BONUS!!! Pass4Test PRINCE2-Practitioner 시험 문제집 전체 버전을 무료로 다운로드하세요: https://drive.google.com/open?id=1GmUvYp885l2NUy8wXOmA12Pn2am68UJj
Pass4Test의 경험이 풍부한 전문가들이PRINCE2 PRINCE2-Practitioner인증시험관련자료들을 계획적으로 페펙트하게 만들었습니다.PRINCE2 PRINCE2-Practitioner인증시험응시에는 딱 좋은 자료들입니다. Pass4Test는 최고의 덤프만 제공합니다. 응시 전PRINCE2 PRINCE2-Practitioner인증시험덤프로 최고의 시험대비준비를 하시기 바랍니다.
| Certification Vendor: | PeopleCert / AXELOS |
|---|---|
| Exam Name: | PRINCE2 Practitioner (Project Management Practitioner Exam) |
| Exam Number: | PRINCE2 Practitioner |
| Exam Duration: | 150 minutes |
| Available Languages: | Spanish, German, Slovak, Dutch, Czech, French, Portuguese (Brasil), Norwegian, Polish, Japanese, Chinese, Danish, Italian, English |
| Certificate Validity Period: | 3 years |
| Passing Score: | 60% |
| Exam Format: | Open book, Scenario-based multiple choice, Objective testing |
| Related Certifications: | PRINCE2 Agile Practitioner PRINCE2 Agile Foundation PRINCE2 Project Management Foundation PRINCE2 Foundation |
| Real Exam Qty: | 70 |
| Sample Questions: | PRINCE2 PRINCE2-Practitioner Sample Questions |
| Exam Way: | Exam is delivered as computer-based or online proctored with open book format (official manual allowed). |
| Pre Condition: | Must hold PRINCE2 Foundation certification or equivalent (e.g., PRINCE2 Agile Foundation, PMP, CAPM, IPMA Level A-D). |
| Official Syllabus URL: | https://www.axelos.com/certifications/propath/prince2-project-management/prince2-practitioner |
>> PRINCE2-Practitioner완벽한 덤프공부자료 <<
PRINCE2 PRINCE2-Practitioner 시험환경에 적응하고 싶은 분은 pdf버전 구매시 온라인버전 또는 테스트엔진 버전을 추가구매하시면 됩니다. 문제는 pdf버전의 문제와 같지만 pdf버전의 문제를 마스터한후 실력테스 가능한 프로그램이기에PRINCE2 PRINCE2-Practitioner시험환경에 익숙해져 시험을 보다 릴렉스한 상태에서 볼수 있습니다.
Prince2 실무자 시험은 Prince2 방법론에서 후보자의 이해와 숙련도를 평가하기 위해 고안된 인증 프로그램입니다. Prince2는 통제 된 환경의 프로젝트를 나타냅니다. 영국과 전 세계의 다른 국가에서 널리 사용되는 프로세스 기반 프로젝트 관리 방법론입니다. Prince2 실무자 시험은 Prince2 프레임 워크를 사용하여 복잡한 프로젝트 관리에 대한 전문 지식을 입증하려는 전문가에게 기본 요건으로 간주됩니다.
PRINCE2 실무자 시험은 PRINCE2 방법론의 원칙, 주제 및 프로세스를 실제 시나리오에 적용할 수 있는 능력을 평가합니다. 이 시험은 후보자가 프로젝트 관리 시나리오를 분석하고 해결책을 제공하는 능력을 테스트하는 다중 선택 문제로 구성됩니다. PRINCE2 실무자 시험에 합격하면 후보자는 PRINCE2 방법론을 사용한 프로젝트 관리 능력이 뛰어나며, 직업 전망을 향상시키고 전 세계적으로 인정받는 프로젝트 관리 자격증을 취득할 수 있습니다.
질문 # 202
Scenario:
Techniques, processes and procedures
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
2.Work is to start at the beginning of week 2 (Stage 4).
3.The project will take two years to complete, at an estimated cost of (GBP)2.5m. Tolerances
4.None.
Constraints
5.MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
6.Installation work must take place during MFH normal working hours.
7.+(GBP)10,000 / -(GBP)25,000.
Reporting arrangements
8.Highlight Report every Monday by 10.00 am.
9.The report must contain a summary of all products worked on during the previous week.
10.
Project Manager must be notified of any issues immediately by telephone.
Problem handling and escalation
11. Impact analysis of all issues must be completed within 24 hours.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion
Which 2 statements apply to either the Techniques, processes and procedures or Constraints sections?
정답:B,E
질문 # 203
Additional Information Product Description
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a
formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1.This document defines the approach to be taken to achieve the required quality levels during the project.
2.The Project Board will have overall responsibility for the Quality Management Strategy.
3.Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4.The selected service provider will operate to industry standards for providing outsourced services.
5.MFH document standards will be used.
Records
6.A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7.Configuration Item Records will be maintained for each product to describe its status, version and variant.
8.Approval records for products that require them will be stored in the quality database. Roles and responsibilities
9.The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10.
Team Managers will provide details of quality checks that have been carried out.
11.
Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12.
The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Which is a correctly defined acceptance criterion for the transferred facilities computer system?
정답:C
질문 # 204
Which of the following statements is FALSE regarding the Continued Business Justification?
정답:D
질문 # 205
Scenario
Additional Information
Product Description
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors) Introduction
1. This document defines the approach to be taken to achieve the required quality levels during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Which statement applies to the Roles and responsibilities section?
정답:C
질문 # 206
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.
Without a Risk Register how can project risks, the progress of risk actions taken to date and the current status of residual risks be measured?
정답:B