What's more, part of that Exam4Tests CCM dumps now are free: https://drive.google.com/open?id=1Z6pqeejLvlvy3pFahjf-ryEZM-tCXooS
We are proud that our Medical Professional CCM exam preparation material is one of the best in the market. You should buy our Certified Case Manager Certification Exam (CCM) (CCM) valid dumps and start preparation now because of some amazing offers. These offers are up to 1 year of Free CCM Dumps updates, free demos of our CCM exam product, and a full refund guarantee. What are you waiting for? Buy actual Medical Professional CCM now at discount and start your preparation.
| Section | Weight | Objectives |
|---|---|---|
| Quality and Outcomes Evaluation and Measurements | 10% | - Outcome measurement and analysis - Data collection and reporting - Cost-benefit and effectiveness analysis - Accreditation and regulatory standards - Performance improvement |
| Ethics, Legal, and Practice Standards | 18% | - Legal and regulatory requirements - Confidentiality and privacy - Advocacy and patient rights - Professional ethics and conduct - Scope of practice and roles |
| Healthcare Delivery Systems and Community Resources | 10% | - Continuum of care settings - Interdisciplinary collaboration - Community-based services and resources - Healthcare policy and systems |
| Psychosocial Concepts and Support Systems | 20% | - Abuse and neglect recognition - Behavioral change theories and models - Family dynamics and support systems - Mental health and substance use considerations - Cultural competence and diversity |
| Reimbursement Methods | 12% | - Coding and utilization review principles - Managed care and accountable care concepts - Financial resources and negotiation - Payment and reimbursement methodologies - Insurance principles and benefit structures |
| Care Management | 30% | - Caseload assignment and selection criteria - Age-specific care application - Cost containment principles - Care coordination and collaboration - Medication management - Evidence-based case management models and tools - Client-centered care plan development |
>> CCM Sample Questions Pdf <<
Exam4Tests, as a provider, specializing in providing all candidates with CCM exam-related materials, focus on offering the most excellent dumps for the candidates. In contrast with other websites, Exam4Tests is more trustworthy. Why? Because Exam4Tests has many years of experience and our Medical Professional experts have been devoted themselves to the study of Medical Professional certification exam and summarize CCM Exam rules. Thus, Exam4Tests exam dumps have a high hit rate. Meanwhile, it guarantees the qualification rate in the exam. Therefore, Exam4Tests got everyone's trust.
NEW QUESTION # 127
Which of the following FIDIC contract forms require certification in the payment process? (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
Answer: B,C
Explanation:
Options A and B are correct: Both the Red and Yellow Books require the Engineer to certify payments before the Employer pays the Contractor.
Option C (Silver Book) typically places the risk on the Contractor and often provides for payment without Engineer certification, reflecting the turnkey nature of the contract.
References:
FIDIC Red and Yellow Books 1999 & 2017 Editions, Clauses on Payment Certification FIDIC Silver Book 1999 & 2017 Editions - Payment Provisions FIDIC Contract Manager Study Guide, Module on Payment Procedures
NEW QUESTION # 128
Which two statements are correct regarding the FIDIC Red Book (edition 2017)?
Answer: A,D
Explanation:
Option B is correct: The Contract Data provides information required by specific Sub-Clauses in the General Conditions to complete the contract.
Option D is correct: If required data is missing in the Contract Data, some Sub-Clauses may not apply.
Option A is incorrect; definitions generally apply throughout the contract including Specifications and Drawings.
Option C is incorrect; case sensitivity of terms can affect contractual meaning.
References:
FIDIC Red Book 2017 Edition, Sub-Clause 1.1 - Definitions and Contract Data FIDIC Contract Manager Study Guide, Module on Contract Documents
NEW QUESTION # 129
You are the Contract Manager of the Engineer in a hotel project. In May 2020, the Employer and the Contractor signed a Contract based on the FIDIC Yellow Book (edition 2017), as per which the Contractor will design and build a hotel project with Contract Price of 5,100,000 USD. The Time for Completion for this project is 12 months (May 2021). The Contract also named a nominated Subcontractor (as referred to in Sub- Clause 4.5) who provides mechanical, electrical, and plumbing services for the project (including the fire fighting system), which was accepted by the Contractor without any discussions.
The Project was delayed due to issues with the fire fighting system, and you issued the Taking-Over Certificate in June 2022.
The Employer sent a Notice of Claim to the Contractor on Delay Damages with a maximum value equal to
10% of Contract Price (510,000 USD). The Employer also gave a Notice to the Contractor stating that the Contractor has failed to submit the evidence of payment to the nominated Subcontractor as well as the reason for withholding payment to the nominated Subcontractor. Therefore, the Employer has paid the nominated Subcontractor directly the entire amount due, coming to 100,000 USD. The Employer intends to include this amount as a deduction in the Final Payment to the Contractor.
As Contract Manager of the Engineer, you are tasked to make a fair determination of the Notices of the Employer. In your "Notice of the Engineer's determination", what is your determination for the deduction of the next Interim Payment to the Contractor in relation to the amount directly paid to the nominated Subcontractor?
Answer: A
Explanation:
Comprehensive and Detailed Explanation:
According to FIDIC Yellow Book 2017, Sub-Clause 4.5, the Employer has the right to pay a nominated Subcontractor directly if the Contractor fails to do so and can deduct the amount from payments due to the Contractor. This provision protects nominated Subcontractors and ensures payment continuity. The Contractor's failure to provide evidence of payment and justification for withholding payment justifies the Employer's direct payment and deduction.
Thus, the Engineer's determination should allow the Employer to deduct the 100,000 USD paid directly to the nominated Subcontractor from the Contractor's next Interim Payment, ensuring fairness and contract compliance.
References:
FIDIC Yellow Book 2017 Edition, Sub-Clause 4.5 - Nominated Subcontractors FIDIC Contract Manager Study Guide, Module on Claims and Payment Procedures
NEW QUESTION # 130
Regarding the FIDIC Red Book (edition 1999), which two statements are true?
Answer: B,C
Explanation:
Comprehensive and Detailed Explanation:
Option A is true: In emergencies, verbal notices are permitted with the requirement to follow up in writing.
Option D is true: Notices and communications may be sent in various formats including handwritten, typed, printed, or electronic systems.
Option B is incorrect; a notice does not necessarily have to be signed by all these representatives; it depends on the party issuing the notice.
Option C is incorrect; proof of receipt is ideal but not always strictly required for legal validity depending on contract provisions.
References:
FIDIC Red Book 1999 Edition, Sub-Clause 1.3 - Communications and Notices FIDIC Contract Manager Study Guide, Module on Contract Communication
NEW QUESTION # 131
Which of the following obligations are relevant to the Engineer's roles with regards to insurance? [2017 Edition] (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
Answer: B,D
Explanation:
Comprehensive and Detailed Explanation:
Option A is correct: The Engineer is entitled to receive evidence that the Contractor has paid for the necessary insurance policies.
Option C is correct: The Engineer has the role of monitoring the validity of these insurances and ensuring that renewals or extensions are arranged in a timely manner.
Option B is incorrect; the Engineer does not have the authority to take out insurance on behalf of the Contractor.
Option D is incorrect; suspension of construction activities is not automatically the Engineer's role for insurance lapses but may require instructions from the Employer.
References:
FIDIC Red, Yellow, Silver Books 2017 Edition, Sub-Clause 18 - Insurances FIDIC Contract Manager Study Guide, Module on Contract Administration and Insurance
NEW QUESTION # 132
......
If you are a workman and you want to pass CCM exam quickly, Exam4Tests will be your best choice. CCM dumps and answers from our Exam4Tests site are all created by the IT talents with more than 10-year experience in IT certification. It can not only save your time, but also help you pass the CCM Exam easily.
CCM High Passing Score: https://www.exam4tests.com/CCM-valid-braindumps.html
What's more, part of that Exam4Tests CCM dumps now are free: https://drive.google.com/open?id=1Z6pqeejLvlvy3pFahjf-ryEZM-tCXooS