Why our Civil-Engineering-Technology exam questions are the most populare in this field? On the one hand, according to the statistics from the feedback of all of our customers, the pass rate among our customers who prepared for the Civil-Engineering-Technology exam with the help of our Civil-Engineering-Technology guide torrent has reached as high as 98%to 100%. On the other hand, the simulation test is available in our software version of our Civil-Engineering-Technology Exam Questions, which is useful for you to get accustomed to the Civil-Engineering-Technology exam atmosphere. Please believe us that our Civil-Engineering-Technology torrent question is the best choice for you.
| Section | Weight | Objectives |
|---|---|---|
| Water Resources & Environmental Engineering | 12% | - Hydrology & Water Systems
|
| Transportation Engineering | 15% | - Highway & Road Design
|
| Construction Management & Materials | 10% | - Construction Methods & Project Management
|
| Structural Engineering | 20% | - Structural Analysis & Design
|
| Geotechnical Engineering | 18% | - Soil Mechanics & Foundation Engineering
|
| Civil Engineering Fundamentals | 25% | - Engineering Mathematics & Applied Science
|
>> Study Civil-Engineering-Technology Center <<
TestPassKing could give you the CTTAM Civil-Engineering-Technology exam questions and answers that with the highest quality. With the material you can successed step by step. TestPassKing's CTTAM Civil-Engineering-Technology exam training materials are absolutely give you a true environment of the test preparation. Our material is highly targeted, just as tailor-made for you. With it you will become a powerful IT experts. TestPassKing's CTTAM Civil-Engineering-Technology Exam Training materials will be most suitable for you. Quickly registered TestPassKing website please, I believe that you will have a windfall.
NEW QUESTION # 24
A civil engineering technologist needs to recommend a foundation design for a commercial building. The borehole logs identify unsuitable bearing soils beneath the proposed floor elevation to a depth of 4 m and shallow bedrock at 5 m. Which of the following types of design should the technologist recommend?
Answer: C
Explanation:
The subsurface profile indicates a weak/unsuitable bearing stratum extending several metres below the proposed founding level, withcompetent bedrock close beneath(shallow bedrock at about 5 m). Shallow foundations (slab-on-grade or strip footings) depend on adequate near-surface bearing capacity and acceptable settlement; with unsuitable soils to 4 m, shallow options would risk excessive settlement or bearing failure unless major ground improvement is performed. Where a strong bearing stratum such as bedrock is available at practical depth,end-bearing pilesare commonly selected to transfer structural loads through weak soils and seat on (or be socketed into) the competent stratum. Engineering references define end-bearing piles as piles driven/drilled to a firm layer/bedrock so that axial load is carried primarily inend bearingrather than relying on skin friction in weak compressible soils. With shallow bedrock, end-bearing piles provide a direct and reliable load path and reduce settlement uncertainty versus friction piles in poor soils.
NEW QUESTION # 25
What is the main reason for taking handwritten notes while surveying?
Answer: D
Explanation:
Survey work depends on traceable, reproducible observations. Handwritten field notes (field book entries, sketches, stationing, and benchmark ties) function as theprimary recordof what was measured, under what conditions, and how control was established. Lindeburg describes that elevations of temporary benchmarks are generally found infield notesand local official filings, reflecting that field notes are treated as an enduring record used later for computations, verification, and re-establishment of control. This is why good surveying practice emphasizes complete notes, clear sketches, and unambiguous identification of points-so results can be checked, recalculated, and defended long after the crew leaves site. While survey data supports mapping and may indirectly support disputes, the fundamental purpose of handwritten notes is to create apermanent, auditable recordof survey results and control ties.
NEW QUESTION # 26
A civil engineering technologist is undertaking a final acceptance review of a subdivision. The technologist finds 35 m of deficient sidewalk and three hydrants which were not tested. As part of final acceptance, what should be done to ensure the hydrants get tested and the sidewalk is repaired?
Answer: D
Explanation:
Final acceptance requires that outstanding deficiencies be clearly identified and tracked to closure. Industry closeout practice uses adeficiency list (punch list/snag list)that itemizes nonconforming work and incomplete testing, and it is issued to the contractor so corrective actions can be completed before final acceptance is granted. A punch/deficiency list is specifically described as a document prepared near the end of a project that lists items that do not conform and must be rectified before completion certification. Best practice is to recordprecise locations(and identifiers like hydrant numbers), often with photos or plan references, to avoid ambiguity and ensure corrective work is verifiable. Verbal communication alone is not sufficiently traceable, and simply noting quantities without locations can lead to missed items and disputes.
Therefore, the correct action is todocument the locations and forward the deficiency list to the contractor so testing and repairs are completed and can be re-inspected for acceptance.
NEW QUESTION # 27
What documents must a contractor submit as part of a project to consultants for review?
Answer: B
Explanation:
In contract administration, consultants review certain contractor submittals to confirm that proposed products and installation details align with thedesign intentand contract requirements. The principal document type submitted for this purpose isshop drawings, which are prepared by the contractor, fabricator, or supplier and show project-specific fabrication, dimensions, connection details, reinforcement layout, and installation information for components (e.g., structural steel, precast, rebar placing drawings, mechanical/electrical supports). This review process is a standard part of construction coordination and quality management because it checks compatibility and constructability before fabrication/installation proceeds. By contrast, change orders are contractual amendments initiated when scope/cost/time changes occur, IFC drawings are produced by the consultant (not submitted by the contractor for review), and meeting minutes are project records rather than technical submittals requiring consultant approval. Therefore, the document the contractor must submit to consultants for review isshop drawings, which enable technical verification and coordination of constructed elements with the contract documents.
NEW QUESTION # 28
Which of the following isnota type of structural foundation system used to hold the weight of a building?
Answer: B
Explanation:
A "foundation system" is a permanent structural/geotechnical arrangement that transfers building loads to the supporting ground (e.g., shallow foundations like strip/spread footings or slabs-on-grade, and deep foundations like piles with grade beams). Options A, B, and D are all recognized foundation systems: pile
/grade beam systems are deep foundation solutions; wall and strip footings are shallow continuous foundations; and structural slabs-on-grade are shallow systems that distribute loads to prepared subgrade. By contrast,concrete formworkis atemporary construction means-the molds, supports, and bracing used to shape and support fresh concrete until it gains strength. Formwork is not part of the final load path once removed, and it does not function as a load-transfer system into soil/rock. Therefore, among the choices, the item that is not a foundation system isconcrete formwork.
NEW QUESTION # 29
......
Everyone wants to have a good job and decent income. But if they don’t have excellent abilities and good major knowledge they are hard to find a decent job. Passing the test Civil-Engineering-Technology certification can make you realize your dream and find a satisfied job. Our study materials are a good tool that can help you pass the exam easily. You needn’t spend too much time to learn it. Our Civil-Engineering-Technology Exam Guide is of high quality and if you use our product the possibility for you to pass the exam is very high.