線 <<
我們Testpdf網站的PRINCE2培訓資料是沒有網站可以與之比較的。它是空前絕後的真實,準確,為了幫助每位考生順利通過考試,我們的PRINCE2-7-Practitioner精英團隊不斷探索。我可以毫不猶豫的說這絕對是一份具有針對性的培訓資料。我們Testpdf網站不僅產品真實,而且價格也很合理,當你選擇我們的產品,我們還提供一年的免費更新,讓你更在充裕的時間裏準備PRINCE2-7-Practitioner考試,這樣也可以消除你對考試緊張的心理,達到一個兩全其美的辦法了。
問題 #11
RISK
Here are three items of information relating to the 'risk' practice.
In which management product (A-E) should each item be recorded?
Choose only ONE management product for each item of information. Each management product may be used once, more than once, or not at all.
答案:A,E
解題說明:
The correct mapping is Item 1 - A; Item 2 - E; Item 3 - E .
Item 1 belongs in the risk register. The cracked pane itself is an existing problem and therefore an issue.
However, the item explicitly identifies a separate uncertainty : the supplier may fail to meet the future replacement date, potentially delaying later work. Because this is an uncertain future event affecting project objectives, it is a risk and should be recorded in the risk register.
Item 2 belongs in the risk management approach. It describes the agreed procedure and frequency for reviewing project risks. The risk management approach defines how risk management will be performed, including responsibilities, procedures, review arrangements, scales, reporting, and supporting techniques.
Item 3 also belongs in the risk management approach. A red-amber-green classification is part of the project's agreed risk assessment and prioritization framework rather than information about an individual risk.
The distinction is fundamental: the risk register contains individual identified risks and their management information , whereas the risk management approach defines the project's overall method, procedures, scales, responsibilities, and controls for managing risk .
PRINCE2 7 reference topics: Risk practice; risk register; risk management approach; uncertainty; risk assessment; risk review arrangements; risk scales.
問題 #12
While the project mandate is being prepared, the Mayor asks the LOB Portfolio Director, acting at the business layer, to select and appoint a suitable project executive for LouisShopping.
Is this an appropriate application of the organization practice, and why?
答案:C
解題說明:
The correct answer is B . PRINCE2 distinguishes the business layer from the project management layer. The business layer commissions projects, establishes the broader organizational context, and appoints an appropriate project executive who will represent the business interest and become ultimately accountable for the project's success within the project board.
The scenario explicitly states that the LOB Portfolio Director is acting at the business layer . Consequently, selecting and appointing an appropriate project executive is consistent with the responsibilities associated with that level of governance.
Option A is too broad. The appointment is not appropriate merely because the Mayor can delegate the activity to any senior stakeholder. The suitability arises because the Portfolio Director is acting as the relevant business-layer representative. Option C incorrectly assumes that the Mayor must personally make the appointment because of the project's civic significance; PRINCE2 does not impose such a requirement.
Option D similarly assigns the responsibility automatically to the Head of Portfolio Office, even though the scenario explicitly identifies the Portfolio Director as the relevant business-layer representative.
The key distinction is therefore between business-layer governance and project-level management. The project executive is appointed from the business layer and subsequently leads the project board.
PRINCE2 7 reference topics: Organization practice; business layer; project executive; commissioning a project; project board structure and accountability.
問題 #13
Before the end of stage 2, the project board authorizes a change that adds more trees and seating to the external landscaping. The change can be delivered in stage 3 without any forecast breach of project tolerance.
While preparing the next stage plan, the project manager incorporates the additional products and work, updates the relevant product descriptions and product register entries, and reviews whether the project initiation documentation needs to be updated.
Is this an appropriate application of 'prepare the next stage plan', and why?
答案:B
解題說明:
The correct answer is A . When preparing the next stage plan, the project manager must incorporate all relevant authorized changes that affect the products or work to be undertaken in the forthcoming management stage. The stage plan must represent the current authorized baseline rather than an obsolete version of what was originally intended.
The additional trees and seating have already been authorized by the project board, and the change can be incorporated without a forecast breach of overall project tolerance. The project manager should therefore reflect the additional products and activities in the stage 3 plan, revise affected product descriptions and product-register information, and determine whether corresponding elements of the project initiation documentation need updating.
Option B is incorrect because an exception plan is not required for every authorized change. Exception planning is used where agreed tolerance is forecast to be exceeded and the higher management level requests a replacement plan. The scenario explicitly states that project tolerance is not forecast to be breached. Option C incorrectly introduces mandatory re-authorization by the business layer. Option D is incorrect because preparing the next stage plan is a project manager responsibility; project assurance may independently review the resulting information but does not prepare it instead.
PRINCE2 7 reference topics: Managing a stage boundary; prepare the next stage plan; authorized changes; product descriptions; product register; PID maintenance; exception plans.
問題 #14
During stage 3, several BuildyBrick subcontractors are working on different work packages. The project manager is concerned that lessons identified by one team will not reach the others and could lead to rework, delay or additional cost. The project manager therefore holds a fortnightly cross-team 'lunch and learn' session.
Is this an appropriate application of the 'learn from experience' principle, and why?
答案:B
解題說明:
The correct answer is A . The learn from experience principle requires learning to occur throughout the project lifecycle, not merely during initiation or closure. Lessons should be sought, recorded where appropriate, communicated to those who can use them, and incorporated into current or future decisions and ways of working.
The fortnightly cross-team session directly addresses the project manager's concern that lessons emerging in one work package may otherwise remain isolated. Sharing them across teams allows corrective knowledge to be applied while it can still prevent rework, delay, cost escalation, or repeated mistakes. Official PeopleCert material emphasizes that lessons should be considered before starting, captured during delivery, and actively applied; simply recording a lesson without changing future behavior does not constitute effective learning.
Option B describes another legitimate source of lessons-previous projects-but does not explain the specific benefit demonstrated in the scenario, which concerns lessons arising across teams during the current stage .
Option C contradicts PRINCE2's expectation that lessons improve project performance rather than being regarded as non-productive overhead. Option D incorrectly postpones learning until the end of the stage, when the opportunity to prevent immediate repetition may already have passed.
PRINCE2 7 reference topics: Learn from experience; lessons log; knowledge sharing; applying lessons throughout the project lifecycle.
問題 #15
During the 'starting up a project' process, the Business Opportunities Director appoints the Regeneration Manager as project manager and states that the portfolio's standard role description will apply without discussion. The Regeneration Manager asks to confirm the responsibilities, but the Director refuses because the project is urgent.
Is the refusal an appropriate application of the 'define roles, responsibilities and relationships' principle, and why?
答案:A
解題說明:
The correct answer is C . PRINCE2 requires project roles, responsibilities, authority, accountability, and working relationships to be sufficiently clear for the people performing those roles to understand what is expected of them. A standard organizational role description can provide a useful baseline, but it does not remove the need to establish how the role applies within the particular project context.
The project manager is responsible for day-to-day management within the authority delegated by the project board. Consequently, the Regeneration Manager must understand the specific responsibilities, decision rights, interfaces, tolerances, reporting expectations, and relationships relevant to this project. Urgency does not justify leaving those matters ambiguous. PeopleCert describes clear roles and responsibilities as fundamental to accountability, reduced ambiguity, effective communication, and project success.
Option A incorrectly treats a generic portfolio description as sufficient in every circumstance. Option B identifies a legitimate project initiation responsibility but does not justify refusing clarification. Option D is incorrect because portfolio management does not replace the PRINCE2 project-level organization and governance responsibilities.
The principle is therefore being applied incorrectly: standardized descriptions may support implementation, but the individual performing the project management role still needs a clear, project-specific understanding and acceptance of the responsibilities assigned.
PRINCE2 7 reference topics: Principles - Define roles, responsibilities and relationships; Organization practice; Starting up a project; role clarity and accountability.