Scrum SMC 是一個專業知識和技能的認證考試。在IT行業中找工作,很多人力資源經理在面試時會參考你有哪些Scrum相關的I認證證書。如果你擁有Scrum SMC認證證書,顯然可以提高你的競爭力。
| Section | Objectives |
|---|---|
| Topic 1: Scrum Overview | - Definition and History of Scrum - Why Scrum - Scrum vs Traditional Project Management - Benefits of Scrum |
| Topic 2: Scrum Artifacts | - Definition of Done - Product Backlog - Increment - Sprint Backlog |
| Topic 3: Agile Overview | - Agile Methods - Agile Principles - Benefits of Agile - Agile Manifesto |
| Topic 4: Scrum Roles | - Scrum Team - Product Owner - Scrum Master |
| Topic 5: Facilitation and Servant Leadership | - Removing Impediments - Conflict Resolution - Facilitating Scrum Activities - Coaching and Mentoring Teams |
| Topic 6: Scrum Events | - Daily Stand-up - Sprint Review - Sprint Planning Meeting - Sprint Retrospective |
| Topic 7: Scrum Phases and Processes | - Review and Retrospect - Release - Plan and Estimate - Initiate - Implement |
我們都清楚的知道,IT行業是個新型產業,它是帶動經濟發展的鏈條之一,所以它的地位也是舉足輕重不可忽視的。IT認證又是IT行業裏競爭的手段之一,通過了認證你的各方面將會得到很好的上升,但是想要通過並非易事,所以建議你利用一下培訓工具,如果要選擇通過這項認證的培訓資源,NewDumps Scrum的SMC考試培訓資料當仁不讓,它的成功率高達100%,能夠保證你通過考試。
問題 #92
While assisting the Product Owner in developing a Prioritized Product Backlog, the Scrum Master must consider the primary factors on which the Prioritized Product Backlog is based-on. Which of the following are those primary factors?
A) Value
B) Dependencies
C) Risk
D) Deliverables
答案:D
解題說明:
The Prioritized Product Backlog contains a prioritized list of business and project requirements written in the form of Epic(s), which are high level User Stories. The Prioritized Product Backlog is based on three primary factors: value, risk or uncertainty, and dependencies. It is also referred to as the Risk Adjusted Product Backlog since it includes identified and assessed risks related to the project.
問題 #93
Beth is a Scrum Master over a newly formed team. What can Beth expect as the team matures in the project?
答案:A
問題 #94
Damage to life and property due to floods and landslides has been identified as a potential risk on a hydroelectric power project. Which of the following Risk Assessment Techniques can the Scrum Team employ to evaluate potential risks and their impact on project objectives?
答案:B
解題說明:
A Probability Impact Grid evaluates each identified risk according to two primary dimensions: its probability of occurrence and its potential impact on project objectives. SBOK explains that each dimension may be assigned a numerical or categorical rating and that probability and impact can then be combined to derive a risk-severity score.
That makes the technique particularly appropriate for the flood-and-landslide scenario. The team can estimate how likely these events are and assess the severity of their consequences for safety, cost, schedule, infrastructure, or environmental objectives. The resulting score helps determine prioritization and the urgency of mitigation.
Probability Trees model multiple possible outcomes as branches and calculate associated expected values.
Pareto Analysis ranks identified risks by magnitude to focus attention on the most significant contributors.
Expected Monetary Value converts uncertainty into a financial expectation by multiplying monetary impact by probability.
All four can support risk analysis, but the question specifically emphasizes evaluating probability and impact on project objectives, which directly matches the Probability Impact Grid.
Study Guide reference: Risk - > Risk Assessment - > Probability Impact Grid.
========
問題 #95
Gregory is the Scrum Master on a project to create automated devices for the health industry. He advocates that every member of the Scrum Team should actively participate in team building activities, estimation meetings, and in Daily Standups. He looks to give more responsibility to team members. Which of the following theories does Gregory seem to subscribe to?
答案:C
解題說明:
Reference:
https://medium.com/serious-scrum/we-dont-let-the-teams-self-organise-fd27807d8e15
問題 #96
Which of the following best defines the team velocity metric used to measure team performance?
答案:C
解題說明:
Velocity measures how many user stories were completed by the team, on average, in previous sprints. It assists in estimating how much work the team is able to accomplish in future sprints.