Adobe AD0-E911 Exam Syllabus Topics:

SectionWeightObjectives
Intake and Planning40%- Manage work intake processes
  • 1. Determine access and sharing permissions
    • 2. Review custom forms and request details
      • 3. Identify work request methods and notification rules
        - Project and task planning
        • 1. Plan resources and workload allocation
          • 2. Define task settings, dependencies and constraints
            • 3. Set up risk management and baseline
              • 4. Configure project structure and hierarchy
                Closeout15%- Project closure processes
                • 1. Complete deliverables and confirm acceptance
                  • 2. Update status and trigger completion actions
                    - Evaluation and documentation
                    • 1. Measure performance and success criteria
                      • 2. Archive project data and lessons learned
                        Execution45%- Reporting and collaboration
                        • 1. Communicate and share project information
                          • 2. Create and customize reports and dashboards
                            - Manage project execution
                            • 1. Manage approvals, reviews and proofing
                              • 2. Handle changes and unplanned work
                                • 3. Track progress, milestones and status updates
                                  - Financial and resource management
                                  • 1. Track project costs, budgets and billing
                                    • 2. Balance workload and adjust assignments

                                      >> AD0-E911復習問題集 <<

                                      AD0-E911勉強ガイド & AD0-E911最新試験

                                      AdobeのAD0-E911認定試験に受かることを悩んでいたら、Topexamを選びましょう。TopexamのAdobeのAD0-E911試験トレーニング資料は間違いなく最高のトレーニング資料ですから、それを選ぶことはあなたにとって最高の選択です。IT専門家になりたいですか。そうだったら、Topexamを利用したください。

                                      Adobe Workfront Project Manager Certified Professional 認定 AD0-E911 試験問題 (Q73-Q78):

                                      質問 # 73
                                      The second task in a project should be completed within 48 hours and needs to begin 5 business days after the first task is completed.
                                      Which task settings should be configured to meet these requirements?

                                      正解:A

                                      解説:
                                      In Adobe Workfront, to configure tasks according to the requirement of the second task beginning 5 business days after the first task, you need to set the appropriate "Duration" and use "Finish-Start" dependencies. The task's duration is key to determining the time allowed for its completion. The "Finish-Start" dependency ensures that the second task begins only after the first is finished, and a lag can be set to introduce a delay, such as 5 business days. Setting a "Finish-Start" dependency with a lag allows for proper scheduling of tasks in sequence without overlapping.


                                      質問 # 74
                                      What are two ways to associate milestone steps to tasks? (Choose two.)

                                      正解:B、C

                                      解説:
                                      Milestones in Adobe Workfront allow project managers to mark significant phases in a project. There are two primary methods for associating milestone steps to tasks:
                                      In-line editing a task list on a project: This method allows you to quickly assign milestones while editing the task list. It's a convenient option when working directly within a project's task list, ensuring you can associate tasks with milestone steps in a streamlined way without navigating away from the list view.
                                      From the Milestone View in the Projects area: The Milestone View is specifically designed to help manage milestones. It allows you to view and organize milestones and their associated tasks in one place, making it easy to connect tasks to milestones without manually editing individual tasks.
                                      These methods are integral for tracking progress and ensuring that tasks align with the significant steps of a project.


                                      質問 # 75
                                      A team member needs to review all records showing charges, payments, and invoicing details for a specific project.
                                      Which section in Workfront should they access to locate this information?

                                      正解:C

                                      解説:
                                      In Adobe Workfront, Billing Records are the correct place to review project-level billing and invoicing information. Adobe documentation explains that billing records are created as attachments to a project and contain financial data from the project as well as financial information from the project's tasks. Billing records are used to gather billable project items, such as billable hours, expenses, and revenue information, into a record that can support invoicing and financial review. This makes them the appropriate section when a team member needs to review records related to charges, payments, and invoicing details for a specific project. Project Details can contain general project information and some finance fields, but it is not the dedicated location for billing record review. Expenses is narrower because it focuses on project expenses and whether they are billable or reimbursable, rather than complete billing or invoice records. Therefore, the correct Workfront section is B. Billing Records.


                                      質問 # 76
                                      An IT department needs to see the Group and Portfolio of each of its projects for reporting purposes.
                                      In which project area does this information reside?

                                      正解:B

                                      解説:
                                      Adobe Workfront, information about the Group and Portfolio assigned to a project is stored in the "Project Details" section. This section contains the overall information regarding a project, such as the Portfolio it belongs to and the Group responsible for it. The "Queue Details" section pertains to request queues, while "Metrics" generally involves the measurement and tracking of key performance indicators but not specific data like Group and Portfolio.


                                      質問 # 77
                                      A team wants to combine structured project planning with the flexibility to manage tasks in sprints.
                                      Which Workfront methodology allows for this hybrid approach?

                                      正解:C

                                      解説:
                                      In Adobe Workfront, Scrum supports this hybrid approach because teams can keep structured project planning in Workfront while managing selected tasks as agile stories within iterations, commonly called sprints. Adobe documentation explains that Scrum teams use a backlog and then plan an iteration by selecting tasks or issues from that backlog. Adobe also notes that many organizations use the words sprint and iteration interchangeably, and that iteration planning occurs after the backlog has been groomed and prioritized. This allows planned project tasks to remain part of a Workfront project while the team manages execution through sprint-based agile practices. Waterfall is structured and sequential, but it does not provide sprint-based task management. Kanban provides flexible visual flow through a board, but it is not centered on fixed sprint or iteration planning. Therefore, the Workfront methodology that combines structured planning with sprint flexibility is A. Scrum.


                                      質問 # 78
                                      ......