VCETorrent believes in customer satisfaction and strives hard to make the entire PSM-II exam preparation process simple, smart, and successful. To achieve this objective VCETorrent is offering the top-rated and real Scrum Certification Exams preparation material in three different Scrum PSM-II Exam study material formats. These Professional Scrum Master level II (PSM II) exam questions formats are PSM-II PDF dumps file, desktop practice test software and web-based practice test software.
| Section | Objectives |
|---|---|
| Scrum Master Responsibilities | - Servant Leadership
|
| Managing Products with Agility | - Stakeholder Collaboration
|
| Supporting Organizational Change | - Agile Transformation
|
| Developing People and Teams | - Facilitation Skills
|
| Scrum Theory and Principles | - Scrum Values
|
>> PSM-II Reliable Exam Tips <<
We have always taken care to provide our customers with the very best. So we provide numerous benefits along with our Scrum PSM-II exam study material. We provide our customers with the demo version of the Scrum PSM-II Exam Questions to eradicate any doubts that may be in your mind regarding the validity and accuracy. You can test the product before you buy it.
NEW QUESTION # 254
What would be typical Scrum Master activities during the Sprint?
Answer: B
NEW QUESTION # 255
What are two ways in which technical debt relates to velocity? (Choose the best two answers)
Answer: A,D
Explanation:
This is a true statement, as some Developers may choose to take shortcuts or compromise on quality in order to deliver more work in a Sprint. However, this is not a sustainable or ethical practice, as it will create more problems and costs in the future. The Scrum Master can help the Developers to avoid this temptation and focus on delivering value and quality instead.
This is a true statement, as technical debt can act as a drag on the productivity and progress of the Developers. Technical debt can make the work more difficult, complex, or risky, and may require more time and effort to fix or refactor. The Scrum Master can help the Developers to identify and manage technical debt, and communicate its impact to the Product Owner and the stakeholders.
NEW QUESTION # 256
Where should the Daily Scrum be held according to the Scrum Guide?
(choose the best answer)
Answer: D
Explanation:
Explanation
According to the Scrum Guide 2020, the Developers can choose the location and structure of their Daily Scrum, as long as it is consistent and conducive to inspection and adaptation. The Daily Scrum is an event for the Developers, not for the Scrum Master, the Product Owner, or the management. The Developers are responsible for planning their work for the next 24 hours and synchronizing their progress toward the Sprint Goal.
References:
Scrum Guide 2020, page 11: "The Developers can select whatever structure and techniques they want, as long as their Daily Scrum focuses on progress toward the Sprint Goal and produces an actionable plan for the next day of work." Scrum Guide 2020, page 12: "The Daily Scrum is held at the same time and place each day to reduce complexity."
NEW QUESTION # 257
Your Scrum Team has been working together for over a dozen Sprints. The Scrum Team consists of 10 members. Each Sprint takes four weeks. As a Scrum Master, you observe that the Developers are hardly collaborating; during the Sprint, members are primarily working on their own items. You also notice that the items on the Sprint Backlog are mostly unrelated. You suspect that the lack of a Sprint Goal might be the cause.
Although you have encouraged the use of a Sprint Goal, both the Product Owner and the Developers have concluded that they are unable to create Sprint Goals based on the wide variety of items on their Product Backlog.
What might explain why this Scrum Team is struggling to craft a Sprint Goal?
(choose all that apply)
Answer: A,B,E
Explanation:
Explanation
The possible explanations for why this Scrum Team is struggling to craft a Sprint Goal are B, D, and E.
B) The Sprints are too long. A four-week Sprint is the maximum duration allowed by the Scrum Guide, and it may not be suitable for complex and uncertain work that requires frequent feedback and adaptation. A shorter Sprint may help the Scrum Team to focus on a clear and coherent Sprint Goal that aligns with the Product Goal and delivers a valuable Increment.
D) The Product Owner is not communicating the Product Goal that they want to achieve in upcoming Sprints.
The Product Goal is a long-term objective for the Scrum Team that provides direction and purpose for their work. The Product Owner is responsible for communicating the Product Goal to the Developers and collaborating with them to create Sprint Goals that move them closer to the Product Goal. Without a clear Product Goal, the Scrum Team may lack a shared vision and end up working on unrelated items.
E) The Scrum Team is too big. The Scrum Guide recommends that the Scrum Team consists of 10 or fewer people, including the Scrum Master and the Product Owner. A larger team may have difficulties in collaborating effectively, self-organizing, and creating a meaningful Sprint Goal that reflects the collective commitment of the Developers. A smaller team may improve the communication, coordination, and cohesion among the Developers and help them to create and achieve a Sprint Goal.
References:
The Scrum Guide, section 2.3 (The Scrum Team), page 7
The Scrum Guide, section 3.1 (The Sprint), page 8
The Scrum Guide, section 3.3 (The Sprint Goal), page 9
The Scrum Guide, section 4.1 (The Product Backlog), page 11
The Scrum Master Learning Path, module 2 (The Scrum Framework), lesson 2 (The Sprint) and lesson 3 (The Sprint Goal)
NEW QUESTION # 258
True or False: During the Sprint Review of a scaled development effort, every Scrum Team should demonstrate its individual Increment separately.
Answer: A
Explanation:
Explanation
During the Sprint Review of a scaled development effort, the Scrum Teams should demonstrate the integrated Increment that they have collectively delivered, not their individual Increments separately. This ensures that the stakeholders can provide feedback on the value and quality of the product as a whole, and that the Scrum Teams can inspect their alignment and collaboration.
References:
Scrum Guide 2020, page 14: "The purpose of the Sprint Review is to inspect the outcome of the Sprint and determine future adaptations. The Scrum Team presents the results of their work to key stakeholders and progress toward the Product Goal is discussed." Nexus Guide 2020, page 7: "The Nexus Sprint Review is an event where appropriate stakeholders review the Integrated Increment that has been built throughout the Sprint by all Scrum Teams in a Nexus."
NEW QUESTION # 259
......
We guarantee that you can enjoy the premier certificate learning experience under our help with our PSM-II prep guide since we put a high value on the sustainable relationship with our customers. First of all we have fast delivery after your payment in 5-10 minutes, and we will transfer PSM-II guide torrent to you online, which mean that you are able to study as soon as possible to avoid a waste of time. Besides if you have any trouble coping with some technical and operational problems while using our PSM-II Exam Torrent, please contact us immediately and our 24 hours online services will spare no effort to help you solve the problem in no time. As a result what we can do is to create the most comfortable and reliable customer services of our PSM-II guide torrent to make sure you can be well-prepared for the coming exams.
Exam Dumps PSM-II Pdf: https://www.vcetorrent.com/PSM-II-valid-vce-torrent.html
BTW, DOWNLOAD part of VCETorrent PSM-II dumps from Cloud Storage: https://drive.google.com/open?id=1e5JFCl4q7Uc4KkGB_thJxQFTLu9BCR5X