PMI PMI-RMP Exam Syllabus Topics:

SectionObjectives
Topic 1: Risk Monitoring and Control- Risk Reporting and Communication
- Risk Audits and Reviews
Topic 2: Risk Response Planning- Threat Response Strategies
- Opportunity Response Strategies
Topic 3: Risk Analysis- Quantitative Risk Analysis
- Qualitative Risk Analysis
Topic 4: Risk Strategy and Planning- Risk Management Planning
- Stakeholder Engagement in Risk
Topic 5: Risk Identification- Identifying Individual Risks
- Overall Project Risk Identification

>> PMI-RMP受験料 <<

PMI-RMP問題トレーリング、PMI-RMP日本語版復習資料

PMI-RMPテストガイドの言語は理解しやすいため、学習障害のない学習者は、学生であろうと現職のスタッフであろうと、初心者であれ、多くの経験豊富な経験豊富なスタッフであれ、年。 PMI-RMP試験問題は、教育レベルに依存しないすべての分野のすべての人に適用されます。したがって、困難なテストを通過するためにPMI-RMPガイドトレントを選択して合格することは素晴らしい素晴らしいアイデアです。

PMI Risk Management Professional 認定 PMI-RMP 試験問題 (Q167-Q172):

質問 # 167
The Project Risk Management knowledge area focuses on which of the following processes?
Each correct answer represents a complete solution. Choose all that apply.

正解:A、B、C


質問 # 168
A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization's risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges What two actions should the risk owner take? (Choose two.)

正解:A、D

解説:
The risk owner should implement the secondary risk response, as it is now being tolerated, and update the project documents accordingly. They should also update and communicate the assessments of the secondary risk's impact to ensure everyone is aware of the situation.
According to the PMI-RMP Handbook1, the risk owner is responsible for implementing the risk response plan and monitoring the risk and its secondary risks. Therefore, the risk owner should take the following two actions when the secondary risk emerges:
Implement the secondary risk response and update the project documents. This action is consistent with the risk response strategy of tolerance, which means accepting the risk and its consequences. The risk owner should execute the planned response for the secondary risk, such as contingency plans or fallback plans, and update the relevant project documents, such as the risk register, the risk report, and the lessons learned register, to reflect the current status and impact of the risk.
Update and communicate assessments of the secondary risk's impact. This action is consistent with the risk monitoring and control process, which involves tracking the identified risks, evaluating their impact and probability, and reporting the risk information to the appropriate stakeholders. The risk owner should reassess the secondary risk's impact on the project objectives, such as scope, schedule, cost, and quality, and communicate the results to the project manager and other relevant stakeholders, such as the sponsor, the customer, and the team members.
PMI-RMP Handbook1
PMBOK Guide, 6th edition, Chapter 11: Project Risk Management2


質問 # 169
Which of the following processes involves choosing the alternative strategies, executing a contingency or fallback plan, taking corrective action, and modifying the project management plan?

正解:C


質問 # 170
Henry is the project manager of the QBG Project for his company. This project has a budget of
$4,576,900 and is expected to last 18 months to complete. The CIO, a stakeholder in the project, has introduced a scope change request for additional deliverables as part of the project work.
What component of the change control system would review the proposed changes' impact on the features and functions of the project's product?

正解:B


質問 # 171
Which risk response is acceptable for both positive and negative risk events?

正解:D


質問 # 172
......

当社PMIのPMI-RMP試験トレントはPDF、ソフトウェア、オンライン3モードで利用できます。これにより、学習教材を紙、携帯電話、またはコンピューターで切り替え、PMI-RMPの対応するバージョンでいつでもどこでも学習できます。 模擬試験。 システムを購入する前に、PMI-RMP模擬テストにより無料の試用サービスが提供されるため、PMI Risk Management Professional顧客は購入前にシステムを完全に理解できます。 オンライン支払いが成功した後、5〜10分でカスタマーサービスからメールを受信し、すぐにPMI-RMPトレーニング準備を学び始めます。

PMI-RMP問題トレーリング: https://www.certjuken.com/PMI-RMP-exam.html

さらに、CertJuken PMI-RMPダンプの一部が現在無料で提供されています:https://drive.google.com/open?id=1m7iD8p-_q1MP6o4m--axu8Y71RYSdm-i