What's more, part of that ActualVCE CCM dumps now are free: https://drive.google.com/open?id=1n-ul1W09JgGpuFZO7ztyKGHEvB0WWFkz
Our excellent Medical Professional CCM practice materials beckon exam candidates around the world with their attractive characters. Our experts made significant contribution to their excellence. So we can say bluntly that our CCM Actual Exam is the best. Our effort in building the content of our CCM study dumps lead to the development of CCM learning guide and strengthen their perfection.
| Section | Weight | Objectives |
|---|---|---|
| Psychosocial Concepts and Support Systems | 27% | - Client dynamics and social determinants of health
|
| Care Delivery and Reimbursement Methods | 31% | - Reimbursement pathways and utilization management tools
|
| Ethical, Legal, and Practice Standards | 15% | - Regulatory compliance requirements and frameworks
|
| Rehabilitation Concepts and Strategies | 9% | - Vocational and physical rehabilitation pathways
|
| Quality and Outcomes Evaluation and Measurements | 18% | - Quality indicator metrics and performance tools
|
>> CCM Valid Dumps Questions <<
There are three different versions of our Medical Professional CCM preparation prep including PDF, App and PC version. Each version has the suitable place and device for customers to learn anytime, anywhere. In order to give you a basic understanding of our various versions on our Certified Case Manager Certification Exam (CCM) CCM Exam Questions, each version offers a free trial.
NEW QUESTION # 114
(Upon review of the revised programme, submitted by the Contractor, if the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) does not give a Notice of Non-Compliance within 14 days after receiving a revised programme, then... [complete the sentence, thereby considering FIDIC Red, Yellow, and Silver Books (edition 2017)]. (1 correct answer applies))
Answer: D
Explanation:
Under FIDIC 2017, Sub-Clause 8.3 [Programme] introduces a clearer and more structured mechanism for the review and acceptance of the Contractor's Programme. When the Contractor submits a revised programme, the Engineer (or Employer in the Silver Book) has a defined period-typically 14 days-to review it and issue a Notice of Non-Compliance if the programme does not meet contractual requirements.
If no such notice is issued within this timeframe, the contract provides a "deemed acceptance" (deemed consent) mechanism. This means that the Engineer is considered to have accepted the revised programme, and it becomes the operative Programme for the Works.
Option B correctly reflects this concept. It ensures continuity of project execution and prevents administrative delays caused by inaction. This is aligned with FIDIC 2017's emphasis on efficiency, proactive management, and avoidance of bottlenecks.
Option D is incorrect because "no objection" is weaker than "deemed consent." FIDIC explicitly uses the concept of consent, not merely absence of objection. Options A and C contradict the contract's intent of maintaining workflow.
Thus, the clause ensures that lack of response does not hinder progress, reinforcing disciplined contract administration.
NEW QUESTION # 115
Under the FIDIC Red and Yellow Books (edition 1999), which two of the following statements are correct regarding the issuance of Interim Payment by the Engineer?
(Choose all correct answers - multiple possibilities)
Answer: A,B
Explanation:
Under the FIDIC Red Book and Yellow Book, 1999 editions, the Engineer issues Interim Payment Certificates certifying the amounts due to the Contractor for completed works and materials on site (Sub- Clause 14.6). The Employer is generally bound by the Payment Certificate and must pay accordingly, except where there is a lawful set-off or compensation claim against the Contractor.
Option A is correct because the Employer must pay the amount certified except for compensation claims that may be offset against the payment (Sub-Clause 14.6).
Option D is also correct: If the Employer intends to claim against the Contractor (e.g., for damages or defects), it must notify the Contractor under Sub-Clause 2.5 and provide particulars. The Engineer then assesses and decides on the claim and incorporates any agreed deductions into the Payment Certificate.
Option B is incorrect because the Employer is indeed bound by the Payment Certificate unless lawful deductions or disputes arise.
Option C is incorrect as the Employer can withhold amounts due for compensation claims once these are properly notified and substantiated.
References:
FIDIC Red and Yellow Books, 1999 Edition, Sub-Clause 14.6 - Interim Payments FIDIC Red and Yellow Books, 1999 Edition, Sub-Clause 2.5 - Employer's Claims FIDIC Contract Manager Study Guide, Module on Payment Procedures and Financial Management
NEW QUESTION # 116
When is the Employer obliged to return the Performance Security (PS) under the FIDIC Red Book (edition
1999)?
Answer: D
Explanation:
Under FIDIC Red Book 1999, the Performance Security (or Performance Guarantee) is held to ensure the Contractor's performance during the defects liability period. The security is typically released only after the Employer issues the Performance Certificate, which confirms the completion of defects liability obligations and that the Contractor has fulfilled the contract.
The contract commonly specifies a fixed period (often 21 days) within which the Employer must return the Performance Security after issuance of the Performance Certificate (Option D). The Taking-Over Certificate (Options A and C) marks substantial completion but does not end the Contractor's obligations for defects.
References:
FIDIC Red Book 1999, Sub-Clause 10.2 - Taking-Over Certificate
FIDIC Red Book 1999, Sub-Clause 10.4 - Performance Certificate
FIDIC Red Book 1999, Sub-Clause 10.5 - Release of Performance Security
FIDIC Contract Manager Study Guide, Module on Payment Procedures and Financial Management
NEW QUESTION # 117
Which two statements reflect an INCORRECT application of a Golden Principle?
Answer: A,C
Explanation:
FIDIC's Golden Principles emphasize clarity, fairness, and completeness in contract drafting and administration. Incorrect applications often create risks, ambiguities, and disputes.
* Option Aiscorrectand reflects a good application of Golden Principles. When deleting clauses from the General Conditions, these must be replaced adequately in the Particular Conditions so that no essential contractual scope or responsibilities are lost or left undefined.
* Option Bisincorrectand reflects an improper deviation from the standard. The standard Commencement Date notification period is42 daysafter the Contractor receives the Letter of Acceptance (per Sub-Clause 8.1). Extending it to 60 days without valid reason or clear agreement introduces uncertainty and potential delay.
* Option Ccan be a legitimate contractual modification, provided it is agreed by the parties. Extending the Contractor's notice period for suspension from 21 days to 3 months is a significant change but not inherently contrary to Golden Principles if done transparently and fairly.
* Option Disincorrectand reflects a poor application of Golden Principles. Deleting all clauses referring to the DAAB/DAB (Dispute Adjudication Board) removes a critical dispute avoidance and resolution mechanism, undermining contract fairness and efficiency.
Therefore,Options B and Drepresent incorrect applications of the Golden Principles.
References:
FIDIC Contract Manager Study Guide, Module on Legal and Ethical Considerations and Golden Principles FIDIC Red Book 2017 Edition, Sub-Clause 8.1 - Commencement of Works FIDIC Red Book 2017 Edition, Clause 21 - Disputes and DAAB
NEW QUESTION # 118
(Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to give notice to the Employer if it discovers errors or defects of a technical nature. Is this statement true or false?)
Answer: A
Explanation:
Under all FIDIC standard forms (Red, Yellow, and Silver Books, both 1999 and 2017 editions), the Contractor has a clear contractual obligation to notify the Employer (or the Engineer, depending on the form) if it discovers errors, faults, or defects in documents or instructions of a technical nature.
This obligation is explicitly stated in Sub-Clause 1.9 [Errors in the Employer's Requirements] (particularly in Yellow and Silver Books) and similarly reflected in provisions related to documents, drawings, and instructions in the Red Book. The Contractor is required to carefully examine the documents provided and promptly give notice upon identifying any discrepancies, ambiguities, or technical defects.
The purpose of this obligation is to ensure early detection and correction of design or specification issues, thereby minimizing delays, rework, and disputes. It also reflects the principle of cooperation and proactive risk management embedded in FIDIC contracts.
Failure by the Contractor to notify such errors may result in loss of entitlement to additional time or cost if the issue later impacts execution. Therefore, this notification duty is both a technical and contractual safeguard.
Thus, the statement is true, as FIDIC imposes a clear obligation on the Contractor to notify discovered technical errors or defects.
NEW QUESTION # 119
......
The ActualVCE is committed to making the Medical Professional CCM certification exam preparation simple, smart, and successful. To achieve this objective ActualVCE is offering top-notch and real CCM exam questions in three different formats. The names of these Certified Case Manager Certification Exam (CCM) (CCM) exam questions formats are PDF files, desktop practice test software, and web-based CCM practice test software.
CCM Valid Exam Pdf: https://www.actualvce.com/Medical-Professional/CCM-valid-vce-dumps.html
What's more, part of that ActualVCE CCM dumps now are free: https://drive.google.com/open?id=1n-ul1W09JgGpuFZO7ztyKGHEvB0WWFkz