P.S. Free 2026 Medical Professional CCM dumps are available on Google Drive shared by Free4Torrent: https://drive.google.com/open?id=1UNkYwBwNm6v9fDVB_16NO9f38LFouVha
Our website focus on helping candidates pass Medical Professional certification exams with our Valid CCM Practice Questions and detailed test answers. The most reliable CCM dumps pdf are written by our professional IT experts who have rich experience in actual test. And you will be enjoyed one-year free updating after you make payment.
| Section | Objectives |
|---|---|
| Topic 1: Rehabilitation and Disability Management | - Return-to-work planning - Rehabilitation principles |
| Topic 2: Ethics, Legal, and Regulatory Aspects | - Professional ethics in case management - Legal and regulatory compliance |
| Topic 3: Psychosocial and Support Systems | - Psychosocial assessment - Community resources and support systems |
| Topic 4: Care Delivery and Reimbursement Methods | - Healthcare delivery systems - Insurance and reimbursement structures |
| Topic 5: Quality and Outcomes Evaluation | - Quality improvement methods - Outcome measurement and evaluation |
As long as you face problems with the CCM exam, our company is confident to help you solve. Give our CCM practice quiz a choice is to give you a chance to succeed. We are very willing to go hand in hand with you on the way to preparing for CCM Exam. And we have three different versions of our CCM learning materials, you will find that it is so interesting and funny to study with our study guide.
NEW QUESTION # 133
You are the Contract Manager of the Engineer in a condominium project under FIDIC Yellow Book (edition
2017), with Time for Completion of 5 months.
The Contractor received a Letter of Acceptance on 1 May 2022. The Contract Agreement was signed on 1 June 2022. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, but it shall be no later than 14 days after the signing of the Contract Agreement, subject to the issuance of the construction permit.
1 July 2022 is the first day the Engineer was at Site. On the same day, the Engineer issued a Notice to the Contractor that the Commencement Date shall be 15 July 2022. However, the construction permit was issued only on 1 August 2022.
The Project was completed on 1 December 2022. After completion, the Employer submitted a claim for Delay Damages. Following consultations, the Parties could not reach agreement on the Commencement Date.
What is the correct Commencement Date?
Answer: A
Explanation:
According to the FIDIC Yellow Book 2017, the Commencement Date is the date notified by the Engineer as the date on which the Contractor shall start the execution of the Works (Sub-Clause 8.1). In this case, although the Engineer notified 15 July 2022 as the Commencement Date, it was subject to the issuance of the construction permit. Since the construction permit was only obtained on 1 August 2022, work could not legally commence before that date.
FIDIC recognizes that the Contractor cannot be expected to start before all necessary permissions are granted.
Hence, the effective Commencement Date must be the earliest date on which the Contractor can legally commence work, i.e., the date when the permit was issued (1 August 2022). The contract's requirement that the Commencement Date notification occur no later than 14 days after signing is subject to actual readiness conditions (permit availability).
Therefore, for purposes of delay and completion, the Commencement Date is 1 August 2022. This affects the calculation of the Time for Completion and any delay claims accordingly.
References:
FIDIC Yellow Book 2017 Edition, Sub-Clause 8.1 - Commencement of Works
FIDIC Yellow Book 2017 Edition, Sub-Clause 2.1 - Right of Access to Site and Permits FIDIC Contract Manager Study Guide, Module on Contract Formation and Execution
NEW QUESTION # 134
In the FIDIC Silver Book (edition 1999), if the Employer has instructed the Contractor as per Sub-Clause 8.6 to provide a revised programme to stay within Time of Completion, the Employer can claim additional costs.
This only applies if the revised programme is still too slow to complete the Works within the Time for Completion. Is this statement true or false?
Answer: B
Explanation:
This statement is true. Under FIDIC Silver Book 1999, Sub-Clause 8.6, the Employer can instruct the Contractor to submit a revised programme to meet the contractual Time for Completion. If, after such instruction, the revised programme still shows the Works will not complete on time, the Employer may claim additional costs (such as delay damages or compensation) due to continued delay.
Thus, the Employer's right to claim additional costs is contingent on the revised programme not enabling timely completion.
References:
FIDIC Silver Book 1999 Edition, Sub-Clause 8.6 - Revised Programme
FIDIC Contract Manager Study Guide, Module on Claims and Delay Damages
NEW QUESTION # 135
The FIDIC Red Book (edition 1999) deals with Value Engineering Clause. It follows from this clause that the Contractor shall give notice to the Engineer with supporting particulars. Upon receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 to agree or determine this Cost, which shall be included in the Contract Price.
Answer: B
Explanation:
Under FIDIC Red Book (1999), the Value Engineering Clause requires the Contractor to notify the Engineer with full details and cost implications when proposing Value Engineering changes. The Engineer then follows the Variation procedure in Sub-Clause 3.5 to agree or determine the cost adjustment, which will be reflected in the Contract Price.
This ensures transparent handling of Value Engineering proposals and proper contractual adjustments.
References:
FIDIC Red Book 1999 Edition, Sub-Clause 13.1 - Value Engineering
FIDIC Contract Manager Study Guide, Module on Variations and Value Engineering
NEW QUESTION # 136
(Which two of the following statements are correct regarding types of Claims under the FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities).)
Answer: A,D
Explanation:
Under FIDIC 2017, Clause 20 introduces a structured and unified claims procedure applicable to both Contractor's and Employer's Claims. Claims are categorized broadly into:
* Claims for time and/or money (Sub-Clause 20.2), and
* Other claims (e.g., disputes or matters under Sub-Clause 20.1(c)).
Option A is correct. The 28-day time bar under Sub-Clause 20.2.1 applies to all claims for time and/or money and is a fundamental procedural requirement. Importantly, unlike FIDIC 1999, this time bar applies equally to both Parties, reinforcing fairness and discipline in claims management.
Option C is also correct. Claims under Sub-Clause 20.1(a) and (b) (typically relating to payment and/or extension of time) are processed under Sub-Clause 20.2, and the Engineer (or Employer's Representative in the Silver Book) must agree or determine the claim in accordance with Sub-Clause 3.7 (Red/Yellow) or 3.5 (Silver).
Option B is incorrect because claims under 20.1(c) are not handled through Sub-Clause 3.7/3.5 in the same structured determination process as time/money claims.
Option D is incorrect because FIDIC 2017 clearly applies the time bar to both Employer and Contractor claims, which is a key update from earlier editions.
This reflects FIDIC 2017's emphasis on symmetry, procedural clarity, and proactive claim management.
NEW QUESTION # 137
Under the FIDIC Red and Yellow Books (edition 1999), which two of the following statements are correct regarding the issuance of Interim Payment by the Engineer?
(Choose all correct answers - multiple possibilities)
Answer: A,C
Explanation:
Under the FIDIC Red Book and Yellow Book, 1999 editions, the Engineer issues Interim Payment Certificates certifying the amounts due to the Contractor for completed works and materials on site (Sub- Clause 14.6). The Employer is generally bound by the Payment Certificate and must pay accordingly, except where there is a lawful set-off or compensation claim against the Contractor.
Option A is correct because the Employer must pay the amount certified except for compensation claims that may be offset against the payment (Sub-Clause 14.6).
Option D is also correct: If the Employer intends to claim against the Contractor (e.g., for damages or defects), it must notify the Contractor under Sub-Clause 2.5 and provide particulars. The Engineer then assesses and decides on the claim and incorporates any agreed deductions into the Payment Certificate.
Option B is incorrect because the Employer is indeed bound by the Payment Certificate unless lawful deductions or disputes arise.
Option C is incorrect as the Employer can withhold amounts due for compensation claims once these are properly notified and substantiated.
References:
FIDIC Red and Yellow Books, 1999 Edition, Sub-Clause 14.6 - Interim Payments FIDIC Red and Yellow Books, 1999 Edition, Sub-Clause 2.5 - Employer's Claims FIDIC Contract Manager Study Guide, Module on Payment Procedures and Financial Management
NEW QUESTION # 138
......
All the CCM training files of our company are designed by the experts and professors in the field. The quality of our study materials is guaranteed. According to the actual situation of all customers, we will make the suitable study plan for all customers. If you buy the CCM learning dumps from our company, we can promise that you will get the professional training to help you pass your exam easily. By our professional training, you will pass your exam and get the related certification in the shortest time.
Valid CCM Braindumps: https://www.free4torrent.com/CCM-braindumps-torrent.html
P.S. Free & New CCM dumps are available on Google Drive shared by Free4Torrent: https://drive.google.com/open?id=1UNkYwBwNm6v9fDVB_16NO9f38LFouVha