| Section | Objectives |
|---|---|
| Topic 1: Processes | - Starting up a project - Closing a project - Controlling a stage - Managing product delivery - Initiating a project - Managing a stage boundary - Directing a project |
| Topic 2: Practices | - Quality - Risk - Business case - Issues - Plans - Progress - Organizing |
| Topic 3: People | - People management and effective collaboration |
| Topic 4: Principles | - Apply the PRINCE2 principles in context |
>> PRINCE2-7-Practitioner합격보장 가능 시험대비자료 <<
PRINCE2인증 PRINCE2-7-Practitioner시험이 너무 어려워 보여서 오르지못할 산처럼 보이시나요? 그건PassTIP의 PRINCE2인증 PRINCE2-7-Practitioner시험문제에 대비하여 제작한PRINCE2인증 PRINCE2-7-Practitioner덤프가 있다는 것을 모르고 있기때문입니다. PRINCE2인증 PRINCE2-7-Practitioner시험에 도전하고 싶으시다면 최강 시험패스율로 유명한PassTIP의 PRINCE2인증 PRINCE2-7-Practitioner덤프로 시험공부를 해보세요.시간절약은 물론이고 가격도 착해서 간단한 시험패스에 딱 좋은 선택입니다.
질문 # 10
A high-level requirement that the design should be consistent with its surroundings was recorded during
'starting up a project'. During initiation, the project manager works with Council members, residents, retailers and BuildyBrick to clarify the required design characteristics and define measurable acceptance criteria.
Which management product should be updated with this information?
정답:A
설명:
The correct answer is A - Project product description . The project product description defines the project' s overall output and establishes the principal basis on which that output will ultimately be judged acceptable.
It includes the overall purpose, composition, quality expectations, acceptance criteria, and other characteristics necessary to determine whether the final project product is fit for its intended purpose.
The original statement that the design should be "consistent with its surroundings" is high level and inherently difficult to verify. During initiation, the project manager works with relevant stakeholders to translate that broad expectation into clearer design characteristics and measurable acceptance criteria . These details refine the definition of the overall project product and therefore belong in the project product description.
Option B is incorrect because a work package authorizes and controls specific work delegated to a team manager; it does not define the acceptance criteria for the entire project product. Option C, the product flow diagram, shows the sequence and dependencies involved in creating products rather than their acceptance requirements. Option D, the project plan, describes how and when the project's products will be delivered, but the overall acceptance definition belongs in the project product description.
This refinement also supports stakeholder alignment by turning an ambiguous requirement into objectively testable acceptance conditions.
PRINCE2 7 reference topics: Plans practice; project product description; quality expectations; acceptance criteria; starting up a project; initiating a project.
질문 # 11
In stage 4, the Heritage Director delegates a review of the inspection arrangements to the Heritage Manager.
The Heritage Manager will work with the BuildyBrick CEO and the project manager, then report whether the planned inspections will provide adequate assurance about impacts on historic buildings.
Is this an appropriate application of the 'define roles, responsibilities and relationships' principle, and why?
정답:A
설명:
The correct answer is B . The principle define roles, responsibilities and relationships requires more than assigning job titles. Individuals need to understand their delegated responsibilities, their authority, their interfaces with other participants, and what they can reasonably expect from those relationships.
The Heritage Director may delegate assurance activity provided accountability and authority remain appropriately structured. In this scenario, the Heritage Manager is expected to coordinate with the BuildyBrick CEO and project manager and report on whether the proposed inspection arrangements provide adequate assurance. For this arrangement to work, the Heritage Manager must understand precisely what the Heritage Director expects, the scope of the delegated review, and the contributions expected from the other parties.
PRINCE2 7 explicitly strengthens its treatment of relationships and recognizes that project effectiveness depends on deliberate interaction between people rather than merely documenting roles. PeopleCert describes clear responsibilities and good relationships as important foundations for governance, assurance, collaboration, and successful change.
Option A is too absolute: the principle does not impose an unrestricted requirement for every communication channel to remain open to everyone at all times. Options C and D incorrectly assume the activity cannot be delegated. PRINCE2 permits delegation while retaining appropriate accountability.
PRINCE2 7 reference topics: Define roles, responsibilities and relationships; Organization practice; delegation; assurance; project relationships.
질문 # 12
Before the end of stage 2, the project board authorizes a change that adds more trees and seating to the external landscaping. The change can be delivered in stage 3 without any forecast breach of project tolerance.
While preparing the next stage plan, the project manager incorporates the additional products and work, updates the relevant product descriptions and product register entries, and reviews whether the project initiation documentation needs to be updated.
Is this an appropriate application of 'prepare the next stage plan', and why?
정답:B
설명:
The correct answer is A . When preparing the next stage plan, the project manager must incorporate all relevant authorized changes that affect the products or work to be undertaken in the forthcoming management stage. The stage plan must represent the current authorized baseline rather than an obsolete version of what was originally intended.
The additional trees and seating have already been authorized by the project board, and the change can be incorporated without a forecast breach of overall project tolerance. The project manager should therefore reflect the additional products and activities in the stage 3 plan, revise affected product descriptions and product-register information, and determine whether corresponding elements of the project initiation documentation need updating.
Option B is incorrect because an exception plan is not required for every authorized change. Exception planning is used where agreed tolerance is forecast to be exceeded and the higher management level requests a replacement plan. The scenario explicitly states that project tolerance is not forecast to be breached. Option C incorrectly introduces mandatory re-authorization by the business layer. Option D is incorrect because preparing the next stage plan is a project manager responsibility; project assurance may independently review the resulting information but does not prepare it instead.
PRINCE2 7 reference topics: Managing a stage boundary; prepare the next stage plan; authorized changes; product descriptions; product register; PID maintenance; exception plans.
질문 # 13
As stage 3 approaches its end, the project manager seeks supplier-related advice from the CEO of BuildyBrick, acting in the senior supplier interest, about planning the testing and inspections in stage 4.
Under which 'directing a project' activity is this informal consultation provided?
정답:D
설명:
The correct answer is B - Give ongoing direction . The directing a project process is not limited to formal authorization decisions at stage boundaries. The project board also remains available throughout delivery to provide advice, guidance, and direction within its areas of responsibility. This continuing governance activity is captured by give ongoing direction .
In the scenario, the project manager informally consults the CEO of BuildyBrick in the senior supplier interest concerning testing and inspection arrangements for the forthcoming stage. This is specialist, supplier- related advice rather than a request for formal authorization. The senior supplier is appropriately positioned to provide guidance on technical feasibility, specialist resources, supplier capability, and the practical implications of planned quality activities.
Option A would apply when the project board formally reviews and decides whether to authorize a stage plan or exception plan. The scenario occurs while stage 4 is being planned, but the activity described is specifically an informal consultation , not the formal authorization decision itself. Option C concerns authorization of the initiation stage near the start of the project. Option D concerns formal authorization of the overall project following initiation.
The defining feature is therefore the provision of responsive board-level guidance during the project's life without making a formal authorization decision.
PRINCE2 7 reference topics: Directing a project; give ongoing direction; senior supplier; project board advice; stage planning; formal versus informal project-board control.
질문 # 14
A new law requires everyone working on public-infrastructure projects to hold an appropriate security clearance. The project manager records the legislation as an external event in the issue register so that its effects can be assessed.
Is this an appropriate application of the issues practice, and why?
정답:A
설명:
The correct answer is A . The legislation is an external event that has already occurred : a new legal requirement now applies to people working on public-infrastructure projects. It therefore represents an issue rather than merely an uncertain future risk. Recording it in the issue register enables the project team to assess its impact and determine what action may be necessary.
The effect could be significant. Existing or planned personnel may not possess the required security clearance, which could constrain the availability of resources, delay mobilization, alter supplier arrangements, increase costs, or affect scheduled delivery. The project manager should therefore ensure the event is captured and assessed rather than waiting until every consequence is known.
Option B is incorrect because external events that affect project objectives should still be managed through the project's agreed governance and issue-management controls. Option C would delay formal management of an event whose implications may require immediate investigation and action. Option D incorrectly assumes that externally generated issues belong exclusively to the business layer. The business may need to participate in resolving some consequences, but the project team must manage impacts on the project within its authority and escalation arrangements.
The key distinction is that an issue concerns something that has happened or is currently relevant , whereas a risk concerns uncertainty about a future event.
PRINCE2 7 reference topics: Issues practice; external events; issue register; issue assessment; resource impacts; risk-versus-issue distinction.