P.S. Free & New CCM dumps are available on Google Drive shared by TopExamCollection: https://drive.google.com/open?id=1dHz7SlSlgq8nSjENC0DhpWvhgKWKgDLJ
Our Certified Case Manager Certification Exam (CCM) test torrent has been well received and have reached 99% pass rate with all our dedication. As a powerful tool for a lot of workers to walk forward a higher self-improvement, our CCM certification training continued to pursue our passion for advanced performance and human-centric technology. Only 20-30 hours are needed for you to learn and prepare our CCM test questions for the exam and you will save your time and energy. No matter you are the students or the in-service staff you are busy in your school learning, your jobs or other important things and canโt spare much time to learn. But you buy our CCM Exam Materials you will save your time and energy and focus your attention mainly on your most important thing. You only need several hours to learn and prepare for the exam every day.
| Section | Objectives |
|---|---|
| Quality and Outcomes Evaluation | - Outcome measurement and evaluation - Quality improvement methods |
| Rehabilitation and Disability Management | - Return-to-work planning - Rehabilitation principles |
| Care Delivery and Reimbursement Methods | - Insurance and reimbursement structures - Healthcare delivery systems |
| Ethics, Legal, and Regulatory Aspects | - Professional ethics in case management - Legal and regulatory compliance |
| Psychosocial and Support Systems | - Psychosocial assessment - Community resources and support systems |
>> Valid CCM Cram Materials <<
If you are forced to pass exams and obtain certification by your manger, our CCM original questions will be a good choice for you. Our products can help you clear exams at first shot. We promise that we provide you with best quality CCM original questions and competitive prices. We offer 100% pass products with excellent service. We provide one year studying assist service and one year free updates downloading of Medical Professional CCM Exam Questions. If you fail exam we support to exchange and full refund.
NEW QUESTION # 13
Applying FIDIC Silver Book (edition 1999), which one of the following elements shallnotform part of the time Programme/revised programme?
Answer: A
Explanation:
Comprehensive and Detailed Explanation:
According to the FIDIC Silver Book, 1999 Edition (The Conditions of Contract for EPC/Turnkey Projects), the Contractor is required under Sub-Clause 8.3 ("Programme") to submit a time programme that illustrates the sequence and timing of the works, including milestones and key events. The intended order of the works (Option A), sequence and timing of inspections and tests (Option B), and review periods (Option D) related to contract management processes such as approval of design or submissions (Sub-Clause 5.2) are integral to effective scheduling and coordination.
However,remedial work instructed under Sub-Clause 7.6, which concerns remedying defects or damage, is generally not part of the initial or revised programme. Instead, remedial works are typically handled as separate tasks or incorporated into specific defect liability or rectification schedules after the main programme has been executed. Such remedial works arise from defects liability obligations and do not belong to the original or revised time programme used to plan the main construction phases.
This distinction is important because the programme reflects planned works execution, whereas remedial work is reactive and may be scheduled separately under defects liability clauses or final project close-out arrangements.
References:
FIDIC Silver Book 1999 Edition, Clause 8.3 - Programme
FIDIC Silver Book 1999 Edition, Clause 7.6 - Remedial Work
FIDIC Contract Manager Study Guide, Module on Time and Delay Management
NEW QUESTION # 14
You are the Contract Manager for the Engineer in a highway project using FIDIC Red Book (edition 1999).
There is a Schedule of cost indexation included in the Contract. The project must be completed by 31 December of this year. If the Contractor fails to complete the Works by then, how will the adjustment of prices take place thereafter?
Answer: A
Explanation:
Comprehensive and Detailed Explanation:
Under FIDIC Red Book 1999, price adjustments after the Time for Completion are based on the indices or prices applicable on the date 49 days before the expiry of the Time for Completion, not the current index. This prevents the Contractor from benefiting from price fluctuations after the contract period.
This clause ensures fairness by locking the price basis as of a fixed reference date, protecting the Employer from increased costs due to delays.
References:
FIDIC Red Book 1999 Edition, Sub-Clause 13.8 - Adjustments for Changes in Cost FIDIC Contract Manager Study Guide, Module on Price Adjustment
NEW QUESTION # 15
Under the FIDIC Silver Contract (edition 2017), which two of the answers provide for preconditions for certification and payment of the Interim Payment Certificate?
Choose all of the correct answers (multiple possibilities).
Answer: B,C
Explanation:
Comprehensive and Detailed Explanation:
Option A is correct: Certification and payment of interim payments are conditional on Employer's receipt of the Contractor's appointment and the Advance Payment Guarantee (Sub-Clause 14.2.1).
Option D is correct: Payment also requires receipt of the Contractor's statement supported by relevant documentation.
Option B alone is insufficient without supporting documents.
Option C relates to appointment and performance security but is not a stated precondition for payment certification.
References:
FIDIC Silver Book 2017 Edition, Sub-Clause 14.6 - Interim Payment Certificates FIDIC Contract Manager Study Guide, Module on Payment Procedures
NEW QUESTION # 16
(You are the Contract Manager for the Engineer in a highway project using FIDIC Red Book (edition 1999).
There is a Schedule of cost indexation included in the Contract. The project must be completed by 31 December of this year. If the Contractor fails to complete the Works by then, how will the adjustment of prices take place thereafter? (1 correct answer applies))
Answer: C
Explanation:
Under FIDIC Red Book 1999, Sub-Clause 13.8 [Adjustments for Changes in Cost] governs price adjustment based on cost indices. A key provision addresses the situation where the Contractor fails to complete the Works within the Time for Completion.
In such a case, the contract protects the Employer from adverse cost escalation due to Contractor delay. The adjustment of prices is calculated using whichever index is more favourable to the Employer between:
* the index applicable at the time of execution (current index), or
* the index applicable 49 days before the expiry of the Time for Completion.
This mechanism ensures that the Contractor does not benefit from price increases occurring after the contractual completion date if the delay is attributable to the Contractor. It reflects a fundamental FIDIC principle: the Contractor bears the financial consequences of delay for which it is responsible.
Option A is incomplete because it ignores comparison with current indices.
Option B is incorrect because it does not account for Employer protection.
Option D is incorrect because the rule is predefined in the Contract, not subject to agreement.
Thus, Option C correctly reflects FIDIC's balanced risk allocation regarding cost escalation after delay.
NEW QUESTION # 17
(Which two statements are correct for the FIDIC Red Book (edition 2017)?
Choose all of the correct answers (multiple possibilities).)
Answer: B,C
Explanation:
Under FIDIC Red Book 2017, Clause 1.1 [Definitions] and Clause 1.5 [Priority of Documents] define the composition and hierarchy of the Contract. The Contract is not limited to only General and Particular Conditions; it includes multiple documents such as the Contract Agreement, Letter of Acceptance, Letter of Tender, Specifications, Drawings, and Schedules. Therefore, Option A is incorrect.
Option B is correct. The term "Conditions of Contract" explicitly refers to the General Conditions as modified or amended by the Particular Conditions. This reflects how Particular Conditions adapt the standard FIDIC provisions to project-specific requirements while forming a single integrated set of contractual conditions.
Option C is incorrect because Contract Data forms part of the Particular Conditions, not the General Conditions. It contains project-specific data that complements and modifies the General Conditions.
Option D is correct. The Contract Agreement, Letter of Acceptance, and Letter of Tender are explicitly listed as core Contract documents under FIDIC 2017. These documents establish the legal formation of the Contract and define the agreed scope, price, and commitments between the Parties.
This structure ensures clarity, proper hierarchy, and enforceability of contractual obligations in FIDIC contracts.
NEW QUESTION # 18
......
For some candidates who want to enter a better company through obtaining a certificate, passing the exam is quite necessary. CCM exam materials are high-quality, and you can pass the exam by using the materials of us. CCM exam dumps contain questions and answers, and you can have a timely check of your answers after practice. CCM Exam Materials also provide free update for one year, and update version will be sent to your email automatically.
CCM Exam Dumps Pdf: https://www.topexamcollection.com/CCM-vce-collection.html
What's more, part of that TopExamCollection CCM dumps now are free: https://drive.google.com/open?id=1dHz7SlSlgq8nSjENC0DhpWvhgKWKgDLJ