Candidates can also check the explanations for the answers to have more understanding of the PRINCE2 PRINCE2Practitioner questions that are asked on the PRINCE2Practitioner practice test by Real4exams You can customize the PRINCE2 PRINCE2Practitioner exam questions and time for the PRINCE2Practitioner practice exam on the software. Assessing their PRINCE2 PRINCE2Practitioner Exam Preparation and speed on the practice exam software helps candidates in making required improvements and succeeding at the PRINCE2 PRINCE2Practitioner exam. The software by Real4exams gives the candidates the results and progress reports to help them monitor their performance for the PRINCE2 PRINCE2Practitioner exam.
| Section | Weight | Objectives |
|---|---|---|
| PRINCE2 Themes | 40% | - Progress - Quality - Business Case - Change - Organization - Risk - Plans |
| PRINCE2 Processes | 30% | - Controlling a Stage - Managing Product Delivery - Managing a Stage Boundary - Directing a Project - Initiating a Project - Starting up a Project - Closing a Project |
| PRINCE2 Principles | 20% | - Tailor to suit the project environment - Continued business justification - Manage by exception - Defined roles and responsibilities - Manage by stages - Learn from experience - Focus on products |
| Tailoring PRINCE2 | 10% | - Adapting to project size, complexity and context - Tailoring principles, themes and processes |
>> PRINCE2 PRINCE2Practitioner Exam Revision Plan <<
We offer you free update for one year if you buy PRINCE2Practitioner study guide materials from us, that is to say, in the following year, you can obtain the latest information about the PRINCE2Practitioner study materials for free. In addition, with the experienced experts to compile, PRINCE2Practitioner exam dumps is high-quality, and it contain most of knowledge points of the exam, and you can also improve your ability in the process of learning. PRINCE2Practitioner Exam Dumps of us have received many good feedbacks from our customers, they thanks us for helping them pass the exam successfully.
NEW QUESTION # 174
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:
End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
Based on lessons from previous projects that used the ABC Company standard development model, the project board has set low cost and time tolerances for stage 2. As a result, the project manager plans to set very low tolerances for time and cost for all work packages to be carried out during stage 2.
Is this an appropriate application of the 'manage by exception' principle, and why?
Answer: C
NEW QUESTION # 175
Having created the Issue Report and analyzed the impact of removing the Facilities Division from the scope of
the Outsourcing project, the proposed option exceeds tolerance. \Nhat is the next action the Project Manager
should consider?
Answer: D
NEW QUESTION # 176
Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.
Which 2 statements should be recorded under either the Records or Reporting headings?
Answer: A,D
NEW QUESTION # 177
Having completed designing the plan, in which order should the next steps take place to produce a plan?
1. Prepare Estimates
2. Define and analyze Products
3. Prepare the schedule
4. Identify activities and dependencies
Answer: C
NEW QUESTION # 178
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for
this question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are
being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago
the professional photographer produced the photo session schedule based on the operational staff schedule.
The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the E500 change budget has been used to date and this is available for the stage.
Which 2 statements apply to the Budgets section?
Answer: C,D
Explanation:
Explanation/Reference:
Plans Theme
Question Set 2
NEW QUESTION # 179
......
Our web backend is strong for our PRINCE2Practitioner study braindumps. No matter how many people are browsing our websites at the same time, you still can quickly choose your favorite PRINCE2Practitioner exam questions and quickly pay for it. There has no delay reaction of our website. So you can begin your pleasant selecting journey on our websites. And you will find our PRINCE2Practitioner practice materials are easy to download.