This desktop practice exam software completely depicts the Scrum SMC exam scenario with proper rules and regulations and any other plugins to access Scrum SMC Practice Test. One such trustworthy point about exam preparation material is that it first gains your trust, and then asks you to purchase it.
The SMC Certification Exam is designed to evaluate an individual’s understanding of Scrum principles, practices, and concepts. SMC exam covers a range of topics, including Scrum theory, roles, events, artifacts, and values. It also tests the candidates' ability to apply Scrum principles to real-world scenarios and their understanding of how to facilitate Agile ceremonies and manage Agile teams effectively.
The Scrum Master Certified (SMC) exam is one of the most valuable certification exams. The Scrum Scrum Master Certified (SMC) exam opens a door for beginners or experienced DumpsFree professionals to enhance in-demand skills and gain knowledge. SMC Exam credential is proof of candidates' expertise and knowledge. After getting success in the Scrum Scrum Master Certified (SMC) exam, candidates can put their careers on the fast route and achieve their goals in a short period of time.
SCRUMstudy WebsiteEncertify WebsiteReference and Course Books
NEW QUESTION # 70
While assisting the Product Owner in developing a Prioritized Product Backlog, the Scrum Master must consider the primary factors on which the Prioritized Product Backlog is based-on. Which of the following are those primary factors?
A) Value
B) Dependencies
C) Risk
D) Deliverables
Answer: D
Explanation:
Explanation
The Prioritized Product Backlog contains a prioritized list of business and project requirements written in the form of Epic(s), which are high level User Stories. The Prioritized Product Backlog is based on three primary factors: value, risk or uncertainty, and dependencies. It is also referred to as the Risk Adjusted Product Backlog since it includes identified and assessed risks related to the project.
NEW QUESTION # 71
One of the responsibilities of the Scrum Master is to help the Product Owner in defining the Done Criteria.
Which of the following could the Done Criteria include?
I. List of issues to be fixed.
II. Unit testing of User Stories.
III. Stakeholder demonstrations.
IV. Documentation relating to User Stories.
Answer: B
Explanation:
Done Criteria establish the common quality conditions that apply across User Stories and provide a consistent basis for determining whether work is complete. The SBOK framework identifies activities such as completed unit testing, completed documentation, quality-assurance activities, peer review, resolution of issues, and successful demonstrations as legitimate examples of Done Criteria.
The critical distinction in this question is statement I. A list of issues to be fixed means unresolved work remains. That is different from the SBOK concept that all relevant issues are fixed before the item satisfies the Done Criteria. Therefore, simply maintaining a list of outstanding problems cannot itself establish completion.
Unit testing is directly associated with confirming technical quality. Documentation may be required to satisfy organizational, regulatory, operational, or support requirements. Demonstration to stakeholders or business representatives can also form part of the general completion conditions established for the project.
Consequently, statements II, III, and IV are appropriate, while statement I is not properly worded as a completion condition.
Study Guide reference: Quality - > Done Criteria; Create Prioritized Product Backlog - > establishment of Done Criteria; distinction between Done Criteria and User Story Acceptance Criteria.
========
NEW QUESTION # 72
Which of the following meetings is not usually Time-boxed?
Answer: D
Explanation:
Reference:
http://blog.scrumstudy.com/time-boxed-meetings-in-scrum/
NEW QUESTION # 73
In a Scrum project, which of the following is NOT a responsibility of a Scrum Master?
Answer: A
Explanation:
Ownership of grooming-or in current terminology, refining-the Prioritized Product Backlog belongs primarily to the Product Owner, not the Scrum Master. SCRUMstudy explicitly states that the Product Owner leads backlog refinement, adds or revises User Stories, reprioritizes work, and ensures upcoming requirements are sufficiently refined.
The Scrum Master may facilitate Prioritized Product Backlog Review Meetings and help ensure that communication, estimation, and Scrum practices remain effective, but facilitation is not the same as owning or grooming the backlog.
The Scrum Master also coordinates creation of the Release Planning Schedule as part of Conduct Release Planning. SCRUMstudy's role mapping explicitly lists that responsibility.
Similarly, the Scrum Master can represent Scrum Core Team experience and lessons learned so that organizational knowledge and Scrum Guidance Body recommendations can improve.
The critical distinction is between facilitating backlog refinement and being accountable for the contents and prioritization of the backlog. The latter belongs to the Product Owner.
Therefore, A is the activity that is not a Scrum Master responsibility.
Study Guide reference: Organization - > Scrum Master Responsibilities; Implement - > Groom/Refine Prioritized Product Backlog.
========
NEW QUESTION # 74
Which of the following is a process in the initiate phase of Scrum?
Answer: A
Explanation:
Explanation/Reference: https://www.scrumstudy.com/whyscrum/scrum-initiate