Do not waste further time and money, get real SAVE International CVS pdf questions and practice test software, and start SAVE International CVS test preparation today. Dumpkiller will also provide you with up to 365 days of free Certified Value Specialist exam questions updates, It will just need to take one or two days to practice SAVE International CVS Test Questions and remember answers. You will free access to our test engine for review after payment.
| Section | Weight | Objectives |
|---|---|---|
| Tools and Techniques | 20% | - Function analysis system technique (FAST) - Creative thinking and idea generation methods - Cost analysis and worth assessment - Decision-making and evaluation tools |
| Value Methodology Principles and Concepts | 25% | - Value index, function and cost relationship - Definition and core concepts of Value - Origins, development and application scope of Value Methodology |
| Leadership and Facilitation | 15% | - Stakeholder management and communication - Leading value study teams - Workshop facilitation skills |
| Value Methodology Job Plan | 30% | - Function analysis phase - Information phase - Creative phase - Evaluation phase - Presentation and implementation phase - Development phase - Preparation phase |
| Standards, Ethics and Application | 10% | - Professional ethics and responsibilities - Application in different industries and sectors - SAVE International standards and guidelines |
Dumpkiller is a website engaged in the providing customer CVS VCE Dumps and makes sure every candidates passing actual test easily and quickly. We have a team of IT workers who have rich experience in the study of SAVE International dumps torrent and they check the updating of SAVE International top questions everyday to ensure the accuracy of exam collection.
NEW QUESTION # 144
Which of the following methods should the VM facilitator utilize during the Creativity Phase using discursive creativity techniques?
Choose 2 answers.
Answer: A,D
Explanation:
The correct answers are C. Break problems into sub-problems and D. Utilize mind-mapping techniques to visualize connections . In the Creativity Phase, the VM team generates alternative ways to perform the selected functions. SAVE's VM guidance describes this phase as a quantity-focused idea-generation activity where ideas are developed without judgment, habit, assumed restrictions, or premature feasibility screening. ( UW Courses ) Discursive creativity techniques are structured, logical, and systematic. They help the team move through the problem deliberately rather than relying only on spontaneous brainstorming. Breaking problems into sub- problems is appropriate because it allows the facilitator to separate a complex function, process, or constraint into smaller idea-generation targets. This improves coverage and prevents the team from treating the problem too broadly. Mind-mapping is also appropriate because it visually organizes relationships among functions, causes, ideas, constraints, and possible solution paths.
Option A is incorrect because focusing on the most feasible ideas belongs to the Evaluation Phase , not Creativity. Option B is a useful facilitation rule, but it is not specifically a discursive creativity technique.
References/topics: Creativity Phase; Discursive Creativity Techniques; Idea Generation; Function-Based Alternatives; Evaluation Phase Boundary.
NEW QUESTION # 145
Which of the following are key considerations when selecting an in-person meeting room?
Choose 4 answers.
Answer: A,C,D,F
Explanation:
The correct answers are C, D, E, and F . Selecting an in-person VM workshop room is a Preparation Phase responsibility because the facilitator must create conditions that support team interaction, visible work products, and uninterrupted execution of the Job Plan. The SAVE Study Guide identifies Pre-Workshop activities as planning and organizing the Value Study, including determining "study dates, times, location and other logistical needs." ( ) It also emphasizes that the VM Job Plan supports team synergy through a structured process, not isolated individual opinions. ( ) A U-shaped table arrangement supports facilitation because participants can see one another, engage in discussion, and view flip charts or projected material. Availability for the full workshop duration is essential because the Study Guide notes that sufficient time must be allotted to apply the VM process and document findings; losing the room interrupts phase continuity. ( ) Windows and wall space matter because VM workshops rely heavily on posted functions, FAST diagrams, idea lists, evaluation matrices, and proposal development materials. Temperature controls are also important because an uncomfortable environment reduces concentration and participation during long workshop sessions. Chair comfort and site proximity may be useful, but they are secondary compared with room layout, uninterrupted access, display/workspace, and environmental control.
References/topics: Preparation Phase; Pre-Workshop Logistics; VM Facilitation; Workshop Environment; Team Dynamics.
NEW QUESTION # 146
Between carpet and vinyl, which is a better value option for the owner over the service life of the products?
Answer: A
Explanation:
The correct answer is A. Carpet $120,000 . This question applies life-cycle cost comparison , which is commonly used in the Development Phase when VM alternatives are being analyzed for economic feasibility and owner value. The better value option is not determined by the lowest initial cost alone; it must include installed cost, maintenance cost, recurring service cost, and service life impacts.
For carpet:
Installed cost = 1,000 sq. m × $30 = $30,000 .
Vacuum maintenance = $500/month × 12 months × 10 years = $60,000 .
Annual shampoo = $3,000/year × 10 years = $30,000 .
Total carpet life-cycle cost = $30,000 + $60,000 + $30,000 = $120,000 .
For vinyl over a comparable 10-year ownership period:
Installed cost = 1,000 sq. m × $10 = $10,000 .
Vacuum maintenance = $400/month × 12 × 10 = $48,000 .
Strip and wax = $1,000/month × 12 × 10 = $120,000 .
Total vinyl cost = $178,000 .
Although vinyl has a lower initial cost, its recurring monthly strip-and-wax cost makes it more expensive.
Therefore, carpet provides the better value.
References/topics: Development Phase; Life-Cycle Costing; Economic Evaluation; Alternative Comparison; Owner Value.
NEW QUESTION # 147
Which of the following could a VM facilitator say to stimulate creativity?
Choose 2 answers.
Answer: A,D
Explanation:
The correct answers are B and C . In the Creativity Phase , the VM facilitator's role is to stimulate open, unrestricted idea generation. The SAVE Value Methodology Standard states that the Creative Phase aims to develop a large quantity of ideas for performing each selected function, and that this effort should be unconstrained by habit, tradition, negative attitudes, assumed restrictions, and specific criteria. It also states that judgment and evaluation are suspended during this phase. ( courses.washington.edu ) Option B is effective because it invites reflection on missed opportunities and encourages participants to identify improvements without immediately judging feasibility. Option C is also effective because it removes normal constraints and encourages broad, imaginative thinking about the study subject. This matches the Creative Phase principle that free flow of thoughts and ideas is required, without criticism or premature evaluation. ( courses.washington.edu ) Option A is not ideal because it introduces authority influence and may cause the team to conform to the project manager's view. Option D restricts open participation and weakens creative flow.
References/topics: Creativity Phase; VM Facilitation; Divergent Thinking; Idea Generation; Suspending Judgment.
NEW QUESTION # 148
Which of the following are key elements of a risk register?
Choose 2 answers.
Answer: A,B
Explanation:
The correct answers are B and D . A risk register is used to document, organize, and evaluate risks so that the VM team can understand how uncertainty may affect proposed alternatives. The two essential risk-register elements shown in the choices are probability of occurrence and impact on the scope . Probability identifies how likely the risk is to happen. Impact identifies what the consequence will be if the risk occurs, including possible effects on scope, cost, schedule, quality, performance, implementation, or stakeholder acceptance.
In the VM Job Plan, risk thinking becomes especially important when ideas move from creativity into evaluation and development. At that point, alternatives are no longer just possibilities; they must be tested for feasibility, consequences, and implementation exposure. A risk with high probability and high impact demands more attention than one with low probability and minor impact.
Option A, performance criteria , is related to evaluation criteria, not a core risk-register field. Option C, function of the risk , is not a standard risk-register element. Functions belong to Function Analysis and are normally expressed in verb-noun format, while risks are documented as uncertain events or conditions.
References/topics: Evaluation Phase; Development Phase; Risk Register; Risk Probability; Risk Impact; VM Proposal Screening.
NEW QUESTION # 149
......
If you buy online classes, you will need to sit in front of your computer on time at the required time; if you participate in offline counseling, you may need to take an hour or two of a bus to attend class. But if you buy CVS test guide, things will become completely different. Unlike other learning materials on the market, CVS torrent prep has an APP version. You can download our app on your mobile phone. And then, you can learn anytime, anywhere. Whatever where you are, whatever what time it is, just an electronic device, you can do exercises. With CVS Torrent prep, you no longer have to put down the important tasks at hand in order to get to class; with CVS exam questions, you don’t have to give up an appointment for study.
CVS Real Testing Environment: https://www.dumpkiller.com/CVS_braindumps.html