| Section | Weight | Objectives |
|---|---|---|
| Topic 1: Corporate Standards and Documentation | 16% | - Establish BIM standards aligned with organizational requirements
|
| Topic 2: Collaboration Process | 36% | - Manage Common Data Environment (CDE) workflows
|
| Topic 3: Data Management | 20% | - Audit and resolve model issues
|
| Topic 4: Project Needs Assessment | 28% | - Initialize project setup
|
如果你選擇了報名參加Autodesk BIM_MGT_101 認證考試,你就應該馬上選擇一份好的學習資料或培訓課程來準備考試。因為Autodesk BIM_MGT_101 是一個很難通過的認證考試,要想通過考試必須為考試做好充分的準備。
問題 #13
The BIM manager is working in an Architectural model that uses the phases Existing and New Construction. They have linked in a Structural model that uses only Phase 1 for existing and Phase 2 for new construction. After linking, they notice that demolition elements from the Structural model do not display correctly in the demolition views.
Which approach allows the BIM manager to display linked elements correctly based on this phase setup, without changing the phases in the linked model?
答案:B
解題說明:
Revit phase mapping is specifically intended to reconcile differences between phase structures in a host model and a linked Revit model. The BIM manager should map Phase 1 in the structural link to Existing in the architectural host and map Phase 2 to New Construction. Revit can then interpret the linked elements' phase-created and phase-demolished conditions in the context of the host view.
This preserves the structural consultant's internal phase definitions and avoids altering a model controlled by another discipline. It also produces consistent display behaviour across host views using phase filters such as Show Previous + Demo, Show Complete, or other project-specific configurations.
A Visibility/Graphics override can alter how an entire link or category appears, but it does not correctly translate the underlying phase relationships. Renaming or restructuring the phases directly in the consultant's model is unnecessary and may disrupt that firm's documentation. A host view template can control link-display settings, but it cannot substitute for correct phase correspondence where the two files use different phase names or phase structures.
Phase mapping is therefore the controlled, non-destructive coordination mechanism for this scenario.
Reference topics: Revit phase mapping; linked-model display; phase filters; demolition views; host and consultant model coordination; multidisciplinary phase standards.
問題 #14
A contractor has requested the Architectural Revit model for a design-bid-build project to help with their fabrication drawings. The contractor understands and agrees that construction documents will govern in case of discrepancies.
How should the BIM Manager proceed?
答案:A
解題說明:
Before releasing an editable or reference model to a contractor, the BIM manager must confirm that the required digital-content release has been executed. Verbal acknowledgement that the construction documents govern does not adequately define permitted model uses, reliance limitations, intellectual-property restrictions, model status, or responsibility for downstream fabrication decisions.
A digital-content release should identify the purpose of the transfer, authorized recipients, accepted file formats, issue date, model-development status, and limitations on modification or redistribution. It should also clarify that the model may contain incomplete, approximate, or non-contractual information and that the recipient remains responsible for verifying fabrication and construction requirements against the governing documents.
Adding the contractor directly to the project environment could expose additional data and does not replace formal release authorization. Sending a copied model immediately bypasses document-control and risk-management procedures. Exporting sheets to DWG may not satisfy the contractor's stated need for model geometry and does not eliminate the requirement to control digital information distribution.
Once the release is confirmed, the BIM manager should prepare a controlled model package containing only the information required for the authorized purpose.
Reference topics: Digital-content release; external model distribution; contractual reliance; intellectual-property controls; authorized BIM uses; information-risk management.
問題 #15
For a project that is well into its Design Development phase, it is discovered that there is an easement on the property that increases the setback by 1 ft 6 in. (450 mm).
Which method for updating the geolocation of the project would be least disruptive to the extended design team?
答案:D
解題說明:
Repositioning the authoritative civil site resource relative to the established building model and then publishing the revised positional relationship is the least disruptive approach. At Design Development, multiple disciplines may already have linked the building model, established views, placed annotations, configured worksets, and coordinated systems around its current internal geometry. Physically moving all building elements would therefore create extensive risk, including displaced annotations, broken constraints, altered links, and inconsistent consultant coordination.
Publishing the updated position preserves the controlled relationship between the project model and the site resource without requiring each discipline to relocate its authored geometry manually. The revised coordinate relationship can then be distributed through the established shared-coordinate workflow.
Specify Coordinates at Point is not appropriate merely because a setback changed; it can redefine the project's coordinate basis based on an isolated point rather than maintaining the managed relationship with the civil reference. Resetting coordinates and reacquiring them is substantially more disruptive because it discards the existing shared-coordinate relationship and can affect every connected model. Moving all model elements is the highest-risk option because it changes design geometry rather than correcting the external positional reference.
Reference topics: Shared coordinates; civil-site coordination; Publish Coordinates; model positioning; geolocation governance; change management during design development.
問題 #16
The BIM manager is launching a civic center project with strict sustainability and lifecycle data goals. During early planning, each discipline proposes different modelling approaches, and there is concern that downstream data handoff may be inconsistent.
To establish BIM goals and uses that ensure alignment from design through operations, what should the BIM manager do first?
Note: In the context of this exam, the term Level of Development (LOD) is used interchangeably with level of information need.
答案:A
解題說明:
The BIM manager must first establish the project's actual information requirements before prescribing models, templates, LOD criteria, or delivery procedures. A structured stakeholder session should identify the owner's sustainability objectives, operational data needs, required BIM uses, asset-management interfaces, exchange milestones, and responsibility boundaries. This provides the basis for determining what information must be authored, by whom, at what stage, and for which downstream purpose.
Consolidating standard BEPs from different firms would reproduce organization-specific practices rather than create a coherent project strategy. Similarly, adopting an LOD matrix from previous projects risks imposing assumptions that do not match the civic center's lifecycle and sustainability requirements. Developing templates before requirements are confirmed can embed incorrect parameters, classifications, units, or workflows into the project environment.
The stakeholder session should result in documented BIM objectives, approved use cases, information requirements, mobilization actions, and preliminary modelling responsibilities. Those decisions can then inform the project BEP, Model Element Table, LOD or information-need matrix, delivery plans, training requirements, and Common Data Environment configuration.
Reference topics: Project needs assessment; stakeholder engagement; BIM-use definition; lifecycle information requirements; sustainability goals; BIM mobilization; level of information need.
問題 #17
A BIM manager is creating a firm-wide template for mobilization plans to outline the key steps, resources, and strategies required to set up and launch BIM operations at the beginning of projects.
Which two components should the template include to accomplish the goal? (Select two.)
答案:C,D
解題說明:
A BIM mobilization plan must define both the operational information environment and the people responsible for establishing and managing it. The Common Data Environment is therefore a core component. The plan should identify the selected platform, folder structure, naming system, permission model, approval states, model-sharing process, and procedures for publishing, reviewing, and archiving project information.
The plan must also define roles and responsibilities. This includes responsibility for model setup, coordination, content management, data validation, model-health reviews, issue administration, information authorization, and delivery approval. Without explicit accountability, essential mobilization tasks may be duplicated, delayed, or left incomplete.
A contract template and project specifications are broader organizational or contractual resources rather than primary BIM mobilization components. Project milestone dates influence the subsequent delivery programme, but mobilization focuses on establishing the environment, resources, access, governance, and responsibilities necessary to begin BIM production. Detailed milestone commitments are normally developed through the project programme and information-delivery plans.
A reusable firm-wide template should allow project-specific entries while enforcing a consistent minimum mobilization standard across projects.
Reference topics: BIM mobilization planning; Common Data Environment setup; roles and responsibilities; project initiation; access governance; model-startup procedures; resource planning.