| Section | Objectives |
|---|---|
| Topic 1: Risk Analysis | - Qualitative Risk Analysis - Quantitative Risk Analysis |
| Topic 2: Risk Monitoring and Control | - Risk Audits and Reviews - Risk Reporting and Communication |
| Topic 3: Risk Strategy and Planning | - Stakeholder Engagement in Risk - Risk Management Planning |
| Topic 4: Risk Response Planning | - Threat Response Strategies - Opportunity Response Strategies |
| Topic 5: Risk Identification | - Overall Project Risk Identification - Identifying Individual Risks |
很多人都認為要通過一些高難度的PMI-RMP認證考試是需要精通很多PMI專業知識。只有掌握很全面的IPMI知識的人才會有資格去報名參加的考試。其實現在有很多方法可以幫你彌補你的知識不足的,一樣能通過PMI-RMP認證考試,也許比那些專業知識相當全面的人花的時間和精力更少,正所謂條條大路通羅馬。
問題 #23
The project manager generates a monthly risk report for key stakeholders which documents high and medium risk items only. Where would the project manager find the list of recipients for the report?
答案:C
問題 #24
An agriculture government agency faces different challenges with farmers and landlords In implementing its ambitious growth strategy. The agency decided to establish an enterprise risk management unit to identify risks, analyze risks, and provide a handbook showing how to handle the surrounding uncertainty.
What should the risk management expert recommend the agency do first to identify risks and develop the handbook?
答案:D
解題說明:
According to the PMBOK Guide1, risk identification is the process of determining which risks may affect the project and documenting their characteristics. It involves the use of various techniques to gather information from different sources and perspectives, such as stakeholders, experts, historical data, assumptions, and environmental factors. Some of the common techniques for risk identification are meetings, facilitated workshops, interviews, brainstorming, checklists, questionnaires, SWOT analysis, and root cause analysis. These techniques help to elicit the knowledge and opinions of the participants, and to generate a comprehensive list of potential risks that can be further analyzed and prioritized. In this case, the risk management expert should recommend the agency to conduct meetings, facilitated workshops, and interviews with stakeholders to identify potential risks and develop the handbook. This will help to understand the context and objectives of the agency, the expectations and concerns of the farmers and landlords, the challenges and opportunities in the agriculture sector, and the possible sources and impacts of uncertainty.
The risk management expert can then use the information gathered from these techniques to create a risk register and a risk management plan, which can form the basis of the handbook. This is part of the Identify Risks process in the PMBOK Guide1. References: 1: A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Sixth Edition Engaging stakeholders through meetings, workshops, and interviews is crucial for risk identification, as it allows the agency to gather diverse perspectives and insights on potential risks. This approach is more effective than relying solely on standard tools or hiring an expert.
問題 #25
.
A project manager is identifying risks on a project and decides to use a risk checklist to gather historical data accumulated from similar projects. With several different historical project files to choose from, which two pieces of information should the project manager include in their risk checklist? (Choose two.)
答案:B,E
解題說明:
A risk checklist is a tool for identifying risks based on historical information and knowledge from similar projects. It is a list of potential risk sources or categories that can be used to prompt the project team to consider possible risks that may affect the project. A risk checklistshould include information that is relevant and useful for identifying risks, such as lessons learned from similar completed projects and previous project risks that may be relevant to this project. These two pieces of information can help the project manager to learn from past experiences and avoid repeating the same mistakes or overlooking the same threats or opportunities. A risk checklist should not include information that is not directly related to risk identification, such as budget variance data from previously completed projects, project scope and cost management plans from previous projects, or stakeholder analysis metrics from projects with similar risk profiles. These pieces of information may be useful for other aspects of project management, such as planning, monitoring, or controlling, but they are not helpful for identifying risks on a project. References: PMI. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - Sixth Edition. Chapter 11: Project Risk Management, p. 397. 5 Lessons learned and previous project risks are valuable sources of information for creating a risk checklist.
They provide insights into potential risks that may impact the current project and help the project manager develop appropriate risk responses. Budget variance data, project scope and cost management plans, and stakeholder analysis metrics, although useful, are not directly related to risk identification. (Reference: Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - Sixth Edition, Section 11.2)
問題 #26
In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk.
What should the risk manager do?
答案:B
解題說明:
Decision tree analysis is a technique that uses a graphical representation of various possible outcomes and consequences of different courses of action, based on their probabilities of occurrence and associated payoffs or costs. It can help the project team to compare and evaluate the alternatives and choose the optimal one. In this case, the risk manager should use decision tree analysis to help the team members predict the outcomes of their potential choices following their probability of occurrence. Political, economic, social, technological, legal, and environmental (PESTLE) analysis, strengths, weaknesses, opportunities, and threats (SWOT) analysis, and cost-benefit analysis are not techniques that can directly help the team members to predict the outcomes of their potential choices following their probability of occurrence, and are therefore not the best answer. Reference: PMI Risk Management Professional (PMI-RMP)Exam Content Outline1, PMI Practice Standard for Project Risk Management2, Risk Management Professional (PMI-RMP)Cert Guide3
問題 #27
A risk management professional is in the process of categorizing risks when a subject matter expert (SME) suggests categorizing the risks by their impact to the project objectives. Why should the risk management professional use this approach?
答案:A
解題說明:
Categorizing risks by their impact on project objectives ensures that risk response plans are aligned with project priorities. This helps in focusing on the most critical risks and their potential impact on the project's success.
Categorizing risks by their impact to the project objectives is a way of aligning the risk management process with the project goals and stakeholder expectations. By doing so, the risk management professional can ensure that the risk response plans are focused on the most critical aspects of the project and that the project priorities are being considered in the decision making. This approach can also help to communicate the value of risk management to the project team and the stakeholders, as they can see how the risk management activities are contributing to the project success. Categorizing risks by their impact to the project objectives does not necessarily help to identify the specific causes of risks, determine the level of project leadership and organizational involvement, or assign risks and risk severities to functional disciplines and departments. These are other possible ways of categorizing risks, but they are not the main purpose of using the impact to the project objectives approach. References: PMI-RMP Certification Handbook1, page 9; PMBOK Guide, page 415.
問題 #28
......
PMI PMI-RMP 認證作為全球IT領域專家 PMI 熱門認證之一,是許多大中IT企業選擇人才標準的必備條件。PMI PMI-RMP 考題由全球領先的IT認證考試中心授權,幫助考生一次性順利取得通過 PMI-RMP 考試;否則將全額退費,這一舉動保證考生權利不受任何的損失。考生考試前需要在全球的Prometric考試中心進行報名並預約考試時間。
PMI-RMP指南: https://www.vcesoft.com/PMI-RMP-pdf.html
2026 VCESoft最新的PMI-RMP PDF版考試題庫和PMI-RMP考試問題和答案免費分享:https://drive.google.com/open?id=1-2qvg-72PPcQucQaEUAJGwOAnrEzc9N3