| Section | Weight | Objectives |
|---|---|---|
| Topic 1: Data management | 20% | - Conduct project closeout
|
| Topic 2: Project needs assessment | 28% | - Develop and implement project-specific BIM Execution Plan (BEP)
|
| Topic 3: Collaboration process | 36% | - Coordinate and maintain geolocation
|
| Topic 4: Corporate standards and documentation | 16% | - Create project and content templates
|
AutodeskのBIM_MGT_101試験に関する権威のある学習教材を見つけないで、悩んでいますか?世界中での各地の人々はほとんどAutodeskのBIM_MGT_101試験を受験しています。AutodeskのBIM_MGT_101の認証試験の高品質の資料を提供しているユニークなサイトはPass4Testです。もし君はまだ心配することがあったら、私たちのAutodeskのBIM_MGT_101問題集を購入する前に、一部分のフリーな試験問題と解答をダンロードして、試用してみることができます。
質問 # 17
The BIM manager on a large mixed-use development is leading the development of the project's information-delivery strategy. The client has strict handover requirements for both asset data and spatial coordination. The design schedule includes overlapping packages, and some task teams are unfamiliar with structured data exchanges.
What is the most appropriate approach to establish the project's information-delivery plans?
正解:B
解説:
The project requires a structured delivery plan that assigns responsibility and timing for each information exchange. The plan must define what information is required, which task team produces it, who verifies and authorizes it, the required format, the delivery milestone, and the receiving party. This is particularly important where design packages overlap and asset-data requirements must develop alongside spatial coordination rather than being added retrospectively.
A task information-delivery plan provides detailed commitments at the team level, while the consolidated information-delivery plan coordinates those commitments across the project. Together they align model production, structured data, coordination submissions, review periods, and final handover requirements.
Allowing each discipline to determine its own formats independently would produce inconsistent data structures and make late consolidation expensive and unreliable. Naming conventions are necessary but represent only one small component of information management. Postponing asset information until construction creates a high risk of missing parameters, unassigned responsibilities, incomplete records, and extensive rework.
The delivery strategy must therefore be established early and integrated with the design programme, BIM Execution Plan, client information requirements, and quality-assurance process.
Reference topics: Task Information Delivery Plans; Master Information Delivery Planning; information-exchange requirements; asset-data handover; structured data; responsibility matrices; delivery milestones.
質問 # 18
During early coordination on a hospital project, the BIM manager runs a general clash detection between all models and generates over 3,000 clash results. Many are low-priority issues, such as wall-grid overlaps and minor duct-ceiling intersections. The project's clash matrix outlines only high-impact clashes between structural, MEP, and architecture in specific zones.
For the BIM manager, what is the most appropriate next step to align clash reporting with the project's coordination strategy?
正解:C
解説:
The clash matrix is the project's approved framework for determining which model combinations, object categories, zones, and tolerances require coordination. The BIM manager should configure clash tests to reflect that matrix rather than distribute an unfiltered list of every geometric intersection generated by the software.
Low-value results should be removed through controlled rule selection, object-category filtering, zone-based scoping, and technically justified tolerance settings. Reports can then be organized according to each discipline's responsibility and focused on clashes that materially affect constructability, design intent, access, maintenance clearances, or code compliance.
Sending all 3,000 results to project teams transfers the BIM manager's triage responsibility to designers and creates substantial coordination noise. Manual spreadsheet sorting separates the results from model context and is inefficient for repeated review cycles. Arbitrarily relaxing clash rules merely to reduce totals is also unacceptable; tolerances must correspond to documented project requirements rather than a desired numerical result.
Applying the clash matrix creates a repeatable, auditable process and ensures that coordination meetings address consequential issues instead of irrelevant geometric contacts.
Reference topics: Clash matrices; clash-test configuration; tolerance management; discipline-based reporting; coordination prioritization; Model Coordination.
質問 # 19
A client's project schedule requires a rigorous milestone/gateway review process, defined in the BIM Execution Plan. The design firm has its own internal checklist.
What should a BIM manager do to ensure the team is complying with the client's requirements?
正解:B
解説:
The BIM manager should perform a gap analysis between the client's BEP-defined gateway requirements and the firm's standard quality-control checklist. The internal checklist may address common model-health and documentation criteria, but it cannot be assumed to cover every project-specific submission, approval, information, or coordination requirement.
Any client requirement not represented in the standard checklist should be incorporated into the project review process. Creating trackable issues or review actions in the Common Data Environment provides assigned responsibility, due dates, supporting evidence, status visibility, and an auditable closure record before each gateway.
Granting the client model access does not demonstrate that the design team has completed the required review. Placing a PDF on the Revit opening view may improve awareness but does not establish compliance, accountability, or verification. Model phases also represent temporal construction conditions and should not be manipulated merely to correspond with project-management milestones such as Design Development.
The milestone process should culminate in documented evidence that each requirement was reviewed, passed, conditionally accepted, or formally resolved before the project advances to the next stage.
Reference topics: BEP compliance; milestone and gateway reviews; quality-control checklists; gap analysis; issue tracking; project-specific standards.
質問 # 20
During a model review, several linked files appear missing or unloadable in the federated coordination file. The files were present and working the day before, and no changes were made to the Revit host model itself.
As the BIM manager, what is the most appropriate step to troubleshoot the issue?
正解:D
解説:
Because the host model itself has not changed, the first investigation should focus on how the external references are being resolved. Relative paths depend on the relationship between the host file and the linked files within the project folder structure. If a folder was renamed, relocated, synchronized differently, or omitted from a distributed package, Revit may no longer locate the linked models even though the links remain correctly configured in the host.
The BIM manager should review the link status and saved paths in Manage Links, confirm that the referenced files still exist, and compare the current folder structure with the approved project structure. Access permissions, cloud synchronization status, and network availability should also be checked where applicable.
Converting all references to absolute paths would make the links dependent on a specific drive or network location and commonly causes failures for other users. Removing and reinserting links risks losing positioning, pinning, display overrides, workset assignments, and coordination history. Rebuilding the host from backup is disproportionate and does not address an external path or access failure.
Reference topics: Manage Links; relative file paths; federated-model folder structures; reference resolution; link-status troubleshooting; Common Data Environment access.
質問 # 21
Which of the following would typically be included in an AECO BIM data handover package at project closeout?
正解:B
解説:
A project-closeout handover package should contain verified record models populated with the asset information required by the owner's operational and facilities-management processes. Depending on the defined information requirements, this may include asset identifiers, classification, manufacturer and model data, installation information, warranty details, maintainability fields, commissioning status, spatial relationships, and links to associated documentation.
The record model must represent the accepted project condition rather than an intermediate coordination state. It should undergo final validation for required parameters, naming, file format, model structure, and information completeness before delivery. Where COBie or another structured asset-data format is required, the embedded model information should correspond with the exported dataset.
Federated clash-detection models and temporary 3D coordination views are process artifacts. They may be archived where the contract or organizational retention policy requires them, but they are not normally the principal operational deliverable. Internal coordination notes likewise document project activity but do not provide the owner with a usable digital representation of the completed facility.
The defining characteristic of a BIM handover deliverable is verified, structured information that supports the owner's specified post-project uses.
Reference topics: BIM closeout; record models; asset-information requirements; COBie; facilities-management handover; data validation; digital deliverables.