We have 24/7 Service Online Support services, and provide professional staff Remote Assistance at any time if you have questions on our CAPM exam braindumps. Besides, if you need an invoice of our CAPM practice materials please specify the invoice information and send us an email. Online customer service and mail Service is waiting for you all the time. And you can download the trial of our CAPM training engine for free before your purchase.
| Section | Weight | Objectives |
|---|---|---|
| Topic 1: Predictive, Plan-Based Methodologies | 30% | - Plan-Driven Process Implementation
|
| Topic 2: Agile and Hybrid Methodologies | 20% | - Agile Estimation and Planning
|
| Topic 3: Project Management Fundamentals and Core Concepts | 50% | - Project Communications Management
|
To prepare for CAPM exam, you do not need read a pile of reference books or take more time to join in related training courses, what you need to do is to make use of our Real4exams exam software, and you can pass the exam with ease. Our exam dumps can not only help you reduce your pressure from CAPM Exam Preparation, but also eliminate your worry about money waste. We guarantee to give you a full refund of the cost you purchased our dump if you fail CAPM exam for the first time after you purchased and used our exam dumps. So please be rest assured the purchase of our dumps.
NEW QUESTION # 1025
Which of the following documents allows the project manager to assess risks that may require near term action?
Answer: A
Explanation:
Section: Volume D
Explanation:
11.3.2.5 Risk Urgency Assessment
Risks requiring near-term responses may be considered more urgent to address. Indicators of priority may include probability of detecting the risk, time to affect a risk response, symptoms and warning signs, and the risk rating. In some qualitative analyses, the assessment of risk urgency is combined with the risk ranking that is determined from the probability and impact matrix to give a final risk severity rating.
NEW QUESTION # 1026
What risk response strategy involves removing high- risk scope elements from a project?
Answer: D
Explanation:
In accordance with the PMBOKGuide, the Plan Risk Responses process identifies several strategies for dealing with negative risks or threats.
* Avoid: Risk avoidance is a strategy where the project team acts to eliminate the threat or protect the project from its impact. This typically involves changing the project management plan to eliminate the risk entirely. Common examples of avoidance include extending the schedule, changing the strategy, or, as mentioned in the question, reducing or removing scope that is deemed too high-risk for the organization to manage.
* Transfer: This involves shifting the impact and ownership of a threat to a third party (e.g., through insurance, performance bonds, or warranties). It does not eliminate the risk from the project scope; it simply makes another party responsible for the financial consequences.
* Exploit: This is a strategy used for positive risks (opportunities), not threats. It seeks to ensure that the opportunity is realized.
* Accept: This strategy indicates that the project team has decided not to act against a risk. It can be passive (doing nothing) or active (establishing a contingency reserve).
Per PMI standards, when a project manager decides that a specific technical deliverable or scope element is beyond the team ' s risk appetite, the most effective way to " Avoid " that risk is to remove that requirement from the project scope statement.
NEW QUESTION # 1027
Which Control Scope input is compared to actual results to determine if corrective action is required for the project?
Answer: B
Explanation:
According to the PMBOKGuide, the Control Scope process is the process of monitoring the status of the project and product scope and managing changes to the scope baseline.
Scope Baseline: This is the primary input used for comparison. To determine if the project is " on track " or if corrective action is needed, the project manager compares the actual work performed (Work Performance Data) against the Scope Baseline.
* The Baseline Components: The scope baseline includes the Project Scope Statement, the WBS, and the WBS Dictionary. If the work being completed does not align with these three documents, it indicates a variance.
* Variance Analysis: This tool and technique is used to determine the cause and degree of difference between the baseline and actual performance. If the variance is significant (e.g., " scope creep " where unauthorized work is being added), a change request for corrective action must be initiated through the Perform Integrated Change Control process.
Analysis of Other Options:
B). Scope management plan: This document describes how the scope will be defined, developed, monitored, controlled, and validated. It provides the " instructions " for managing scope, but it does not contain the specific " yardstick " (the baseline) used for performance comparison.
* C. Change management plan: This plan defines the process for managing changes across the entire project. While it tells you how to process a corrective action once identified, it is not the document used to identify the need for that action via result comparison.
* D. Cost baseline: This is used in the Control Costs process. While scope and cost are related (the " Triple Constraint " ), you would not use a cost baseline to determine if the scope of the project requires corrective action.
NEW QUESTION # 1028
Which of the following correctly explains the term "progressive elaboration'?
Answer: A
Explanation:
Explanation/Reference:
Explanation:
Progressive Elaboration. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
NEW QUESTION # 1029 
When would be the most appropriate time to address the issue raised on the iteration review?
Answer: B
Explanation:
The issue raised during the iteration review - concerns about how decisions were made without team involvement - is best addressed in the sprint retrospective. The retrospective is specifically designed to reflect on team processes, improve collaboration, and discuss what went well and what needs to be improved.
NEW QUESTION # 1030
......
n modern society, whether to obtain CAPM certification has become a standard to test the level of personal knowledge. Many well-known companies require the CAPM certification at the time of recruitment. Whether you're a student or a white-collar worker, you're probably trying to get the certification in order to get more job opportunities or wages. If you are one of them, our CAPM Exam Guide will effectively give you a leg up.
Exam CAPM Certification Cost: https://www.real4exams.com/CAPM_braindumps.html
What's more, part of that Real4exams CAPM dumps now are free: https://drive.google.com/open?id=1c80AaCBkpwxBSj3yGP8Eu3FmQ0RMmx-y