Nowadays, using electronic materials to prepare for the exam has become more and more popular, so now, you really should not be restricted to paper materials any more, our electronic PRINCE2Practitioner exam torrent will surprise you with their effectiveness and usefulness, and the pass rate of PRINCE2Practitioner Practice Test is high as 98% to 100%. I can assure you that you will pass the exam as well as getting the related certification under the guidance of our training materials PRINCE2Practitioner as easy as pie.
| Certification Vendor: | AXELOS / PeopleCert |
|---|---|
| Exam Name: | PRINCE2® Project Management Practitioner (Version 7) |
| Exam Number: | PRINCE2-Practitioner |
| Exam Duration: | 150 minutes |
| Certificate Validity Period: | 3 years |
| Passing Score: | 60% (42 out of 70 marks) |
| Related Certifications: | PRINCE2 Agile PRINCE2 Foundation PMP MSP CAPM |
| Real Exam Qty: | 70 |
| Available Languages: | English, Japanese, Polish, Portuguese, Spanish, Chinese (Simplified), German, Italian, Dutch, French, Arabic |
| Exam Format: | Scenario-based objective test, Open-book (official PRINCE2 manual only), No negative marking, Multiple-choice |
| Exam Price: | $450 - $550 USD / £470 - £520 GBP / €395 - €450 EUR |
| Recommended Training: | Official PRINCE2 Training Providers |
| Exam Registration: | PeopleCert Official Registration |
| Sample Questions: | PRINCE2 PRINCE2Practitioner Sample Questions |
| Exam Way: | Online remote proctored exam or authorized test center |
| Pre Condition: | Must hold valid PRINCE2 Foundation (6th or 7th edition), or equivalent: PMP, CAPM, IPMA A-D, or other recognized project management qualifications |
| Official Syllabus URL: | https://www.peoplecert.org/certifications/axelos/prince2/project-management/practitioner |
>> PRINCE2Practitioner Test Question <<
Our specialists check whether the contents of PRINCE2Practitioner real exam are updated every day. If there are newer versions, they will be sent to users in time to ensure that users can enjoy the latest resources in the first time. In such a way, our PRINCE2Practitioner guide materials can have such a fast update rate that is taking into account the needs of users. Users using our PRINCE2Practitioner Study Materials must be the first group of people who come into contact with new resources. When you receive an update reminder from PRINCE2Practitioner practice questions, you can update the version in time and you will never miss a key message.
PRINCE2 Practitioner certification exam is a 2.5-hour multiple-choice exam consisting of 68 questions. PRINCE2Practitioner Exam is designed to test a candidate's ability to apply the PRINCE2 methodology in different project scenarios. It covers topics such as project planning, risk management, quality management, change management, and project governance. Passing the PRINCE2 Practitioner certification exam requires a minimum score of 55%. Successful candidates are awarded the PRINCE2 Practitioner certification, which is valid for three years.
NEW QUESTION # 56
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom- based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:
End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company' s document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
During stage 3, the operational staff that handle course bookings asked for the project scope to be increased for an online booking function. The additional product has been as it will enable them to process bookings more quickly and accurately.
Is this an appropriate application of the 'focus on products' principle, and why?
Answer: C
NEW QUESTION # 57
ABC Company has decided to include the Health and Safety Training Project in a programme to support their strategy to deliver globally. The programme team has provided the detailed business justification and, as a result, the project board has decided that the business case will not need refining further during the
'initiating a project' process.
Is this an appropriate action for the project board, and why?
Answer: C
NEW QUESTION # 58
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:
Do nothing.
Re-engineer selected business functions.
Outsource selected business functions.
The feasibility study concluded that there was a case for outsourcing the MFH Information Technology
Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:
One service provider should be contracted to provide the services currently provided by the
Information Technology Division and the Facilities Division.
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems and
operating models, plus an outline Business Case for the required project. The external consultants
also made the following recommendations for the management of the project:
Use PRINCE2.
Set up the project with 4 management stages:
Stage 1. Standard PRINCE2 initiation activities.
Stage 2. Create detailed designs (future organization, processes, systems and operating
models) and the service level agreement between MFH and the future service
provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run
trial period.
Initial estimates indicated that the project would cost (GBP)2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the
recommendations as a basis for the project. There is an expected saving of (GBP)20m over 10 years.
The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.
Which 2 statements should be recorded under the Expected benefits heading?
Answer: B,E
Explanation:
Reference: http://www.whatisprince2.net/prince2-theme-business-case.php
NEW QUESTION # 59
Scenario
Additional Information
Product Description
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors) Introduction
1. This document defines the approach to be taken to achieve the required quality levels during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Which statement applies to the Records section?
Answer: B
NEW QUESTION # 60
A concern about possible subsidence damage has been recorded as an issue.
Is this an appropriate application of the issues practice, and why?
Answer: C
Explanation:
PRINCE2 defines an issue as any event that has happened, is happening, or is expected to happen and requires management action. The concern raised represents a potential problem requiring assessment.
Recording it as an issue is correct and enables structured evaluation.