P.S. Free & New CCM dumps are available on Google Drive shared by Dumpkiller: https://drive.google.com/open?id=1QkDMnWNNyua3962eevFTqDPBi0tJVTeX
Our CCM test braindumps are in the leading position in the editorial market, and our advanced operating system for CCM latest exam torrent has won wide recognition. As long as you choose our CCM exam questions and pay successfully, you do not have to worry about receiving our learning materials for a long time. We assure you that you only need to wait 5-10 minutes and you will receive our CCM Exam Questions which are sent by our system. When you start learning, you will find a lot of small buttons, which are designed carefully. You can choose different ways of operation according to your learning habits to help you learn effectively.
| Section | Objectives |
|---|---|
| Rehabilitation and Disability Management | - Return-to-work planning - Rehabilitation principles |
| Psychosocial and Support Systems | - Community resources and support systems - Psychosocial assessment |
| Care Delivery and Reimbursement Methods | - Insurance and reimbursement structures - Healthcare delivery systems |
| Ethics, Legal, and Regulatory Aspects | - Professional ethics in case management - Legal and regulatory compliance |
| Quality and Outcomes Evaluation | - Outcome measurement and evaluation - Quality improvement methods |
As is known to us, there are best sale and after-sale service of the CCM certification training materials all over the world in our company. Our company has employed a lot of excellent experts and professors in the field in the past years, in order to design the best and most suitable CCM Latest Questions for all customers. More importantly, it is evident to all that the CCM training materials from our company have a high quality, and we can make sure that the quality of our CCM exam questions will be higher than other study materials in the market.
NEW QUESTION # 52
You are the Contract Manager of the Employer's Representative in a Thermal Power Plant Project. The Contract for this project is EPC Turnkey Contract using the FIDIC Silver Book (edition 2017) with a Contract Price of 28 million USD. The Employer's Requirements require that: "the Contractor design in accordance with international and national technical regulations, and standards, [etc.]".
For piling works, the Employer's Requirements state that the Contractor will design according to a specific national standard for piling works NTS-PW-01. After all piles for the jetty have been installed, a pile load test on lateral bearing capacity shows that actual lateral bearing capacity is much lower than the calculated lateral bearing capacity. It was later revealed by the Technical Standard Committee that there was a typo mistake during preparation of the NTS-PW-01 (translated from a foreign standard). The lateral bearing capacity of installed piles had been substantially overestimated as a result of this typo. Contractor submits a claim for
200,000 USD regarding extra costs for installing additional piles as a result of errors in the Employer's Requirements.
In the hydrological information of Site Data provided by the Employer, the annual high water level is 4.0m.
However, during the design stage, with updated data from local stations along the rivers, the Contractor found out there was a mistake in the calculation. The annual high water level should be 4.5m. As a result, the Contractor has to design and build additional flood walls along the river to protect the Plant from flooding.
The Contractor claims an amount of 300,000 USD to construct the flood wall, based on Unforeseeable difficulties.
As the Employer's Representative, after you have consulted with both Parties but failed to reach agreement, you will make a fair determination of the Claims of the Contractor.
In your "Notice of the Employer's Representative's determination", what is your determination for the Contractor?
Answer: C
Explanation:
Both claims are valid under the Silver Book principles:
The error in the Employer's Requirements (typo in NTS-PW-01) leads to entitlement for additional piling costs.
The unforeseen hydrological data causing additional flood protection works qualify as unforeseeable physical conditions entitling the Contractor to compensation.
Hence, Option D is correct - the Contractor is entitled to both claims.
References:
FIDIC Silver Book 2017 Edition, Sub-Clause 4.1 (Employer's Requirements) and Sub-Clause 4.12 (Unforeseeable Physical Conditions) FIDIC Contract Manager Study Guide, Module on Claims and Employer's Requirements
NEW QUESTION # 53
Which one answer holds two statements that are both correct with regards to risks and key considerations regarding the Golden Principles?
Answer: A
Explanation:
Comprehensive and Detailed Explanation:
Option A correctly reflects Golden Principles emphasizing the Employer's objective of obtaining value for money and the importance of avoiding disputes as much as possible.
Other options either misrepresent the balanced nature of FIDIC principles or promote unfair or unbalanced positions.
References:
FIDIC Contract Management Guidelines - Golden Principles
FIDIC Contract Manager Study Guide, Module on Legal and Ethical Considerations
NEW QUESTION # 54
The FIDIC Red Book (edition 1999) deals with Value Engineering Clause. It follows from this clause that the Contractor shall give notice to the Engineer with supporting particulars. Upon receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 to agree or determine this Cost, which shall be included in the Contract Price.
Answer: A
Explanation:
Under FIDIC Red Book (1999), the Value Engineering Clause requires the Contractor to notify the Engineer with full details and cost implications when proposing Value Engineering changes. The Engineer then follows the Variation procedure in Sub-Clause 3.5 to agree or determine the cost adjustment, which will be reflected in the Contract Price.
This ensures transparent handling of Value Engineering proposals and proper contractual adjustments.
References:
FIDIC Red Book 1999 Edition, Sub-Clause 13.1 - Value Engineering
FIDIC Contract Manager Study Guide, Module on Variations and Value Engineering
NEW QUESTION # 55
You are the Contract Manager for the Engineer in a highway project using FIDIC Red Book (edition 1999).
There is a Schedule of cost indexation included in the Contract. The project must be completed by 31 December of this year. If the Contractor fails to complete the Works by then, how will the adjustment of prices take place thereafter?
Answer: D
Explanation:
Comprehensive and Detailed Explanation:
Under FIDIC Red Book 1999, price adjustments after the Time for Completion are based on the indices or prices applicable on the date 49 days before the expiry of the Time for Completion, not the current index. This prevents the Contractor from benefiting from price fluctuations after the contract period.
This clause ensures fairness by locking the price basis as of a fixed reference date, protecting the Employer from increased costs due to delays.
References:
FIDIC Red Book 1999 Edition, Sub-Clause 13.8 - Adjustments for Changes in Cost FIDIC Contract Manager Study Guide, Module on Price Adjustment
NEW QUESTION # 56
Under both FIDIC Yellow Book (YB) and Silver Book (SB) (edition 1999), if the Engineer (YB) / Employer (SB) instructs the Contractor based on Sub-Clause 8.6 to provide a revised programme, the acceptance by the Engineer (YB) / Employer (SB) of a revised programme with a completion within Time of Completion entitles the Contractor to a payment of the needed extra costs. Is this statement true or false?
Answer: A
Explanation:
This statement is false. Acceptance of a revised programme that shows completion within the Time for Completion does not automatically entitle the Contractor to extra payment. The Contractor must demonstrate additional costs arising from the instruction or circumstances to claim payment.
The acceptance of a compliant programme is a scheduling and administrative matter, not a compensation guarantee.
References:
FIDIC Yellow and Silver Books 1999 Editions, Sub-Clause 8.6 - Revised Programme FIDIC Contract Manager Study Guide, Module on Claims and Payment
NEW QUESTION # 57
......
The field of information technology has seen multiple advancements lately. Reputed companies around the globe have set the Certified Case Manager Certification Exam (CCM) CCM certification as criteria for multiple well-paid job roles. Only CCM certified will easily get high-paying posts in popular companies. Additionally, a Medical Professional CCM Certification holder can climb the career ladder and get promotions within the current organization.
Pass4sure CCM Pass Guide: https://www.dumpkiller.com/CCM_braindumps.html
DOWNLOAD the newest Dumpkiller CCM PDF dumps from Cloud Storage for free: https://drive.google.com/open?id=1QkDMnWNNyua3962eevFTqDPBi0tJVTeX